Root Barrier Installation Presentation

Download Report

Transcript Root Barrier Installation Presentation

ROOT BARRIER ™
PRESENTATION
WATERPROOF FLEXIBLE
CUTOFF WALL
Version 1.9 01.10.2011
www.rootbarrier.com.au
c
ROOT BARRIER ™
PRESENTATION
Click on these links to skip to different parts of the presentation. Alternatively view
the presentation as normal.
1. Product Overview \ Matric Suction
2. Sodium Bentonite
3. (UPGI) Under Path Growth Inhibitor
4. Design & Installation Guidelines
Below are links to supplementary documents CONTAINED ON OUR WEBSITE if
you do not have internet access these links will not work. You can request a
CD version by contacting ROOT BARRIER ™ on 1300 136644.
Technical Specs – includes technical information & product specification.
Material Safety Data Sheet for Sodium Bentonite.
BSA Advisory Guidelines and Fact Sheet for Contractors and Home Owners.
BSA Fact Sheet on Subsidence – Page 1, Page 2, Page 3, Page 4.
BCC Natural Assets Law
BCC Natural Assets Law Summary
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
Root barrier has many applications
Civil works; Back of kerb, bio swales, protecting infrastructure.
New houses; Stabilizing reactive clay under foundations,
Established houses; Buildings cracked by clay shrinkage can be restored by
isolating and stabilizing the moisture under the building.
Water proof cutoff walls; Stopping contamination migration through the soil.
Landscaping applications; Root group separation, hardscape protection.
Services protection; New innovation is pipe wrap to provide an insulation
layer around pipes and conduits.
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
Australian varieties of trees and shrubs use
large amounts of water in normal conditions.
This problem (known as Matric Suction),
especially combined with reactive (clay)
soils can cause substantial damage to the
foundation of buildings, walls, pathways
and roads.
After damage has occurred underpinning
of footings and more costly repairs (even
the most drastic demolition) is often the
only answer.
HOME
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
The Solution - The cut-off wall.
So what can be done to prevent damage in the
First place, or after the event to make sure it
Doesn’t re-occur.
The proven method is to construct a cut-off wall.
The cut-off wall effectively prevents tree roots
and also moisture movement, thus stabilising
the soil, and clay contraction and expansion
under the footing.
HOME
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
Traditionally the cut-off wall has comprised of
a 300mm trench filled with reinforced
concrete usually at a depth between 1 and 2
metres. These are generally difficult and thus
very expensive to construct.
Introducing Root Barrier - the cost effective
way to prevent root and moisture damage.
Root Barrier is the answer for moisture
stabilisation. This light weight plastic shield
(just 0.75mm thick) is especially designed
to form an impenetrable barrier against tree
roots and excessive moisture and damp.
HOME
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
Root Barrier is placed in a narrow trench,
which is dug around the building, normally to a
depth of 1 to 2 metres depending on soil type.
The narrowness of this trench means far less
mess and refill.
The trench is located 1 to 2 metres from the wall
of the building. This effectively extends the
foundations on which the building sits.
This impermeable barrier acts as a cut-off wall,
stopping the moisture leaching away from under
the buliding. The Root Barrier prevents
moisture moving sideways, through the
soil. Very little moisture loss can take place, and
thus future movement from this cause is
HOME
eliminated.
www.rootbarrier.com.au
c
PRODUCT OVERVIEW
WHY ROOT BARRIER™?
ROOT BARRIER ™ is a specially engineered waterproof cut-off wall.
IT’S WATERPROOF: ROOT BARRIER ™ is the answer for moisture stabilisation.
IT’S FLEXIBLE: Root Barrier has a 700% elongation and is able to handle hydrostatic pressure
resulting from moisture stabilization, root barrier insulates the protected area. In the dry period
the reactive clay out side the protected area will dry and shrink away from the cutoff wall,
“RIGID CUTOFF WALLS WILL BREAK AND FAIL” while root barriers 700% elongation is able
to handle these naturally occurring variations.
