NUCLEAR POWER DEVELOPMENT
PROGRAM IN VIETNAM
Eng. Phan Minh Tuan
Deputy Director General
Hanoi, January 2013
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
I. COUNTRY OVERVIEW
Country Profile
Area: 330.957 sq. km
Population: 87.8 million (2011)
Density: 265 pop./km2
GDP: 120 billion USD
Install. Capacity: 22,029 MW
Power Production: 100 billion KWh
Capita Consumption: 1,140KWh/year
Installed capacity by fuel sources:
Hydro
: 45,5%
Combined/open cycle gas turbine:
33.6%
FO oil fired: 4,2 %
Coal-fired : 15,3%
Diesel
: 1,4%
Growth of Power Demand: 12% –
15%/year
(As of the year of 2011)
I. COUNTRY OVERVIEW
 Installed capacity composition (according to Master Plan VII) :
2020
2030
 Rationale for nuclear power development:
• To enhance energy security and energy diversity
• To meet rapidly increasing power demand of the country when domestic natural resource
is limited;
• To protect the environment (nuclear power is almost CO2 free)
• To contribute to the national technical and technological capacity building,
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
II. VIETNAM AND NUCLEAR POWER
DEVELOPMENT PROGRAM (cont.)
 National Policies on Nuclear Power:
The Government of Vietnam has approved strategies, plans of energy development and
application, clearly indicating the role and necessity of nuclear power:
01/2006
Strategy on Peaceful Utilization of Atomic Energy up to 2020
07/2007
National Power Development Plan during the period 2006-2015 with vision to
2025 (Master Plan VI)
12/2007
National Energy Development Strategy of Vietnam up to 2020, with vision to
2050.
06/2010
Oriented Planning for Nuclear Power Development in Vietnam up to 2030
07/2011
National Power Development Plan during the period 2011-2020, with vision to
2030 (Master Plan VII)
II. VIETNAM AND NUCLEAR POWER
DEVELOPMENT PROGRAM (cont.)

Main milestones
1.
On June 03, 2008, the National Assembly promulgated the Atomic Energy Law No.
18/2008/QH12, which is the highest legal document regulating the development and
peaceful utilization of atomic energy.
2.
On Oct. 08, 2009, a Public Hearing
Conference was held in Ninh Thuan to
gather opinions of local People Councils at
three levels: province, district and
commune, chaired by the Vice Prime
Minister Hoang Trung Hai.
3.
On Oct. 26, 2009, Ninh Thuan Provincial
People Council issued its Resolution
regarding agreement on the policy of NPP
development in Ninh Thuan province.
4.
On November 25, 2009, the twelfth National
Assembly at her sixth session approved the
investment policy of Ninh Thuan Nuclear
Power Project.
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
III. GENERAL INTRODUCTION OF NINH THUAN
NUCLEAR POWER PROJECT
On the 18th of March, 2010, the Prime Minister approved the overall plan for implementation of
Ninh Thuan Nuclear Power Project. Accordingly, the overall project is composed of seven
component projects (or eight component projects for the time being) and two studies:
Component projects
Project Owner
1. Ninh Thuan 1 nuclear power plant project (2000MW)
2. Ninh Thuan 2 nuclear power plant project (2000MW)
3. Project on infrastructure for construction of nuclear power plants in Ninh Thuan
province (infrastructure project);
4. Project on operation management zone, expert zone, headquarters of Ninh Thuan
nuclear power project management board (EVNNPB)
Vietnam Electricity
(EVN)
5. Project on Public Relation Center for nuclear power;
6. Project on human resource training for nuclear power plants in Ninh Thuan province
7. Localization project in construction, design and equipment manufacture.
Ministry of Industry
and Trade
8. Project on nuclear science technology center.
Ministry of Science
and Technology
9. Project on information and propaganda for nuclear power development in Vietnam
10. Resettlement project for the nuclear power plant projects in Ninh Thuan province.
Ninh Thuan
Provincial People
Committee
III.GENERAL INTRODUCTION OF NINH THUAN
NUCLEAR POWER PROJECT (Cont.)
Ninh Thuan NPP fundamental information
•
Construction site:
Ninh Thuan 1 nuclear power plant is located at Phuoc
Dinh commune, Thuan Nam district, Ninh Thuan
province;
Ninh Thuan 2 nuclear power plant is located at Vinh
Hai commune, Ninh Hai district, Ninh Thuan
province.
