Transcript Network Analysis - Staffordshire University
Network Analysis
01/05/2020
BCI Lecture 9b
Peter Considine Staffordshire University Business School 1
Network Analysis
• • •
Involves:
– Critical path analysis (CPA) – Project evaluation & review (PERT)
Used:
– When consecutive actives must be planned
Allows projection of:
– Duration of the project – Delays to estimated completion date 01/05/2020 Peter Considine Staffordshire University Business School 2
Features LFT
•
Nodes EST LFT
– Numbered to the left of a circle – Symbolise start & finish of an activity – Consecutive activities go on the same line – Simultaneous activities on in the same column – Right side – top – earliest start time – Right side – bottom – latest finish time 01/05/2020 Peter Considine Staffordshire University Business School 3
Earliest Start Time
•
Earliest that the next activity can be started
– E.G. At stage 5, the next activity can start on day 4 at the earliest
4
5
01/05/2020 Peter Considine Staffordshire University Business School 4
Latest Finishing Time
•
Latest date by which the previous activity must be finished if completion date is to be met
– E.G. Everything must be ready for stage 7 by day 21 or the whole Project will be late
7
21
01/05/2020 Peter Considine Staffordshire University Business School 5
Activities
• •
Labelled using letters (A, B, C …) Duration is usually given
– E.G. Activity A takes 2 days starting at stage 1
1
0 0
A, 2
2
2
01/05/2020 Peter Considine Staffordshire University Business School 6
Schedule
01/05/2020
Activity Duration Preceding activity A B C D E F G 2 3 5 2 4 2 2 A A B C C D, E
Peter Considine Staffordshire University Business School 7
Task Analysis
• • • •
Add activity duration to previous EST Choose highest number when simultaneous activities occur Arrive at estimated completion day Calculate LFT by tracing backwards
– Deduct activity time from preceding LFT – Choose lowest number when simultaneous activities occur 01/05/2020 Peter Considine Staffordshire University Business School 8
Example Network
B,3
1
0
0 A2
2
2
2 C,5
3
5
9 D,2
4
7
7 E,4 F,2
5
11
11 G,2
6
13
13 01/05/2020 Peter Considine Staffordshire University Business School 9
Critical Path Analysis (CPA)
• •
Sequence of critical activities
– If any of these are delayed, then project will be late
Path through all points where EST=LFT
– Must start & finish exactly as planned – Others are non-critical • May overrun/delayed, without affecting completion date, but should not be ignored 01/05/2020 Peter Considine Staffordshire University Business School 10
Float
• • • •
Extent of delay/overrun allowable without extending total duration time Total float = LFT-EST But, delay/overrun in one activity alters EST of another – knock-on effect ‘Free float’ (FF)
– Allocation of float between activities – FF=EST (next activity)-activity duration-EST activity 01/05/2020 Peter Considine Staffordshire University Business School 11
Management
• •
If ‘free float’ = nil, then that activity cannot actually be delayed/overrun, even if EST
– Ensures that the project will be completed on time
If ‘free float’ exists, then labour & equipment is idle and can be re-allocated to other projects & activities
– Reduces cost and/or completion time 01/05/2020 Peter Considine Staffordshire University Business School 12
P.E.R.T.
•
Identify all activities
– Sequence them – Estimate their timings – Construct a diagram representing the above – Evaluate the network & identify the critical path (schedule) – Monitor actual performance of project against the schedule – Draw activities across a time horizon (Gantt chart) 01/05/2020 Peter Considine Staffordshire University Business School 13
Gantt Charts
• • •
Used to display the schedule over time time
– Horizontal bar chart – Float becomes explicit
Plot critical path first Then others using EST
– Creates labour/resource histogram • Shows idle resources 01/05/2020 Peter Considine Staffordshire University Business School 14
CPA Changes
•
New activity leads to new critical path
– New time critical set of activities – Iterative – Identifies the most risky & time threatening activities 01/05/2020 Peter Considine Staffordshire University Business School 15
Further Readings
•
MEREDITH, J.R. & MANTEL, S.J. 2002.
Project Management: a managerial
approach. John Wiley.
01/05/2020 Peter Considine Staffordshire University Business School 16