SODIUM BENTONITE is a vital part of the installation process. Sodium Bentonite is used to seal
the bottom of the trench and bind the bottom of the root barrier to the undisturbed soil.
HOME
www.rootbarrier.com.au
c
MATRIC SUCTION, WHAT IS IT?
Matric suction is the pressure dry soil exerts on the
surrounding soils to equalise the moisture content in the
overall block of soil.
Matric suction conditions in the soil profile (H site) were
obtained through steady state unsaturated seepage
analyses.
Fig10. Illustration of Example 2
The initial matric suction profile is the same, suction
varied from 409 kPa at tree root to 49 kPa at lower
boundary of the soil domain. The contours of changes in
matric suction are presented in Fig. 11. The closer to the
tree, the more change in suction is observed.
Fig 11. Contours of Final Matric Suction (kPa)
The results of stress deformation analysis are shown in
Fig 14 as contours of vertical displacement. A maximum
foundation settlement of 80mm and minimum settlement
of 25 mm was observed. A maximum settlement in the
soil profile took place at tree location and decrease with
horizontal distance and depth.
Fig 14. Contours of vertical displacements (mm)
HOME
Includes Extracts of Proceedings of Geo-institute Shallow Foundations and Soil Properties Committee sessions at the ASCE 2001 Civil Engineering Conference. (2001). Expansive Clay Soils and Vegetative
Influence on Shallow Foundations (pp. 36 - 37). Houston: American Society of Civil Engineers.
Page 7 of 10 (Overview)
www.rootbarrier.com.au
c
AS2870 – 2011 EXTRACT
REVISED STANDARD INCLUDES TREE EFFECT
Root Barrier for Moisture Control
Length
Sufficient to protect the structure from the effects of moisture change in
the soil. BSA guidelines consider the following distances as reasonable.
Structures closer than these distances to trees must be protected from,
or be specially engineered to withstand the effect of the tree/s.
Height of Tree(h) Distance from house (d)
d = 1 h for class H and M sites.
d = 1.5 h for class E sites.
d = 2 h for rows or groups of trees.
What does this mean?
The depth of ROOT BARRIER ™ /
moisture cutoff wall for protecting
foundations is determined by the soil
test data, and depths of 2, 3 and 4m
are not unusual.
c
MATRIC SUCTION, WHAT IS IT?
An example of bad design when repairing failed foundations.
This building has been repaired by filling and painting obvious cracking which
occurred during a dry spell. After two weeks of heavy rain edge heave occurred
under the building foundations. The results are obvious.
Had ROOT BARRIER™ been installed as part of the initial repair the moisture
content would be stable and the edge heave would not have occurred.
HOME
www.rootbarrier.com.au
c
MATRIC SUCTION, WHAT IS IT?
Examples
To the left are two examples of damage that
can be caused by Matric Suction.
Due to variations in moisture content under the
slab the corners of the structure have dropped
down as the clay shrinks.
Note: This property was underpinned 3 years
prior without root barrier.
ROOT BARRIER™ is now being installed as
part of the remedial works to stabilise the
house and the underpinning.
HOME
Page 9 of 10 (Overview)
www.rootbarrier.com.au
c
MATRIC SUCTION, WHAT IS IT?
HOW DO WE MINIMISE THE
SHRINKAGE OF REACTIVE CLAY?
By placing a 1.5 to 2 metre root proof and
waterproof wall around the structure that we
wish to protect. This will create an island effect
and keep the change in moisture content to a
minimum. Root barrier will effectively
disconnect the tree from the moisture under the
slab.
ROOT BARRIER is a flexible waterproof
Cut-off wall which will achieve both goals of
stabilising the clay an keeping the tree roots
away.
HOME
www.rootbarrier.com.au
c
EXAMPLES OF SUCCESSFULL
REMEDIATION
ANNERLEY STATE SCHOOL, JUNCTION RD — TWO JOBS
JOB 1 — These two photos show a neighbouring property effected by school
fig trees, Root barrier installed after Ministerial intervention in the dispute.
Installed 2003 customer happy.
