(1) ESA Review Objectives

Download Report

Transcript (1) ESA Review Objectives

ggonzale:
ggonzale:
Herschel/Planck
Herschel PACS
Instrument Qualification Review
Review Objectives
and
Organisation
G.Crone/G.Pilbratt Herschel/Planck Project
January 13, 2005
PACS IQR - SCI-PT/33202
1
Herschel/Planck
Instruments Review Cycles in Perspective
Spacecraft
ITT
SRR
PDR
CDR
Phase B
Instruments: ISVR
1999
2000
January 13, 2005
IIDR
2001
…
Phase C/D
IBDR
2002
2003
…
IQR
IHDR
2004
PACS IQR - SCI-PT/33202
Launch
2005
IFAR
2006
2007
2
Herschel/Planck
From Qualification to Flight Acceptance
• CQM at module (EQM) level :
Delivery (DRB)  Test readiness (TRR)  Test review (PTR) 2005
After CQM System Campaign hold a Instrument Status Review
• FM at instrument level:
ILT TRR  ILTs  ILT Test review prior to warm-up (PTR)
2005
To decide on need for further tests or to terminate & deliver
• FM at module (PLM) and system level:
Delivery (DRB)  Test readiness (TRR)  Test review (PTR)
In preparation of FAR Instrument Status Review
January 13, 2005
PACS IQR - SCI-PT/33202
2006
3
Herschel/Planck
Herschel Status
• Herschel Payload Module CDR completed in July and Space Segment
CDR completed in October with official close-out end 2004
• Herschel EQM - Ready for Herschel CQM Focal Plane Units.
• All Herschel Instruments: HIFI, PACS and SPIRE have successfully
completed CQM Instrument Level Tests.
• All instruments delivered and in ASED OTN. (N.B. SPIRE to be
returned 17th January)
• Instrument testing to commence April 2005
• Instrument FM program underway – Baseline delivery Nov 2005
January 13, 2005
PACS IQR - SCI-PT/33202
4
Herschel/Planck
Herschel EQM
January 13, 2005
PACS IQR - SCI-PT/33202
5
Herschel/Planck
Herschel PFM status
•
All units passed CDR, manufacturing well
underway
•
Optical bench delivered
•
HTT delivered, most cryo-components,
instrumentation, MLI integrated
•
HOT delivered instrumentation, cryocomponents and MLI mounted. Tank
integrated on framework.
Both fully integrated
•
Cylinder thermal shields delivered-Others
completed
•
CVV cylinder delivered-Upper and lower
bulk head imminent.
•
Integration to be completed by May 2005;
first cool-down with MTD instrument prior
to shipment to ESTEC for STM campaign
January 13, 2005
PACS IQR - SCI-PT/33202
6
Herschel/Planck
Instrument Qualification Review - Objectives
Ref: IQR Proceedings - v2 Aug 26, 2004 - SCI-PT/27108
 Confirmation of instrument CQM hardware/software qualification
 Completion of instrument design verification
 Assessment of performance and compliance with sci. reqs
 Identification and confirmation of improvements for FM
 Completion of OBSW design and demonstration of functionality
 Confirmation of EGSE design and demonstration of functionality
 Confirmation of instrument operability - User Manual
January 13, 2005
PACS IQR - SCI-PT/33202
7
Herschel/Planck
IQR - Proceedings
Data Package – complete delivery at K.O. [PACS]
Documents as identified in SCI-PT/27108
 Presentations as given during the K.O. meeting

Review of Data Package [Board]
Discrepancies and open issues raised as RIDs
 RIDs issued up to one week before co-location

Answers to RIDs [PACS]

Provided, discussed and resolved at co-location
Board Report = Result of the three items above [Board]
January 13, 2005
PACS IQR - SCI-PT/33202
8
Herschel/Planck
IQR Timeline
K.O. Meeting and Data Pack
today
Preliminary feedback
18 Jan 2005
Issue of RIDs
02 Feb 2005
Co-location
Issue of Board Report
January 13, 2005
10-11 Feb 2005
25 Feb 2005
PACS IQR - SCI-PT/33202
9
Herschel/Planck
Review Board / Representatives of third parties
Herschel/Planck Project
(ESTEC)
G. Crone (chair)
G. Pilbratt (co-chair)
A. Heske (secretary)
P. Estaria
J. Rautakoski
F. Pedersen
T. van der Laan
Industry Representative
G. Doubrovik (Alcatel)
January 13, 2005
SPIRE Representative
B. Swinyard (RAL)
Funding Agency Representatives
M. Falvella (ASI)
K. Mercier (CNES)
K. Proetel (DLR)
H. Schroeven-Deceuninck (Prodex)
Experts
D. Schink (Astrium)
B. Collaudin (Alcatel)
G. Coe (ESTEC)
F. Marliani (ESTEC)
PACS IQR - SCI-PT/33202
10
Herschel/Planck
PACS IQR K.O. - Agenda
09:00
09:05
09:15
09:45
11:45
12:15
Welcome
Review Organization and Objectives
Introduction – IHDR close-out and docs
Instrument Qualification Status and plans for PFM
Mechanical, Thermal, Electrical I/Fs and EMC, Optical
PhFPU Qualification and plans for PFM
Ge:Ga detector arrays Qualification
with Coffee Break at 11:00
12:45
13:45
14:15
14:25
15:30
15:40
15:55
16:15
16:30
17:00
MPE
ESA
MPE
MPE
CEA
MPE
Lunch
On-Board Software and UM
EGSE, I-EGSE and MIB
CQM/AVM ILT Results
PA/QA Status
Management and Schedule
Critical Items and next steps
Lessons learnt from CQM Integration in Industry
Questions and Clarifications
First Impressions and Feedback
with Coffee Break at 15:15
January 13, 2005
PACS IQR - SCI-PT/33202
MPE
MPE
MPE
MPE
MPE
MPE
MPE
All
ESA
11