CITY OF TULSA
Fee-in-Lieu of Detention, Tulsa, Oklahoma: Best
Management Practice
William H. Robison, PE, CFM, City of Tulsa
Janet K. Meshek, PE, CFM, Meshek & Associates, PLC
Chris S. Hill, GISP, CFM, Meshek & Associates, PLC
1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM
CHRIS S. HILL, GISP, CFM
Senior Engineer for City of Tulsa
GISP Manager for Meshek &
Public Works Department
Been with City since 1988
Extensive experience in
stormwater engineering design &
construction, Community Rating
System (CRS), Hazard Mitigation
including FEMA grant
applications, construction
management & multiple software
programs
BS, Civil Engineering, Oklahoma
State University
JANET K. MESHEK, PE, CFM
Founder of Meshek & Associates &
Principal Engineer
32 years experience in stormwater
planning, management, design &
hydrologic & hydraulic modeling
Associates, PLC
Been with Meshek & Associates
for 10 years
Involved in numerous mapping &
GIS projects for communities
throughout Oklahoma
Expertise in project mapping, data
visualization, project data
organization & project
administration
Currently Adjunct Professor
teaching Introduction to
Geographic Information Systems
(GIS) at Tulsa Community College
B.S. in geography with minor in
interdisciplinary perspectives on
environment, University of
Oklahoma
ABOUT THE SPEAKERS
WILLIAM H. ROBISON , PE, CFM
floods – 3 dead & $55
million damage
1977 Earth Change &
Drainage Ordinances
1978 Design Criteria
Manual – established feein-lieu of detention as
“trade-off” option
1984 “worst” flood - 14
dead & $150 million
damage
Post-1984 Flood Watershed Development
Ordinance
FEE-IN-LIEU HISTORY
1974 & 1976 devastating
No downstream adverse impact
Proposed fee structure $25,000/ac.-ft. or $0.20/sq. ft.
Adopted fee structure - $0.10/sq.
ft. additional impervious area
2003 increased to $0.20/sq. ft.
Fee significantly less actual costs
2009 RESULTS & RECOMMENDATIONS
Increase fee to $0.73/sq. ft.
Implement over 3 years
Update regularly
FEE-IN-LIEU HISTORY
1994 STORMWATER MANAGEMENT CRITERIA MANUAL
CURRENT CONSTRUCTION COSTS
Storage volume estimated
Unit costs from current City
construction projects
Used 5 detentions
Ranging in size from 50
ac.-ft. to 122 ac.-ft.
City “as-builts” & surface
acres
Calculation of average
actual construction costs
CURRENT LAND VALUES
Based on County
Assessor’s property
tax base data
Calculation of
average land costs
for detentions
STUDY METHODOLOGY
DETENTION SITES
STUDY METHODOLOGY
5 DETENTIONS CITYWIDE
Alsuma
Brookwood
Haikey
Turner Park
Heatherridge
6
STUDY METHODOLOGY
CONSTRUCTION
COSTS
Example - Haikey
Creek Detention
Facility
50 ac.-ft. storage
volume
7
Current construction costs
were projected:
50 ac.-ft. at $19,000/ac.-ft.
Amount of additional
impervious area computed:
50 ac.-ft./0.3 ac.-ft. =
166.67 ac.
or 7,260,000 sq. ft.
STUDY METHODOLOGY
PROJECTED CURRENT CONSTRUCTION COSTS – HAIKEY CREEK
Current construction costs were projected:
50 ac.-ft. at $19,000/ac.-ft.
Amount of additional impervious area computed:
50 ac.-ft./0.3 ac.-ft. = 166.67 ac. (7,260,000 sq. ft.)
To mitigate 1 acre of additional impervious area:
$19,000 X 0.3 ac.-ft. = $5,700/ac.
To mitigate 1 sq. ft. of additional impervious area:
$5,700/43,560 sq. ft. = $0.13/sq. ft. of additional
impervious area
Actual construction cost = $0.13/sq. ft.
STUDY METHODOLOGY
PROJECTED CURRENT CONSTRUCTION COSTS - HAIKEY CREEK
Range in actual total costs of construction of 5
detentions
$0.13/sq. ft. to $0.38/sq. ft.
