Transcript Slide 1
Westar Energy’s 2013 Annual Transmission Revenue Requirement Meeting October 30, 2012 1 Today • Status Report: Transmission Projects • Quick Review of the Past • The Results: 2013 ATRR • What Do These Results Mean to Our Customers? • Protocol Review • Meter Cost Recovery Policy 2 2007 2008 2009 2010 2011 2012 2013 2014 3 Transmission Investment 350 260 300 Millions $ 250 210 200 200 150 160 2008 2009 165 145 150 100 70 50 0 2007 2010 2011 2012 Projected 4 2013 2014 Projected Projected Future Projects in the Southwest Power Pool 5 Quick Review: The Formula • • Gross Revenue Requirement (GRR) includes: • • • • • Projected Transmission Plant In-Service Projected Transmission O&M Projected Transmission Depreciation Expense Taxes Return Net Revenue Requirement adjusts the GRR for: • • • Revenue Credits received for Point-to-Point Transmission Service “Rent” received (i.e. pole attachments) True-Up for prior year’s difference between actual and projected, including interest 6 Quick Review: The Past • 2009 was the first ATRR that included the forwardlooking, revised formula • History of true-up adjustments: • • • • -$17.8 M was applied in the 2011 ATRR, for 2009 business $4.5 M was applied in the 2012 ATRR, for 2010 business -$9.8 M will be applied in the 2013 ATRR, for 2011 business Key aspect of true-up amounts: O&M • • The TFR calculates a projected O&M based on the percentage increase in Transmission Plant times the actual O&M from the previous actual year This function of projecting O&M is part of the FERCapproved TFR 7 The Results: ATRR for 2013 Westar’s Gross Rev. Requirement $230,234,224 Revenue Credits ($ 22,198,015) True-Up from 2011 ($ 9,786,991) Westar’s Net Rev. Requirement $198,249,218 SPP’s BPF Rev. Requirement* ($ 64,795,034) SPP Zonal Rev. Requirement** $133,454,184 * Funds collected under Schedule 11 ** Resulting rates go into effect with January 1, 2013, business 8 The Results: What Does this Mean to You? Example of a Customer’s Estimated Transmission Costs, 2012 vs. 2013 Customer’s 2011 Load Ratio Share .00475 2012 Westar Zonal Rev. Req., plus SPP Schedule 11* $182,198,978 Customer’s Annual Transmission Service Charge (before Ancillary Services and Fees) $ Customer’s 2012 Load Ratio Share 865,445 .00475 2013 Westar Zonal Rev. Req., plus SPP Schedule 11* Customer’s Estimated Annual Transmission Charge (before Ancillary Services and Fees) Estimated Difference $183,038,901 $ 869,434 + .46% * Includes Westar’s respective Zonal ATRR plus the most recent information posted in Attachment H of SPP’s OATT; amounts in Attachment H vary throughout the year, depending on activities of other TOs in SPP 9 Formula Protocols: Annual Update • Today: October 30, 2012 • Comments and questions are preferred by November 20, 2012, so we can review and revise the ATRR if necessary • If necessary, revised ATRR will be posted by November 30, 2012 • Send comments or questions via e-mail to: – Sheila Gropp at [email protected] – Please cc: [email protected] and [email protected] • SAVE THE DATE FOR THE 2012 TRUE-UP MEETING: June 25, 2013 10 Meter Cost Recovery Policy • Purpose: To assure fair, consistent treatment of all Transmission Customers for meter-related costs • Key Aspects: – Outlines recoverable capital expenses: • • • • New meter points Failed equipment Upgrades (requested by TC) Back-up meter points – Outlines recoverable O&M expenses • Meter service fee • TBD and filed with FERC before charged • Effective Date: September 1, 2012 11 Questions? 12