Alberta Airspace & Services Project
(AASP)
AOCM Presentation
Nov 30, 2011
Jim Strukalo – NAV CANADA Project Manager
[email protected]
1
AASP Goals
 To maintain or enhance the level of safety within the
new airspace system.
 To renew the airspace and procedures in Alberta and
update our systems in support of the new parallel
runway in Calgary,
 To update the NAV CANADA airspace system to take
full advantage of current and planned technologies
that will enable our customers to utilize the latest in
flight deck technologies and
 To complete the development and design of the
project by May 2013 for implementation and opening
of the new runway in May of 2014.
2
Calgary Parallel Runway Ops – May 2014
CYEG
CYYC
4
Collaboration
 Fully collaborative design process.
 Technical Design Working Group established, to facilitate the design
process
 Customer technical representatives (Pilots), Air Traffic Controllers and Planning
Specialists
 Additional consultation through individual and/or AASP group
meetings:
 Customers
 Air Carriers
 Oil Sands and Additional Corporate
 Flight Training and Recreational
 Airport Authorities
 Calgary, Edmonton
 Additional Stakeholders
 Adjacent Facilities – WG, VR, FAA (SEA, SLC)
 TC
 NAV CANADA Departments – AIS, Airspace Design Specialists, Procedures, Simulators
 Communities
5
Current Project Status
 Business Case – nearing completion
 4 Options Developed – based on bedpost design
 STARs for the 4 options in draft
 Circulated amongst Design Working Group
 Upcoming design meeting to get feedback on STARs
 Enroute phase of flight - designs work in progress
6
Near Term Next Steps
 Meet with Design Working Group to review YC
terminal designs.
 Finalize Option Cases – (4)
 Fast Time simulation of Option Cases to evaluate
efficiencies to Base Case.
 Narrow the design to 1 or 2 and focus on these for
final efficiency determination.
 Further business case analysis.
 Finalize Enroute portions of plans.
7
AASP Project Kickoff
6/1/11
Runway Opening
5/29/14
Stakeholder Meeting
6/23/11
Design Complete/Lockdown
5/31/13
Stakeholder/DWG Meeting
8/24/11
Final Bedpost Location
5/31/12
2011
' 11
Jun
2012
Oct
AIS Submission
6/3/13
2013
Feb
Jun
Oct
30 Day SMS Review
6/30/14
60 Day SMS Review
7/31/14
2014
Feb
Jun
Oct
Feb
Jun
' 14
Today
Design Development
6/1/11
5/31/13
SMS
6/1/11
Communications Planning
9/12/11
10/1/11
10/3/11
6/30/14
Aero Studies
5/30/14
2/28/13
Staff Planning TCU & Twr
5/30/14
Procedures Design
1/1/13
4/1/13
12/31/13
AIS Management & Q.C.
9/1/13
Training Design
1/1/14
5/29/14
4/30/14
Training Delivery 5/29/14
8
Edmonton Terminal Airspace
Review

Timelines - driven by CYXD and CZVL milestones.

Current Project Activities
 Stakeholder Identification
 Review of current airspace structure
 Identification of operational opportunities for both Customers and ANSP

Areas of Initial Consideration
 A review of the utilization of the airspace to the North and Northeast of CYXD; since RWY
16-34 has been closed.
 A feasibility review of resizing the size of Class C airspace, with the closure of CYXD, and
a goal of increased access to this airspace. i.e. the Chipman Soaring Area
 Assurance that any new approaches are kept within controlled airspace and the impact
this will have on future designs.

Collaborative Approach
 To determine requirements and constraints of Stakeholders.
 Communication and coordination for customer feedback is a project requirement.
9
Comments
Time to Update the System?
10