Transcript Project Scheduling: Networks, Duration Estimation, and
Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-1
Project Scheduling Terms
• • • • • Successors Predecessors Network diagram Serial activities Concurrent activities B A D E C F Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-2
Project Scheduling Terms
• • • • • Merge activities Burst activities Node Path Critical Path B A D C Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall E F 9-3
Network Diagrams
Show interdependence Help schedule resources Facilitate communication Show start & finish dates Determine project completion Identify critical activities Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-4
AOA Vs. AON
The same mini-project is shown with activities on arc… D E B F C B D …and activities on node.
E F C Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-5
Node Labels
Early Start Activity Float Late Start ID Number Activity Duration Early Finish Activity Descriptor Late Finish Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-6
Duration Estimation Methods
• Past experience • Expert opinion • Mathematical derivation – Beta distribution – Most likely (m) – Most pessimistic (b) – Most optimistic (a) =
s
2 6 2 = TE
a
4 6 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-7
1. Sketch the network described in the table.
2. Determine the expected duration and variance of each activity.
Task Predecessor Z - Y X Z Z a 7 13 14 b 8 16 18 W V Y, X W 12 1 14 4 T W 6 10 S T, V 11 14 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall c 15 19 22 16 13 14 19 9-8
Constructing the Critical Path
• Forward pass – an
additive move
through the network from
start to finish
• Backward pass – a
subtractive move
the network from
finish to start
through • Critical path – the
longest path
from end to end which determines the
shortest project length
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-9
Rules for Forward/Backward Pass
Forward Pass Rules (ES & EF) – ES + Duration = EF – EF of predecessor = ES of successor – Largest preceding EF at a merge point becomes EF for successor Backward Pass Rules (LS & LF) – LF – Duration = LS – LS of successor = LF of predecessor – Smallest succeeding LS at a burst point becomes LF for predecessor Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-10
Task Predecessor Time A B - A 4 9 C D E F G H K A B B C D, F E, G H 11 5 3 7 3 2 1 1. Sketch the network described in the table.
2. Determine the ES, LS, EF, LF, and slack of each activity Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-11
Laddering Activities
Project ABC can be completed more efficiently if subtasks are used A(3) B(6) C(9) ABC=18 days A 1 (1) A 2 (1) A 3 (1) B 1 (2) B 2 (2) Laddered ABC=12 days C 1 (3) Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall B 3 (2) C 2 (3) C 3 (3) 9-12
Hammock Activities
Used as summaries for subsets of activities 0 A 0 5 5 5 5 B 15 5 10 15 15 C 18 15 3 18 0 Hammock 18 0 18 18 Useful with a complex project or one that has a shared budget Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-13
Reducing the Critical Path
• Eliminate tasks on the CP • Convert serial paths to parallel when possible • Overlap sequential tasks • Shorten the duration on critical path tasks • Shorten – early tasks – longest tasks – easiest tasks – tasks that cost the least to speed up Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-14
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-15