HOME
www.rootbarrier.com.au
c
EXAMPLES OF SUCCESSFULL
REMEDIATION
ANNERLEY STATE SCHOOL, JUNCTION RD — CONTINUED
JOB 2 — place Root Barrier around school swimming pool to
stabilize foundations, fourth photo shows crack in brick wall is
closed and stable. Installed 2003 customer happy.
HOME
www.rootbarrier.com.au
c
EXAMPLES OF SUCCESSFULL
REMEDIATION
Private house, Frank Crowther, 42 Newcastle, Fairfield.
House cracked by moisture movement due to Jacaranda tree. Remediation job
completed 1993. House was renovated and landscaped last year. Photo of brick wall
shows crack is still closed after 17 years. Custom happy.
HOME
www.rootbarrier.com.au
c
SODIUM BENTONITE
Sodium bentonite is a naturally occurring clay material composed predominantly of the
active constituent montmorillonite. On exposure to water, bentonite exhibits high
swelling properties. Use is made of this in the sealing of porous soils where the
swollen mass fills the voids and binds the soil particles to create an impermeable sea.
Sodium bentonite is best suited to incorporation in coarse textured soils of clay content
less than 10% because of the relatively easy workability. In high clay soils,
incorporation is more difficult, both with respect to the placing of sodium bentonite and
to ensuing compaction.
Sodium bentonite is a vital part of the installation process. Sodium Bentonite is used to
seal the bottom of the trench and bind the bottom of the root barrier to the undisturbed
soil.
HOME
www.rootbarrier.com.au
c
UPGI – UNDER PATH GROWTH
INHIBITOR
A simple measure that ensures you’ll double the life expectancy
of your concrete paths around trees.
HOW IT WORKS
Under concrete moisture is trapped naturally, this provides a food source for the tree. Tree roots find the food and
transport it back to the tree, the root that finds the most food grows the biggest. Root Barrier™ Under Path Growth
Inhibitor creates a 50mm deep zone under the structure which is outside the pH range that trees like to feed on.
Roots in this immediate area will not develop to damage the path. The other roots will find a more
suitable food source allowing them to support and feed the plant.
This product is 100% natural with no manufactured chemicals and the same salinity as sea water. The product
is stabilised to prevent active components leaching from under the path.
DPI tested, certifying the product meets EPA guidelines protecting local environment. Not dangerous to handle
in normal circumstances, MSDS available.
INSTALLATION
1. Clear the damaged section, remove
existing roots in the vicinity and
prepare the subgrade as normal,
2. Pour the dry Under Path Growth
Inhibitor on to the exposed subgrade
and spread with a rake at a ratio of 10
Kg per m2 of subgrade.
3. Continue to lay the new path as
normal.
RESULT 50 mm deep zone
immediately below the treated area will
have a pH level outside the range
required by the tree.
HOME
www.rootbarrier.com.au
UPGI - PRODUCT ASSESSMENT
REPORT SUMMARY 16 Aug. 2010
c
Root Barrier’s Under Path Growth Inhibitor has undergone preliminary testing through DEEDI (Department of Employment,
Economic Development and Innovation). Below is a summary of the report prepared by Matt Roche Acting senior research
scientist, Agri-Science Queensland.
Objectives
To monitor the pH and electrical conductivity/salinity (EC) of the trial site prior toand following the application of the root growth
inhibitor treatment by the Client. The collected data will be provided to the Client within this, a preliminary report (16 Aug.
2010) and a final report (7 Jun. 2011).
Plate 1. Photos taken 2 August 2010 of (a) sample location A, under the current footpath and (b)
sample location B, adjacent to the footpath under the turf profile.
(a)
(b)
Sample AA
Sample
Sample A
Sample B
HOME
www.rootbarrier.com.au
UPGI - PRODUCT ASSESSMENT
REPORT SUMMARY 16 Aug. 2010
c
Root Barrier’s Under Path Growth Inhibitor has undergone preliminary testing through DEEDI (Department of Employment,
Economic Development and Innovation). Below is a summary of the report prepared by Matt Roche Acting senior research
scientist, Agri-Science Queensland.
