Transcript 0 - IAY
Indira Awaas Yojana Performance Review Committee 7th June, 2013 Salient features of IAY Guidelines • Unit assistance for construction of new house & housesite component enhanced (Cabinet decision - 10 Dec, 2012) • An Empowered Committee - oversee operationalisation of new guideline • Special projects from Reserve fund to be sanctioned by EC (5% of Annual th budget for scheme retained by MoRD) • Administrative expenses – 4% of funds released • Greater role for State in • Allocation of district wise targets • Distributing admin cost to districts • Identifying Difficult Areas • Habitation & Individual house approach for better coverage of target group • IT enabled Monitoring through AwaasSoft Allocation • Annual allocation for States/UTs based on existing formula ( 75% weight to houselessness & 25% weight to Poverty ratio) rationalised to achieve fair category wise distribution • Targets for SCs, STs and Minorities made in proportion to population of these categories in States/UT’s • Upto 20% of district allocation can be used for upgradation • Once SECC is finalised allocation would be based on houseless people from BPL population for each category Administrative Cost • District allocation to include two parts, – Fixed expenditure which would be same for all districts – Working expenses in proportion to the targets allotted • Formula for distribution to intermediate & Village Panchayats in accordance to workload assigned Distributed to districts in proportion to their targets in 2013-14. Eligible items of expenditure • • • • • IEC material on designs & technology options Construction of prototypes & models for demonstration Cost of hardware/software for MIS, data entry, photographs, quality supervision & monitoring Training of master masons, CRPs & NGOs, Elected representatives Honorarium to CRPs & service charges to NGOs etc. Convergence… with other schemes With Nirmal Bharat Abhiyan for construction of Sanitary toilet in IAY houses – IAY beneficiaries to be accorded priority – State/District Water and Sanitation Mission would be agency in charge – State Dept. in charge of MGNREGS to issue directions to GP’s on dovetailing MGNREGS funds with NBA funds – IAY Implementing agency to send progress reports to MoDW&S – Last installment of IAY & NBA funds to be released only after construction of toilet is completed – Letter on implementation jointly issued - uploaded on website State/ Implementing Agency should promote convergence with other schemes like RGGVY, RSBY,AABY etc. * Letter dated 16/5/2013 Use of AwaasSoft • Uploading Annual selection list before release of 1st installment • Registration of complete beneficiary details • Financial & Physical progress as reflected in AwaasSoft would be considered for all purposes • All transaction have to be done through AwaasSoft • Use of AwaasSoft reports for monitoring • Regular uploading of photos every quarter • Follow up till completion Progress of MIS 2012-13 Status of data entry as on 30.05.2013 Central Scheme Number of Houses State ARUNACHAL PRADESH ASSAM MANIPUR Annual Target 8339 184408 % Houses sanctione 1st 2nd Sanctioned Registered Consolidated Installment Installment 3rd Installment d in MIS to MPR as per MPR in Mis At block Sanctioned released released released 1819 0 0 0 0 0 0 0 182021 136425 118204 113622 87205 16443 3174 62.42 7238 1468 1820 1232 1064 0 0 0 72.48 12608 13232 11427 9034 7932 2319 221 0 60 MIZORAM 2687 1941 2310 1290 1268 876 405 0 65.33 NAGALAND 8343 0 1180 0 0 0 0 0 0 SIKKIM 1596 1596 1746 1595 1594 0 0 0 99.87 16245 0 18445 10625 7144 3708 4 4 0 MEGHALAYA TRIPURA Training requirements? Status of complaints No. of complaints sent for action/report awaited State 2011-12 2012-13 Assam 2 7 Tripura 1 - Physical Performance 2012-13 (In thousand units) State Annual Target Total Houses Sanctioned Houses under construction Houses Completed %age of target achieve d Arunachal Pradesh 8.33 1.82 0.65 1.52 18.19 Assam 184.41 182.02 145.69 97.45 52.84 Manipur 7.24 1.47 0.95 1.87 25.86 Meghalaya 12.61 13.23 8.70 5.36 42.48 Mizoram 2.69 1.94 0..24 1.93 71.54 Nagaland 8.34 0 0 0 0 Sikkim 1.60 1.60 0 1.41 88.35 Tripura 16.25 0 0 0 0 Financial Performance 2012-13 (In lakhs of Rupees) State Central Allocation Central Release