South Frontage Road
Download
Report
Transcript South Frontage Road
2014 Construction Plans
Jon Chiglo, PE
Project Director
Tentative 2014 Construction Timeline
Access to businesses and residences
Local access will remain during business
hours and at all times to residences.
- Business signage
- Detour signage
- Temporary gravel roads
2014 Minn. Approach Work
Contracted Maximum Impacts
• North Frontage Road—50 calendar days
• Osgood Avenue—40 calendar days
• Greeley Street—40 calendar days
• Oakgreen Avenue—25 calendar days
• South Frontage Road—70 calendar days
Highway 36
• Single-lane in each direction – Open AT ALL TIMES
• Work: Resurface road
• Westbound: Spring to mid-summer 2014(red)
• Eastbound: Mid-summer to fall 2014(green)
South Frontage Road – East of Osgood
•
•
•
•
Closed to through traffic
Local access to businesses and residences
Work: Resurface road, replace public utilities
Spring to mid-summer 2014 (red)
Hwy 95 / Lookout Trail / Sunnyside
• Hwy 95
• Single-lane in each direction
• Work: Construct 4-lane road
• Spring to mid-summer 2014 (red)
• Lookout Trail
• Work: Reconstruct access to Hwy 95
to right in/out intersection
• Spring to mid-summer 2014
• Sunnyside Marina
• Work: Reconstruct driveway
• Spring to mid-summer 2014
North Frontage Road
• North Frontage Road –
Northwestern to Greeley
• Possible detours to access
North Frontage Road.
• Work: Resurface road, add
turn lane, add curb &
gutter
• Spring to mid-summer
2014 (red)
North Frontage Road
• North Frontage Road – Greeley to Osgood
• Possible detours to access North Frontage Road, either from
Greeley St. or Osgood Ave.
• Permanent closure of right in/out connection to Hwy 36
• Work: Resurface road, add turn lane, add curb & gutter
• Spring to mid-summer 2014 (red)
Greeley St./Oakgreen Ave. Intersection
• North/south traffic closed for
2 periods of 6 calendar days each
• Oakgreen—Closed between S.
Frontage Road and 58th St./Oak
Park Blvd. for 25 days. Local
residential access only. (green)
• Work: Build new frontage road
system further away from Hwy 36;
shift intersection to the east; install
three traffic signal systems; add
double left turn lanes
Osgood Ave. Intersection
• North/south traffic closed for 2
periods of 6 calendar days each
• Work: Add double left turn lanes,
resurface intersection
• Osgood intersection and
Greeley-Oakgreen intersection
WILL NOT close at the same time
Final Hwy 36 Intersections Looking East
S. Frontage Road – Oakgreen to Osgood
• Possible detours/temporary roads to access
businesses/residences
• Work: Resurface road, add turn lane, add curb & gutter,
replace public utilities
• Late summer to fall 2014 (blue)
Trail Construction
• Work: Construct pedestrian/bicycle trails
• Occurs as time allows, complete in fall 2014
Other area county/city projects
Wisconsin Approach Work
Work occurs: March 2014-late summer 2016
Goal: Open WIS 64 at the same time as the new bridge
2014 Wisc. Approach Work
• Grade from the bluff to
County Road E
• Build the WIS 35
overpass over the new
WIS 64
2014-2017 Wisc. Approach Schedule
The New St. Croix Crossing
Bridge Superstructure
• Timeline: Dec. 2013 to late-summer/early fall 2016
• Winter/Spring 2014 Impacts: Pile driving on the
Minnesota shoreline and work on Pier 8
• Through May
• 6 days per week -- 7 a.m.-7 p.m.
• Goal: As much work done as possible while
windows are closed
Minnesota Land Piers Work Progress
2014 Bridge Construction
• Build all river piers and land piers vertically
(Piers 1-13)
2014 Bridge Construction
• Begin casting segments – Approx. 1,000
• 656 extradosed segments
• 330 approach segments
• Two casting yard locations -- Gray Cloud Island and
at the Hwy 36/95 interchange
• Place first segment in fall 2014
River Bridge Construction Staging
Segment Lifter Example
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Construction Sequence
Contact Information
Hotline
1-855-GO-CROIX (462-7649)
Email
[email protected]
Website/Regular project updates
www.mndot.gov/stcroixcrossing
Facebook
www.facebook.com/saintcroixcrossingmndot
Twitter
@stcroixcrossing
Questions?