Objectives
To monitor the pH and electrical conductivity/salinity (EC) of the trial site prior toand following the application of the root growth
inhibitor treatment by the Client. The collected data will be provided to the Client within this, a preliminary report (16 Aug.
2010) and a final report (7 Jun. 2011).
Plate 1. Photos taken 2 August 2010 of (a) sample location A, under the current footpath and (b)
sample location B, adjacent to the footpath under the turf profile.
(a)
(b)
Sample AA
Sample
Sample A
Sample B
HOME
www.rootbarrier.com.au
c
UPGI - PRODUCT ASSESSMENT
REPORT SUMMARY 16 Aug. 2010
Results -DEEDI soil testing
Results for testing on 8 June (Prior to placing treatment) and 2 August
2010 (Post treatment) using TPS smartCHEM-LAB meter.
Electrical Conductivity (EC) is
a convenient method for
measuring soil salinity. The bar
charts show June soil samples
in Black and August samples
in Green.
The graph below shows that
the Under Path Growth
Inhibitor did not leach into the
surrounding environment.
HOME
www.rootbarrier.com.au
c
DESIGN GUIDELINES
HERE ARE LINKS TO DESIGN & INSTALLTION GUIDELINES FOR TYPICAL ROOT BARRIER ™ APPLICATIONS
WITHIN THE PRESENTATION.
Design & Installation Guidelines – Moisture Control (inc Hydration System)
Design & Installation Guidelines – Moisture Control
Design & Installation Guidelines – As Part of a Foundation
Design & Installation Guidelines – For Contaminated Sites
Design & Installation Guidelines – Roads
Design & Installation Guidelines – Trees
Design & Installation Guidelines – Underground Tanks
Design & Installation Guidelines – UPGI – Under Path Growth Inhibitor
Design & Installation Guidelines – Root Barrier as a Pipe Wrap
Design & Installation Guidelines – Surface Finish Options for Root Barrier
Links to installation drawings CONTAINED ON OUR WEBSITE if you do not have internet access these links will not
work. You can request a CD version by contacting ROOT BARRIER ™ on 1300 136644: Moisture Control, Moisture
Control with Hydration pipe, Roads (Option A, Option B), Trees, Foundation, Underground Tanks, Pipe Wrap.
Links to supplementary documents CONTAINED ON OUR WEBSITE: Technical Specs , MSDS for Sodium Bentonite.
BSA Advisory Guidelines, Subsidence Fact Sheet Page 1, Page 2, Page 3, Page 4.
BCC Natural Assets Law BCC Natural Assets Law Summary
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
SIX CRITICAL POINTS TO SOLVE PROBLEMS WITH
TREE ROOTS, MOISTURE AND REACTIVE SOILS
1. PLACEMENT: Normal placement of the barrier is to locate it around the structure, out
from and parallel to the footings of the structure.
Try not to surround the tree. Our preferred method is placing the root barrier along beside
the building, path, road etc so that the tree roots cannot gain access to the structure.
Root barrier works as a waterproof seal protecting the soil under the structure from moisture
loss laterally. The structure prevents loss of moisture vertically and so the moisture content
of the soil can be stabilised and will stay reasonably constant. After installation the soil under
the building can be rehydrated to return it to the moisture content that it was when the
building was built
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
2. Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
3. Depth
Depth is determined by a civil engineer’s assessment of “the zone of influence” in the soil. In
“normal” reactive clay depths between 1500mm and 4 metres may be expected. on the other
hand if you strike rock at 700mm, the moisture cannot move through it then that is deep
enough.
4. Seal
Sodium Bentonite is used to seal the bottom of the trench and bind the bottom of the root
barrier to the undisturbed soil.
In summary take the barrier down to soil that nothing will move through and bind the root
barrier to it.
5. Length
Sufficient to protect the structure from the effects of moisture
change in the soil. BSA guidelines consider the following
distances as reasonable. Structures closer than these distances
to trees must be protected from, or be specially engineered to
withstand the effect of the tree/s.