Total Available funds Utilization of funds %age Utilisation Arunachal Pradesh 3640.22 3327.41 3631.88 689.55 18.99 Assam 80494.43 57349.21 108358.37 64278.28 59.32 Manipur 3159.90 2130.81 2769.18 973.77 35.16 Meghalaya 5503.42 4894.99 5996.06 5216.19 86.99 Mizoram 1172.84 1080.27 1155.94 989.90 85.64 Nagaland 3641.79 3641.79 3641.79 0.00 0.00 Sikkim 696.50 348.25 348.25 540.45 155.15 Tripura 7090.90 6186.32 6566.70 0.00 0.00 Common Issues • All releases will be linked to AwaasSoft entries • Compliance of conditions imposed during release of 2nd installment, 2012-13 to enable releases in 2013-14 • Special audit of special packages sanctioned • Bank details of DRDAs – CPSMS registration mandatory • Action Taken Report on complaints and NLMs report • DRDA’s to submit information as per check list • Performance Audit – CAG 2007-08 to 2012-13 - States should provide necessary information & support Arunachal Pradesh 2013-14 Ist instalment – District wise targets awaited 2012-13 – 2nd installment • Proposal not received - Dibang valley, Lower Dibang valley and Papumpare • Released during 2013-14 - East Siang, East Kumang and West Siang • Request for 780 houses for the families of freed bonded labour belonging to Suiling tribe in East Kameng district – needs to be sent to EC Special Packages 5% IAY S.No District 1. 2. 3. 4. 5. 6. 7. Chang lang Dibang Valley Lower Dibang Valley Lower Subansiri Upper Siang Upper Subansiri West Kameng 8. Kurung Kurmey 9. Lower Dibang Valley Amount (in lakhs) 2007-08 37.500 37.500 11.344 18.750 37.125 18.750 18.750 2008-09 37.500 2009-10 18.75 DISTRICTS need to submit Utilisation Certificate, Auditor Report and Completion Certificate Border Package S.No District 1st installment Year 2nd installment Year Documents required 1. Dibang Valley 2008-09 Amount (in lakhs) 18.710 2. Kurung Kurmey 2008-09 261.954 2011-12 Amount (in lakhs) DISTRICTS need to submit 261.954 3. Tirap 2009-10 112.715 - - 4. Upper Subansiri 2009-10 34.475 - - 5. Anjaw 2010-11 413.721 - - 6. Lower Dibang Valley 2010-11 26.040 - - 7. Upper Subansiri 2010-11 159.105 2011-12 159.105 - Utilisation Certificate, Auditor Report Assam 2013-14 1st instalment - under examination 2nd installment 2012-13 • Sanctions for Sonitpur, Golaghat, Darang, Kamrup (M) & Karbi Anglong issued • Bongaigaon is under examination • Kamrup (Rural) – proposal not received Special Package • Proposal for 2nd installment under FRA - 2011-12 awaited • Proposal for 2nd installment under 5% from Kamrup (M) and Nalbari awaited • Request for 68,832 additional houses for beneficiaries under FRA & people affected by erosion need to be brought to the EC for approval Manipur 2013-14 1st instalment - under examination 2012-13 – 2nd installment – Proposals not received from Chandel, Bishnupur and Thoubal Special Package – Settlement of accounts 5% IAY – 2009-10 to Senapati district – UC, AR & Completion Certificate awaited Border districts – 2009-10 Chandel - UC, AR & Completion Certificate awaited Senapati - 2nd installment not availed Request for 1263 houses as additional target for the families of insurgency affected in Thanlon T.D block of Churachandpur district – needs to be sent to EC Meghalaya 2013-14 Ist instalment – sanctions issued to 5 districts 2012-13 - 2nd instalment – South Garo hills – proposal not received – East Khasi Hills - under objection Mizoram 2013-14 Ist instalment – sanctions issued to all districts Nagaland 2013-14 Ist installment – submitted to IFD Special Package - Settlement of accounts – 5% IAY – 2007-08 to Peren district – 5% IAY - 2008-09 to Mokokchung district Both have not availed 2nd installment Sikkim • 2013-14 Ist instalment – revised district wise targets awaited • 2012-13 – 2nd installment – Not availed by all districts Tripura 2013-14 Ist instalment – revised district wise allocation awaited 2012-13 – 2nd installment • North Tripura - under objection Special Package • Border package - 2010-11 to North Tripura district – 2nd installment not availed • Incentive package - 2010-11 to all 4 districts – UC, AR & Completion Certificate awaited • Incentive package - 2011-12 to all 4 districts – Dhalai district has to submit UC,AR & Completion Certificate – Other districts have to submit proposals for 2nd instalment Thank you