IMP - Sea King Symposium

Download Report

Transcript IMP - Sea King Symposium

IMP AEROSPACE
Sea King Pylon Repair and Overhaul
by
Anick Chiasson
Intermediate Aero/Mechanical Engineer
Rotary Wing Engineering
IMP AEROSPACE
IMP Aerospace, P.O. Box 970, Enfield, Nova Scotia, Canada B2T 1L5
Tel. 902. 873.2250 • Fax 902 873 2290 • e-mail. [email protected]
Website. www.impaerospaceanddefence.com
1
Presentation Outline
• Introduction
• Overview of the Pylon
• Areas of Interest on the Pylon
• Engineering Process
• Area 1: Tail Gearbox (TGB) Support Fitting
• Area 2: Pylon Fold Fitting
• Area 3: Oversized Rivets on left side of a Pylon
• Area 4: Hinge fittings
• Area 5: Oversized Fasteners at Hinge Fittings
• Questions
2
Introduction of IMP Group Ltd.
Number of
professionals
IMP Group
Ltd.
IMP AEROSPACE &
DEFENCE
IMP AEROSPACE
Engineering Branch
Aeronautical
Support
Engineering
Rotary Wing
Engineering
= 22
Fixed Wing
Engineering
= 26
Specialty
Engineering
= 12
= 32
Integrated Logistics
Support (ILS)
= 29
Technical
Publications
= 30
3
Overview of the Pylon
Pylon
The Pylon is the tail end of the aircraft.
4
Overview of the Pylon
• The Pylon holds the Tail Rotor and the Stablilizer.
• The Intermediate Gearbox (IGB) and the Tail
Gearbox (TGB) are installed on the Pylon.
• The Pylon is under intense load (torsion and
bending).
• The Pylon is a critical primary component of the
Sea King.
5
Areas of Interest on the Pylon
Area 1
Area 3
Area 2
Area 4
Area 5
•
Area 1: TGB Support Fitting
•
Area 4: Hinge Fittings
•
Area 2: Pylon Fold Fitting
•
•
Area 3: Row of oversized
Rivets along LH side
Area 5: Oversized Fasteners
at Hinge Fittings
6
Engineering Process
•
Sea King part or component is inducted in our facility.
•
The damage is assessed.
•
Production department requests Engineering services for a
serviceability assessment.
•
Engineering team calculates safe limits for rework/repair.
•
Engineering team prepares a detailed repair scheme document.
7
Area 1 : TGB Support Fitting
Mounting
Pads and
Bolt Holes
Barrel
Nut Holes
•
Damage found inside barrel nut bore holes and bolt holes
•
Damage found on Tail Gearbox (TGB) mounting pads
8
Area 2: Pylon Fold Fitting
The power fold system was added to the Canadian
version of the Sea King.
Pylon
Fold
Fitting
9
Area 3: Oversized Rivets on left side of a Pylon
Rivet #55
FWD
UP
Rivet #1
Row of oversized Rivets (Quantity 55) was discovered at overhaul.
The rivets found were 1/4” and the OEM design was 3/16”.
10
Area 4: Hinge Fittings
Upper Hinge Fitting
(Top View)
Lugs
• The lugs are two of the
attachment points to the
aircraft fuselage.
• The four mounting pads
are to install the
Intermediate Gear Box.
IGB
Mounting
Pads
11
Area 5: Oversized Fasteners at Hinge Fittings
Upper Hinge
Fitting
Hi-Lok fasteners qty 11
on either side at upper
hinge fitting
UP
FWD
Hi-Lok fasteners qty 8
on either side at lower
hinge fitting
12
Area 5: Oversized Fasteners at Hinge Fittings
Initial Problems:
• 11 pylons with oversized fasteners at installation of Upper and
Lower Hinge Fittings.
• No approved documentations were found to substantiate the
oversized fasteners.
• Up to 0.292” from their original design size of 0.188”.
• Biggest problem was the lack of acceptable edge distance (ED)
on the different structure parts.
13
Area 5: Oversized Fasteners at Hinge Fittings
Assessment:
Option 1
Repairing the pylon by replacing
the structure affected; and
revert to 3/16” fasteners:
Option 2
Analyzing the damage for
serviceability:
• The margins of safety of the
• 400 man-hours per pylon
• Lead time to get parts
• Material cost
• Manufacturing hours to
manufacture parts needed
Fittings were high
• The skin, cap angles and
doubler had to be analyzed
• The analyses would render
at least 8 pylons serviceable
14
Area 5: Oversized Fasteners at Hinge Fittings
Example of the multiple layers
within the Pylon.
Plugging the oversized holes
was required for this repair.
15
Area 5: Oversized Fasteners at Hinge Fittings
Results:
• Engineering was able to analyze the structure with
the oversized fasteners.
• Those completed and approved analyses rendered
6 pylons serviceable.
• More pylons will be deemed serviceable using the
completed analyses.
• Fatigue limits in terms of life span for each pylon
were achieved.
16
Area 5: Oversized Fasteners at Hinge Fittings
Edge Distance
(ED) less than 2D
Splice cut line
Example of spliced skin (above)
Example of less than 2D edge distance (left)
17
Questions
Thank you for the opportunity to highlight IMP’s
Pylon R&O capabilities!
Please come see a Pylon at our booth to discuss any
further questions that you may have!
18