Termination Provisions - Allen & Overy Seminars > What`s new?
Download
Report
Transcript Termination Provisions - Allen & Overy Seminars > What`s new?
How do we get out of this? Terminating
contracts in a time of financial crisis.
Andrew Denny, Partner and Richard Farnhill,
Senior Associate
Allen & Overy LLP
The three regimes
Common law: repudiatory breaches
Conditions precedent
The termination provisions in your contract
LT:3995898
Common law
Some myths
You can always terminate for breach
If you do not terminate for breach, you cannot
recover damages, either
Damages for breach are always calculated the
same way
LT:3995898
Common law
Two separate issues
Breach
Failure to perform a term or terms of the contract
Remedy – damages for losses caused by breach of
the clause or clauses
Repudiation
Manifesting an intention not to be bound
Remedy – option to terminate prospectively and claim
damages for loss of the contract
“Anticipatory breach” is not a case of breach at all
but, rather, of repudiation
LT:3995898
Common law
The risk of wrongful termination
Wrongful termination is, itself, a repudiatory breach
For example
A has a loan facility with B Bank
B Bank is in difficulty and it seems certain that it will be
unable to transfer funds on time
Bridging finance will cost A £1m
A replacement facility will cost A £15m
B Bank’s profit on the facility is £20m
If A sues on the breach alone he recovers £1m
If A terminates with cause he recovers £15m
If A terminates wrongfully, B Bank can sue for £19m
LT:3995898
Common law
The first step – classification of terms
Condition
Warranty
Innominate terms
The types of repudiatory breach
Breach of condition
Serious breach of innominate terms
Repeated other breaches in exceptional cases
LT:3995898
Conditions precedent
Different regime
Specified obligations do not take effect
Generally, no damages
LT:3995898
Termination Provisions
Two types of express termination clauses:
a) Failed performance (“Events of Default”)
b) Circumstantial events (“Termination Events”)
LT:3995898
Termination Provisions
a) Express provisions for failure to perform
LT:3995898
ISDA Master Agreement 2002 Clause 5(a) defines
an “Event of Default”, e.g. “failure to pay or deliver”
Clause 6 states what happens if an Event of
Default occurs – right to specify Early Termination
Date
Termination Provisions
Frequently asked questions
Do I have to give notice or can I terminate
immediately?
Can I terminate for breach even if the breach is
trivial?
What is a “material” or a “substantial” breach?
Can I still claim damages if I terminate?
LT:3995898
Termination Provisions
Do I have to give notice before terminating?
Will depend on wording of contract
Generally:
Notice often not required if breach cannot be
remedied
If can be fixed, usually have to give chance to do
so – failure to rectify following notice adds to
seriousness of breach
LT:3995898
Termination Provisions
Can I terminate for breach even if the breach is
trivial?
Garden Guardian case: a cautionary tale
Court rejected argument that “any breach” could
cause the right of termination to arise
Alan Auld Associates: repeated minor breaches can
be repudiatory if they deprive the innocent party of
substantially the whole benefit of the contract
LT:3995898
Termination Provisions
What about contractual freedom?
c.f. ISDA 2002 Master:
Clause 5(a)(i) – failure to pay or deliver
Clause 5(a)(ii)(1) – failure to comply with “any
agreement or obligation”
LT:3995898
Termination Provisions
What is a “material” breach?
Not the same as a repudiatory breach
National Power – remediable breach likely to have
serious effect on counterparty if not rectified
Dalkia Utilities – look at nature of breach – failure to
pay three monthly instalments (out of 173) in a row
was material
Why does “any breach” have to be a repudiatory
breach while a “material breach” does not?
LT:3995898
Termination Provisions
What is a “substantial” breach?
Crane Co v Wittemborg – essentially the same as
repudiatory breach
So why is “substantial” any different from “material”?
Anticipatory breach was not a breach for the purpose
of this clause
LT:3995898
Termination Provisions
Can I still claim damages if I terminate?
Yes – but limited if breach is not also repudiatory:
Will recover loss suffered to date
Won’t get “loss of bargain” damages unless
contract specifically provides for it
LT:3995898
Termination Provisions
b) Contractual provisions for circumstantial events
LT:3995898
ISDA Master Agreement 2002, Clause 5(b) defines
“Termination Events”, e.g. illegality
Clause 6 sets out consequences - may give only one
party the right to terminate e.g. party who is not the
Affected Party (if only one Affected Party)
Termination Provisions
Would market turmoil constitute a “material adverse change”?
Check drafting
MAC clauses narrowly construed – WPP v Tempus
Reliance on a MAC clause can be perceived by the market
as a sign of weakness
Alternatives:
Specify events / economic indicators / target performance
to constitute a MAC
Texas Pacific Group relied on a termination right connected
to Bradford & Bingley’s debt ratings to walk away from
proposed £179m investment
LT:3995898
Termination Provisions
Drafting express termination clauses
Be specific re:
Breaches for which a party can terminate
What is meant by terms such as “material”,
“substantial”, or “material adverse change”
Steps that are required to terminate (e.g. notice)
Consequences of termination e.g. damages for loss
of bargain?
LT:3995898
Conclusions
Important points
Clearest to rely on an express termination clause, but take care if
you wish to preserve the full benefit of the contract damages
Keep in mind difference between breach of a condition and
condition precedent
Keep in mind the difference between breach and repudiation
For repeated small breaches, consider the cumulative position
LT:3995898