ENGINEERING CONSTRUCTION ( BAA 1322 )

Download Report

Transcript ENGINEERING CONSTRUCTION ( BAA 1322 )

LECTURE 2:
TENDER PROCESS
AND
DOCUMENTATION
Lecture by:
Ms. Noorhidayah Sunarti (012-6254776)
LOC1/AC2
1
WHAT IS TENDER?
LOC1/AC2
2
Tender is an offer which incorporates
the sum of money, time and other
conditions required to carry out the
contract obligations in order to complete
a project or a part of it consisting of
specified works.
LOC1/AC2
3
WHAT IS
TENDERING ?
LOC1/AC2
4
Stages of a project
 Stage 1: inception & feasibility – identifying
project objectives / set up project brief
 Stage 2: design – develop further project brief /
develop concept & schematic design / Undertake
detailed design & detailing / prepare cost plan &
budget
 Stage 3: tendering – issue tender documents /
prepare & submit tender / evaluation of tender /
award tenders / prepare contract documents
LOC1/AC2
5
Stages of a project
 Stage 4: construction – site possession &
mobilization / undertake procurement fabrication,
installation, construction / carry out contract
admin
 Stage 5: handover & maintenance –
undertake all testing, commissioning & training /
obtain CF / handover project to owner /carry out
necessary maintenance / Defect rectification / etc
LOC1/AC2
6
Tendering
Will be started after the design complete and
project budget must be approved
The process that is used to obtain offers
leading to a contract between:
client
contractor
client
main contractor
consultant
sub-contractor
LOC1/AC2
7
Purpose of tendering process
 To select a suitable contractor at a
time appropriate to the situation of
the project.
 To obtain from the contractor
selected at the proper time, an
acceptable tender or offer upon which
a contract can be let.
LOC1/AC2
8
Difference between a contract and
a tender
 A tender formally means an invitation
to trade under the terms of offer.
 A contract is the term used for when
the parties have reached agreement.
LOC1/AC2
9
General
TENDERING
PROCESS
LOC1/AC2
10
Tendering process –
PRINCIPAL ACTIVITIES
1.
2.
3.
4.
5.
Selection of the most preferable or
appropriate contract procurement
method.
Development of tender list
Preparation of tender documentation
Invitation / calling off tender
Preparation and submission of
tenders
LOC1/AC2
11
Tendering process –
PRINCIPAL ACTIVITIES (cont’d)
6. Receipt and opening of tenders
7. Evaluation of tenders
8. Acceptance of tender award or award
of contract
LOC1/AC2
12
Stage 1: Selection of the most preferable or
appropriate contract procurement
method.
 Traditional contract procurement
route


Longer time – lead to critical work
scheduling
Less errors – more precise
 Fast-track contract procurement
route


Shorter time
Consequences – may be lead to critical
error, variation.
LOC1/AC2
13
Stage 2: Development of tender list



Potential tenderers can directly apply to
the employer for future works.
Employer generate list based on previous
dealings
The professional team generate their own
list and recommend to the employer.
LOC1/AC2
14
Stage 3: Preparation of tender
documentation – typical contents
 Letter of invitation
 Checklist for submission of tender
 Articles of agreement
 Conditions of contract
 Form of tender
 Tender specifications
 Bills of quantities
 Tender drawings
 Sample copy of letter of acceptance
 Sample copy of bang guarantee for performance
bond
 Schedule of day work rates
 Sample copy bank guarantee for advance payment
LOC1/AC2
15
Tendering process
Stage 1:
Stage 2:
Stage 3:
PREPARATION
APPROVAL TO
TENDER
DOCUMENTATION
Stage 6:
Stage 5:
Stage 4:
AWARD
CONTRACT
PROCESSING
INVITATION
LOC1/AC2
16
Stage 1: Preparation
 Final completion of drawings,
specification, measurement / take-off
process.
 Choose conditions of contract.
 Parties involved: architect, engineers,
QS, client, project manager
LOC1/AC2
17
Stage 2: Approval to tender
 Discussion and decision on type of
tender to be used.
 Selection of tender:



Open
Selective
Negotiate
Shortlist the selected contractor
 Parties involved: CLIENT,
CONSULTANT, PROJECT MANAGER
LOC1/AC2
18
Stage 3: Documentation
Contract based on tender & specs
 Compilation of:
 Letter of invitation to
tenderers
 Articles of agreement /
conditions of contract
 Form of tender
 Form of tenderer’s details.
i.e: contractor’s registration,
organization background, track
record (past and present
projects)
 Letter of acceptance
 Bank and insurance guarantee
forms (performance bond)
 Bank and insurance guarantee
forms (advance payments)
 Specifications
 Summary of tender
 Schedule of rates
LOC1/AC2  Relevant drawings
19
Contract based on quantities
 Compilation of:
 Letter of invitation to tenderers
 Articles of agreement /
conditions of contract
 Form of tender
 Form of tenderer’s details. i.e:
contractor’s registration,
organization background, track
record (past and present
projects)
 Letter of acceptance
 Bank and insurance guarantee
forms (performance bond)
 Bank and insurance guarantee
forms (advance payments)
 Specifications
 Bills of quantities
 Relevant drawings
Stage 4: Invitation
 Based on selection of tendering
methods



