Transcript Site Proposal
Clause No. 3.0 and Clause No. 6.0 of the MSA to be followed.
By Tenant
Site Request
in the standard format by Tenant to BSNL for each site
By Tenant
Intimation of RFAI date by BSNL 10 days prior to anticipated RFAI date.
Acceptance/rejection of RFAI within next 10 days by Tenant If RFAI rejected by Tenant
By BSNL Circle
BSNL to rectify the defects within next 10days and re-offer the site to Tenant 3days prior to clearance of defects.
By BSNL Circle
Site Proposal
by BSNL to Tenant (if accepted) within
2 weeks
after site request from Tenant
By BSNL Circle
Site RFAI (Passive infrastructure up gradation )
: •30 days from date of service order acceptance.
•.Roll out penalty after 90days form date of service order acceptance.
By Tenant
Service order
Tenant by
within 1 week
from the date of site proposal
By BSNL Circle
BSNL shall confirm the Service Order Acceptance in writing to Tenant within
1week
after service order If RFAI accepted or no defect notified by tenant RFAI date shall be 11 th day from date of receipt of Notice of readiness or 4 th day from date of re-offer intimation. Individual Site Agreement to be signed with 7days form RFAI date. Telecom implementation by Tenant Commencement date shall be 15 th day from date of RFAI