Actual average total cost of construction
$0.26/sq. ft. of additional impervious area
STUDY METHODOLOGY
PROJECTED TOTAL CONSTRUCTION COSTS – HAIKEY CREEK
Assessor’s data valuable resource
- Verifiable & defensible database
GIS valuable tool for real estate data
GIS demonstration to follow
2 adjustments due to nature of publicly-owned
land
Surrounding real estate basis for cost projections
Cost adjustment of 2.5 factor for eminent domain
STUDY METHODOLOGY
PROJECTED CURRENT LAND COSTS – HAIKEY CREEK
STUDY METHODOLOGY
HAIKEY CREEK –LAND COSTS BEFORE ADJUSTMENT
Total surrounding land value divided by total
number of square feet = average of $4.20/sq. ft.
land cost
Adjusted land cost is $4.20/sq. ft. X 2.5 = $10.50/
sq. ft.
Current land costs = total surface acreage
multiplied by adjusted cost per square foot
396,573 sq. ft. X $10.50/sq. ft. = $4,164,018
Projected cost to mitigate 1 sq. ft. of additional
impervious area:
$4,164,018/7,260,000 sq. ft. = $0.57/sq. ft.
STUDY METHODOLOGY
PROJECTED CURRENT LAND COSTS – HAIKEY CREEK
Range in actual total cost of land for 5
detentions
$0.20/sq. ft. to $0.63/sq. ft.
Actual average total cost of land for 5
detentions
$0.48/sq. ft. of additional impervious area
STUDY METHODOLOGY
PROJECTED TOTAL LAND COSTS – HAIKEY CREEK
Average actual total construction & land costs to
mitigate 1 sq. ft. of additional impervious area
Average total construction costs = $0.26
Average total land costs = $0.48
$0.26 + $0.48 = ~$0.73/sq. ft. of additional
impervious area
STUDY METHODOLOGY
PROJECTED ACTUAL TOTAL COSTS – ALL DETENTIONS
STUDY METHODOLOGY
16
current construction and land costs
Easy to update data with minimal effort to
input new data, including GIS services
Cost-effective
Fees reflect actual public costs
METHODOLOGY ADVANTAGES
Valid and reliable data based on actual
Current actual total cost of
$0.73 is significant
increase
Possible difficulty in
implementing due to
magnitude of increase
CONSEQUENCES NO INCREASE
INCREASE
Fee will defray only part of
total actual public costs
Costs not paid by
development community will
become future public
costs
INCREASE IS DIRECT RESULT
Lack of periodic fee review
Historical fees not
reflective of total actual
public costs
Development community
influential in decisionmaking
OTHER CONSEQUENCES
Proliferation of onsite nonregional detentions can
result in negative impacts
Objections to
implementation likely
RESULTS AND CONCLUSIONS
INCREASE IS SIGNIFICANT
Sept. 2009 – Board approved fee
increase over 3 years
Apr. 2010 – City Council approved
implementation effective immediately
April 2011 & 2012 - Incremental
increases - $0.18/sq. ft. per year
IMPLEMENTATION
THE END OF THE STORY
Matrix developed to determine when use of Fee-InLieu is appropriate
- Developer may implement Best Management
Practices to assure no adverse downstream impact &
no requirements
If not, issues to consider before using Fee-in-Lieu:
- Any increase in impervious area?
- Any downstream structures that flood? Downstream
damages? Capacity of downstream system?
- Compliance with Master Drainage Plan?
Based on the above, Fee-in-Lieu may be an option
SUCCESSFUL IMPLEMENTATION CONSIDERATION OF OTHER ISSUES
SUCCESSFUL IMPLEMENTATION – OTHER CONSIDERATIONS
DECISION MAKING PROCESS PERMITTING
FEE-IN-LIEU OF DETENTION
DECISION MATRIX TO DETERMINE USE OF FEE-IN-LIEU
Uses existing accessible
and reliable databases
Allows quick & easy
updates at minimal cost
Uses actual public costs
Promotes development
without public cost
Fees based on original
intent of “trade-off’
Has applicability to other
communities
Use of decision matrix
QUALIFICATIONS
Should be an option – not
mandated
Should consider adverse
downstream impact in
approval process
BEST MANAGEMENT PRACTICE
EXCELLENCE
CITY OF TULSA
GIS presentation follows
Fee-in-Lieu of Detention, Tulsa, Oklahoma: Best
Management Practice
William H. Robison, PE, CFM, City of Tulsa
Janet K. Meshek, PE, CFM, Meshek & Associates, PLC
Chris S. Hill, GISP, CFM, Meshek & Associates, PLC