•
Project size:
Ninh Thuan 1 nuclear power plant: planned for 4
units among which 2 units with capacity of
approximately 2 x 1000 MW shall be invested in the
first phase;
Ninh Thuan 2 nuclear power plant: planned for 4
units among which 2 units will capacity of
approximately 2 x 1000 MW shall be invested in the
first phase.
•
NPP Technology: Advanced light water reactor
technology which is the most modern, proven, top
safe and economically efficient.
III.GENERAL INTRODUCTION OF NINH THUAN
NUCLEAR POWER PROJECT (Cont.)
3. Project implementation process
12
1. Technical Reports and Appendixes
2. Design Drawings
3. Safe Analysis Report
4. Maintenance procedure
5. Project Cost
6. Tender Document: Approval by Prime Minister
Technical Design Report: Approval by MoIT
SAR: Approval by MOST
2014~2016
1. FS and Basic Design Documents
2. Site Approval Dossier
3. EIA Report; Safe Analysis Report
NT1: 12/2011~7/2013; NT2: 10/2011~3/2013
Review: MOIT, MOST, MORE, Commetees
FS and Site Approval Dossier: Approval by Prime Minister
SAR: Approval by MOST
NT1: 8/2014; NT2: 3/2014
Pre-FS
FS
Resolution No 41/2009/QH12
(25/11/2009) adopted Ninh Thuan
NPP investment by National
Assembly
2006~11/2009
Technical Design
&Tender
Construction
1. Contract form: EPC (Contraction+Training)
2. Quality control: by Consultant/Owner.
3. Inspection by MOC and MOST
4. Construction Permit: MOST
2016~2022
12
Operation
1. Operation Permit: MOIT
2. Trial Operation and COD
3. Operation by Vendor and
Owner
2021~2022
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
IV. IMPLEMENTATION STATUS OF THE COMPONENT
PROJECTS
1.
Ninh Thuan 1 NPP project:
June, 2012
The Consultant submitted the
Investigation Intermediate
Report of phase 1.
Continuing to acquire, analyze
and process the geological and
environmental data
2013
2012
October, 2010
The
Inter-Governmental
Agreement on cooperation
in construction of Ninh
Thuan 1 NPP between
Government of Vietnam and
Government of Russia
Federation
2009
December 2009
MOU on cooperation in the
first NPP in Vietnam territory
between EVN & ROSATOM
2011
November, 2011
2010
Contract
for
the
development of Site
Approval Dossier and
FS of Ninh Thuan 1 NPP
project
Agreement on financing
for development of site
approval dossier and
feasibility study of Ninh
Thuan 1 NPP project.
State Export Credit
Agreement between the
Government of Vietnam
and the Government of
the Russian Federation.
Completion of Site
Approval Dossier
and FS for Ninh
Thuan 1 NPP project
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
1.
Ninh Thuan 1 NPP project:
Site Investigation work
Execute in 2 stages:
1st stage: site selection,
2nd stage: investigation on
selected site.
Investigation works:
Topography
Geology
•Geology in the site area
•Foundation geotechnique
•Hydrogeology
•Mineral resources
Meteorology
Hydrology and oceanography
Human factors
Impacts of radiation on the
public communities and
Emergency Preparedness Plan
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
1. Ninh Thuan 1 NPP project: Site investigation works
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
2.
Ninh Thuan 2 NPP project:
October, 2011
The Arrangement on Cooperation in
Construction of Ninh Thuan 2 NPP between
the Government of Japan and the
Government of Vietnam (SRV) on October
2011
2010
October 2010
Vietnam - Japan
Joint Statement on
the Comprehensive
Development of
Strategic
Partnership for
Peace and
Prosperity in Asia
November, 2012
The investigation work
has been principally
completed
Continuing to implement
additional investigation
works, analyze and
process collected data
and make reports
2012
2011
September, 2011
The Consulting services
Contract for developing
Site Approval Dossier
and Feasibility Study of
Ninh Thuan 2 NPP
Project between Vietnam
Electricity (EVN) and the
Japan Atomic Power
Company (JAPC)
MOU for Ninh Thuan 2
NPP Project between
EVN and the Japan
International
Nuclear
Energy
development
Company (JINED)
2013
Completion of Site
Approval Dossier and
FS for Ninh Thuan 2
NPP project
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
2. Ninh Thuan 2 NPP project:
Site Investigation Works
18
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
2. Ninh Thuan 2 NPP project:
Site Investigation Works
Execute in 1 stage.
Investigation works:
Topography
Geology
•Geology in the site area
•Foundation geotechnique
•Hydrogeology
•Mineral resources
Meteorology
Hydrology and oceanography
Human factors
Impacts of radiation on the
public communities and
Emergency Preparedness Plan
19
IV. IMPLEMENTATION STATUS OF THE PROJECT (Cont.)
3.