Open / competitive / bid tender –
produce tender notice
Selective – shot listed contractors will
be invited to tender if they wish
Negotiated – only one contractor is
approached- direct entry to project
LOC1/AC2
20
TENDER NOTICE
OR NOTICE
INVITING TENDER
LOC1/AC2
21
 The Tender Notice is a brief
description of the job being tendered
which is to be published in Newspapers
and on the Internet.
 The Internet is a very cost effective
way of publishing the tenders.
LOC1/AC2
22
Format of an ideal Tender
Notice
a. Name of the Project.
b. Name & Address of the
c.
d.
e.
f.
g.
h.
Company floating the
tender.
Name of work, materials
or services.
Place of work location.
Approximate estimated
cost of work.
Earnest Money.
Period of completion.
Date on which the Tender
Document sale commences.
LOC1/AC2
i.
j.
k.
l.
m.
n.
Date on which the Tender
Document sale commences.
Date and time up to which
tender documents can be
obtained.
The cost of tender
documents.
The date and time up to
which the tenders to be
submitted and are to be
opened.
Specification.
Eligibility Criterion.
23
Stage 5: Processing
 Received tender submitted by contractor
 Tender assessment / evaluation





Completed tenders are received
Arithmetical check
Reasonable tender sum
Reasonable completion time
Capabilities of tenderers under considerations
 Tender recommendation / report – tender
board
LOC1/AC2
24
Guidelines to fulfill in the
Tender System
 The capacity, past credentials and financial
status of the tendered is thoroughly
investigated before awarding the contract.
These aspects should be commented in detail
along with the tender documents.
 The rates should be quoted in the numbers
and words without any corrections. To take
advantage of any possible increase in
statutory taxes & duties, the tax component
such as excise duty, Sales Tax, Works
Contract Tax, etc. should be clearly
indicated.
LOC1/AC2
25
 Tenderers should not quote many
special conditions as some of them may
have financial implications, did this can
be added to your quoted cost. Also it
creates confusion and creates room
for manipulative forces.
 The rates quoted for individual items
should be realistic and should not be
abnormal and unworkable.
LOC1/AC2
26
Stage 6: Award contract
 Pre-award meeting with contractors –
validation of lowest complying bid
 Validate lowest bid - Pre-contract meeting
with contractor for contract signing
 Approval by tender board / treasury (tender
exceeds RM10 mill.) – an acceptance of
tender form is issued to tenderer , signed by
the authorised officer
LOC1/AC2
27
TENDER PROCESS
FOR CONTRACTOR
LOC1/AC2
28
Tendering process
Stage 1:
Stage 2:
Stage 3:
Decision to
tender
Determine
basis of
tender
Preparation of
cost estimates
Stage 6:
Stage 5:
Submissio
n of
tender
Conversion
of estimate
to tender
LOC1/AC2
Stage 4:
Commercial
appreciation
29
Stage 1: Decision to tender
 Receipt of tender documents
 Pre-tender data sheet
 Decision to tender
 Consider implications of:




Bonds
Warranties
Parent company
Guarantees
 Funding
LOC1/AC2
30
Stage 2: Determine basis of
tender
 Abstract materials and subcons
 Sent out enquiries
 Consider construction methods / prepare method






statement
Design temporary works / consider alternatives
Prepare outline programme
Check major quantities
Identify restrictions
Visit site and compile site report
Campaigning meeting (designating areas
responsibilities)
LOC1/AC2
31
Stage 3: Preparation of cost
estimate
 Calculate recurrent rates using:
Operational
 Unit rates
 Man-hours estimating
 Analyse and check subcontractors’ quotations
 Price prelims / general items (in association
with members of the team
 Prepare summary sheets

LOC1/AC2
32
Stage 4: Commercial
appreciation
 Tender committee meeting part 1 Review:









Method
Programme
Technical and commercial risks
Cash flow and finance
Use of own plant
Competition
Commercial opportunities
Economic climate
Check prelims against historical cost data
LOC1/AC2
33
Stage 5: Conversion of tender
estimate to tender bid
 Tender committee meeting – part 2
 Calculate ‘spread’ and add to estimate
LOC1/AC2
34
Stage 6: Submission of tender
 Submit in format required
 Organize delivery
LOC1/AC2
35