The Port of Bar
Download
Report
Transcript The Port of Bar
SEE Port Development
A Variation on the Story of
the Rabbit and the Turtle
Erich Cossutta, President
Confindustria Serbia
Presentation Outline
1.
General description of port of Bar and Durres
2.
Comparison of the two ports
•
Port of Koper – as a model for growth
•
Conclusions
2
Location // Position
Gravitational field
Bar
Montenegro, Serbia, BiH, Kosovo,
Macedonia,
Durres
Albania, Kosovo, Macedonia, South
Serbia
3
The Port of Bar
Port of Bar Container Terminal and General Cargo – joint stock company with
the Government of Montenegro as majority holder (54% shares). Currently
under privatization, working under concession of the Montenegro Port Authority
Capacity – 2 million tons of cargo
Modern and healthy infrastructure – good rail connections
Good expansion potential
Poor road connection with the gravitational field
4
The Port of Durres
Durres Port Authority
Biggest port of Albania
78 per cent of maritime trade at national level
Well positioned for Corridor VIII, good new road connection to Skopje and
Pristina
Very poor or not existing rail connection with the gravitational field
5
Connection with gravitational field – BAR and DURRES
Road / rail distance
MARKET
PORT
SKOPJE
PRISTINA
DURRES
120km railway
200km road
No direct railway
260km road
BAR
642km railway
428km road
651km railway
335km road
6
Connection with gravitational field – BAR
Road / rail distance
Bar
7
Current capacity
Investments – PLAN
Bar
Durres
60,000 TEU
80,000 TEU
…with minimum investments 150,000
already at max capacity
Project for the new area for the accommodation
of the empty containers, approximately 24,300 acquisition of machinery : 2 reach stacker, 4
m2
trailers, 1 spreader for 20’- 40’ containers
Supply of mobile cranes and STS cranes –
planned in 2013
Planned implementation of a software Container Terminal Operation Information
System
Reconstruction of the southern coast of Wharf 1,
implementation of the forehead of Wharf 1
New 54 reefer connections for reefer
containers
Investments in the separation
available storage space.
of
the
8
Other specifications
BAR
DURRES
Shipping company
Maersk, MSC, Hapag Lloyd, CMA
CGM
CMA CGM, MSC, Evergreen Line
ZIM
Type of service
feeder, no direct services
feeder, no direct services
Container block train
Presently no regular block train,
possibility of single vagon
shipments
no cargo rail infrastructure
Terminal total area
80.000 m2 + 50.000 m2 possibility
of expansion
50.000 m2
Lenght of operational quay
330 m
150 m
Draft
12 m
8m
9
Other specifications
BAR
DURRES
Special equipment
Gantry crane 40t;
Reach stacker 45 ton;
Electric and diesel forklifts for
loading/discharging of containers 1,5 t
/3 t /5 t;
2 frontal forklifts 42t/40t;
tag master sisu, 1 pc;
trailers fm 8 to 35 tons
MHC 120 t, MHC 63 t, 1
reach stacker, 2
forklifts 32 t , forklift 12 t, 1 pc
ECH 7 ton
Reefer connections
184
92
2010
2011
2010
2011
30,477
14.068
(full only)
85,875
50.745
(full only)
Container traffic
10
Additional info
Bar
Durres
The entire area of AD "Container Terminal and No possibility for expansion, the port is located in the
General Cargo" has the status of Custom Free Zone. middle of the town
Possibility to berth simultaneously 9 different types of Very low draft and need for continuous dredging of the
entry channel
vessel at docks under international rules.
Road and rail connections to each storage, vessel Very poor railway infrastructure to Macedonia, no
railway connection to Kosovo or Southern Serbia
berth and warehouse
NEW! Serbian FIAT car production going via port of Good road connection to Macedonia and Kosovo
Bar, 90% on rail from August 2012
Future highway planned to connect Pristina with
Slow and not attractive (Container terminal together Southern Serbia?
with General Cargo) privatization process
Poor road connection
11
The future?
12
Model for growth
Port of Koper, Slovenia
13
14
15
16
17
Port of Koper Container traffic in years
1996 - 2009 (tons, TEU)
18
19
20
21
22
HOW THEY
DID IT?
23
24
25
26
27
Thank you!
Erich Cossutta, President Confindustria Serbia
28