Project on infrastructure for construction of nuclear power
plants in Ninh Thuan province (infrastructure project):
The Feasibility Study of the project has been being verified by
EVN.
4.
Project on operation management zone, expert zone,
headquarters of Ninh Thuan nuclear power project
management board:
The Ninh Thuan provincial people committee has been verifying
the 1:500 planning to be the basis for developing the Feasibility
Study
5.
Project on Public Relation Center for Nuclear power:
To be implementing the investigation works for Feasibility Study
development
6.
Project on human resource training for nuclear power
plants in Ninh Thuan province:
The project report has been carefully reviewed with comments
contributed by IAEA’s experts and shall be submitted to the Prime
Minister for approval
Master perspective of Public Relation Center for
nuclear power
CONTENTS
•
•
•
•
•
Country overview
Nuclear power development in Vietnam
General Introduction of Ninh Thuan nuclear
power project
The implementation status of component
projects
Other related works
V. OTHER RELATED WORKS
1.
Human Resource Training:
EVN has proactively conducted long term training activities for
nuclear power since 2006 as follows:
Long-term education and training:
Electric Power University under EVN has built up
the nuclear curicculum and enrolled students
from 2010.
Dispatching 03 personnel abroad for Ph.D education
program in Russian, Sweden, Czech Republic, two of them
have returned for working in Vietnam.
Master/Engineer program: From 2006 - 2009, 31 good
students were dispatched to Russia and France for
Master/Engineer program education
15 staffs are being trained in Japan to be core members of
Ninh Thuan 2 NPP
Participating in education and training programs of MOET
and MOIT.
Short-term training:
More than 200 turns of people were trained in nuclear powerdeveloped countries.
More than 360 turns of people were locally trained in the field
of project management in cooperation with VINATOM and
V. OTHER RELATED WORKS (Cont.)
2.
Public information activities :
Hosting or co-hosting seminars in Ninh Thuan
province on subjects regarding nuclear power plant
safety, technologies, career opportunities for local
people when implementing NPP projects in Ninh Thuan
province, etc.
Organization of facility visits to Da Lat nuclear
research reactor for the local people and local
authorities;
Participation in local support activities in order to
consolidate and develop the friendly relationship with
the local authorities and communities, especially with
those who live in the project area via the active
involvement in local socio-political, cultural activities,
charity activities
Information provision to and cooperation with mass
media organizations
Participation in international and local exhibitions on
nuclear power in Hanoi and Ninh Thuan
V. OTHER RELATED WORKS (Cont.)
3.
International cooperation:
Cooperation with Russia:
A MOU was signed between ROSATOM and EVN on the 15th of
December, 2009 expressing the cooperation willingness of both
parties in construction of the first nuclear power plant in Vietnam.
On February 8, 2012, the MOU between Atomstroyexport and EVN
on cooperation during preparation period for construction of Ninh
Thuan 1 NPP was signed.
On November 21, 2011, the consulting service contract for
development of Site Approval Dossier and Feasibility Study of
Ninh Thuan 1 NPP project was signed in Hanoi between EVN and
the Consortium E4-KIEP-EPT
Cooperation with Japan:
On September 28, 2011, the Consulting services Contract for
developing Site Approval Dossier and Feasibility Study of Ninh
Thuan 2 NPP Project was signed between EVN and JAPC.
On September 29, 2011, the MOU for Ninh Thuan 2 NPP Project
was signed between EVN and JINED
Training courses/workshops provided and sponsored by
Japanese organizations such as JEPIC, JINED, JAIF, JNES...
V. OTHER RELATED WORKS (Cont.)
Cooperation with IAEA:
Under the TC project number VIE/4/015 chaired by MOST of
Vietnam, IAEA has cooperated and directly assisted EVN with the
following activities:
National workshop on nuclear power plant project management
Workshop on integrated management and safety culture
Workshop on NPP project funding and financing;
National workshop on public information for nuclear power
program
Expert Mission to Assist Vietnam on the Preparation of the
Request for Proposal of EPC Contract for the Nuclear Power
Project
Expert Mission to Review Report of “Human Resource Training
Project for Nuclear Power Plants in Ninh Thuan Province”
National workshop on grid-NPP interaction
Expert Mission to assist to develop environmental impact
assessment report in radiological effects
Expert mission/Workshop to assist the establishment of EVN’s
sitting team and working plan
IAEA has also provided supports to EVN’s experts in attending
workshops and training courses in other countries
THANK YOU FOR YOUR ATTENTION!