GOAA CONSTRUCTION
Upcoming Projects
Mike Patterson, P.E.
Tuesday, February 8, 2011
Capital Improvement Plan
Tuesday, February 8, 2011
Highlights of Upcoming Projects
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
BP-039, OEA Taxiway E Rehabilitation and Miscellaneous Airfield Improvements (2012)
BP-402A-D, Landside Emergency Electrical Infrastructure Improvements – Phase 2
BP-402E, Airside 4 Emergency Power Infrastructure Improvements
BP-411, Taxiway A Widening and Related Work (2012)
BP-418, Baggage Handling System Renovation (Design/Build)
BP-419, Baggage Handling System Infrastructure Renovation
BP-427, CCTV Renovation
BP-428, Taxiway B-2 Extension and Taxiway B-1 Rehabilitation (2011)
BP-429, Enplane Drives Structural Rehabilitation
E022, Airside 4 APM Switchgear Replacement
V-445, Landside Level 2 FIDS Replacement (Design/Build)
V-562, Hyatt Air Handling Unit Replacement - Phase 2
V-578, Hyatt Water Pipe Replacement – Phase 2
V-581, Airside 4 FIS Relocation
V-582, Airside 4 HVAC Improvements
V-584, Airside 4 APM Guideway Rehabilitation
Tuesday, February 8, 2011
BP-039, OEA Taxiway E Rehabilitation and
Miscellaneous Improvements
Project Scope
Rehabilitation of
existing pavement for
Taxiway E, area north
of Runway 7-25,
install airfield signage
and pavement
marking, and install
two high mast lights
on the East Ramp
Construction Cost
Approx. $400 K
Duration
Nov. 2010 - Jan. 2011
Tuesday, February 8, 2011
BP-402A-E, Landside Emergency Electrical
Infrastructure Improvements – Phase 2
Project Scope
Phase 2 of the emergency
electrical distribution
modifications establishes
the infrastructure for
security and equipment
branches of the Landside
Terminal and Airside 4
emergency power system
Construction Cost
Approx. $20+ M
Duration
Winter 2011 - Fall 2012
Tuesday, February 8, 2011
BP-411, Taxiway A Widening and Related Work
BP-428, Taxiway B-2 Extension and Taxiway B-1
Rehabilitation
Project Scope
Widening of Taxiway A,
reconfiguration of current Taxiway A1, and the extension of Taxiway B-2
from Runway 18L-36R to Taxiway A
The extension of Taxiway B-2 from
Runway 18L-36R to Runway 18R-36L
and associated connecting taxiway to
Taxiway B-1 and widening of Taxiway
B-1
BP-411
BP-428
Construction Cost
Approx. $10 M for each
Duration
Nov. 2011 - Dec. 2012
Nov 2012 – Dec 2013
Tuesday, February 8, 2011
BP-418, Baggage Handling System
Renovation (Design/Build)
Project Scope
Replacement of the
baggage handling
systems in the Delta,
AirTran, United, and
BA make-up areas
Construction Cost
Approx. $14 M
Duration
Mar. 2011 – Dec. 2012
Tuesday, February 8, 2011
BP-419, Baggage Handling System
Infrastructure Renovation
Project Scope
Renovation of the
infrastructure for the
baggage handling
systems in the Delta,
AirTran, United, and
BA make-up areas
Construction Cost
Approx. $8 M
Duration
June 2011 – Feb. 2012
Tuesday, February 8, 2011
BP-427, CCTV Renovation
Project Scope
Replacement of the
Closed Circuit
Television (CCTV)
Monitoring System at
the Landside Terminal
passenger screening
checkpoints and
Airsides 1 and 4 FIS
West Black Diamond Lane Images
360 Camera
Construction Cost
Approx. $1.5 M
Duration
Summer 2011 Summer 2012
Tuesday, February 8, 2011
BP-429, Enplane Drives Structural Rehabilitation
Project Scope
Repair to expansion
joints, beam seats, and
concrete elements of the
enplane roadway drive,
A and B sides
Construction Cost
Approx. $1.5 M
Duration
May 2011 – Nov. 2011
Tuesday, February 8, 2011
E-022, AS 4 APM Switchgear
Replacement
Project Scope
New enclosure and
electrical switchgear at
Airside 4
Construction Cost
AS1
Approx. $600K
AS4
Duration
AS3
Apr. 2011 – Sept. 2011
Tuesday, February 8, 2011
V-445, Landside Level 2 FIDS Replacement
Project Scope
Remove existing FIDS display
cabinets on Level 2 Landside
Terminal. Replace with column
mounted LCD FIDS at the four
entry points to Level 2 from
Level 3.
Final Construction Cost
Approx. $400K
Duration
Apr. 2011 – Jan. 2012
Tuesday, February 8, 2011
V-562, Hyatt Air Handling Unit Replacement
V-578, Hyatt Water Pipe Replacement – Phase 2
Project Scope
Replacement of cold
water pipe.
Replacement of
multiple air handling
units.
Construction Cost
Approx. $300K (Water)
Approx. $600K (HVAC)
Duration
2011 - 2012
Tuesday, February 8, 2011
V-581, Airside 4 FIS Relocation
V-582, Airside 4 HVAC Improvements
Project Scope
Upgrade Hub HVAC.
Relocate FIS to open
concessions space in
transfer level.
Construction Cost
Approx. $1.5M (HVAC)
Approx. $200K (FIS)
Duration
2011 - 2012
Tuesday, February 8, 2011
V-584, Airside 4 APM Guideway Rehabilitation
Project Scope
Crack sealing, crack repairs,
concrete running surface
sealing, concrete repairs
and/or replacement
Construction Cost
Approx. $500K
Duration
October 2011 – May 2012