Height of Tree(h) Distance from house (d)
d = 1 h for class H and M sites.
d = 1.5 h for class E sites.
d = 2 h for rows or groups of trees.
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
6. Top Finish
Root Barrier must be finished above the ground or sealed into concrete so that roots cannot grow
over the top of it. See options below.
HOME
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
INSTALLATION SYSTEM
1.Dig a trench a depth of 2m (unless noted
otherwise), insert ROOT BARRIER.
Ensure 50mm of root barrier is left above
finished ground height (this is to allow for
settlement and may be trimmed off later).
2. Trim exposed roots to leave a clean cut.
Treat with fungicide if required.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
INSTALLATION SYSTEM contd
3. Fill the base of the trench with a 50100mm layer of Bentonite, then backfill
to 50% of trench depth using spoil
from the trench.
Pipe Crossings. Ideally cut all services,
lay Root Barrier and cut small holes for
penetrations to reinstate services,
sealing crossings with sodium
bentonite.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
INSTALLATION SYSTEM contd
4. Place a 60Ø slotted hydration pipe
and then back fill the balance with
soil. The hydration pipe should start
3.0m from uphill end of trench with
200mm of pipe above ground. The
pipe is to drop vertically and turn 90
degrees finishing 3.0m from the end
of the trench.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
INSTALLATION SYSTEM contd
5. Provide slow running water to
hydration pipe and fill the trench until
the ground at the lowest point
becomes soggy. System will be
working if some closure of cracks
occurs. Repeat every second day
until recovery slows.
6. Cap end of hydration pipe and bury
just below surface (if problem recurs,
dig up pipe end and repeat process.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Curtain Wall
Moisture Control (inc Hydration System)
MOISTURE CONTROL BARRIER WITH
HYDRATION PIPE
1.
2.
3.
4.
5.
6.
7.
Excavate 75mm wide trench to a depth of 2m (unless noted
otherwise). Ensure that tree roots are cut without splitting or
tearing.
Place a layer of ROOT BARRIER™ in trench taking into
account installation guidelines. Leave top of barrier exposed,
50mm above finished height. (Trim later after trench settlement
ensuring finished height is such that roots cannot breach
barrier).
Provide a 50-100mm layer of dry sodium bentonite to the base
of the trench to bind the Root Barrier system.
Back fill to %50 of depth using existing soil.
Place a 60Ø slotted hydration pipe and then back fill the
balance with soil. The hydration pipe should start 3.0m from
uphill end of trench with 200mm of pipe above ground. The
pipe is to drop vertically and turn 90 degrees finishing 3.0m
from the end of the trench.
Provide slow running water to hydration pipe and fill the trench
until the ground at the lowest point becomes soggy. System
will be working if some closure of cracks occurs. Repeat every
second day until recovery slows.
Cap end of hydration pipe and bury just below surface (if
Guidelines Index
problem recurs, dig up pipe end and repeat process.
Page 8 of 8 (Moisture with
Pipe)
Print
HOME
www.rootbarrier.com.au
Design & Installation Guidelines –
Moisture Control
c
SIX CRITICAL POINTS TO SOLVE PROBLEMS WITH
TREE ROOTS, MOISTURE AND REACTIVE SOILS
1. PLACEMENT: Normal placement of the barrier is to locate it around the structure, out
from and parallel to the footings of the structure.
Try not to surround the tree. Our preferred method is placing the root barrier along beside
the building, path, road etc so that the tree roots cannot gain access to the structure.
Root barrier works as a waterproof seal protecting the soil under the structure from moisture
loss laterally. The structure prevents loss of moisture vertically and so the moisture content
of the soil can be stabilised and will stay reasonably constant. After installation the soil under
the building can be rehydrated to return it to the moisture content that it was when the
building was built
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Moisture Control
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
2. Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines – Moisture Control
3. Depth
Depth is determined by a civil engineer’s assessment of “the zone of influence” in the soil. In
“normal” reactive clay depths between 1500mm and 4 metres may be expected. on the other
hand if you strike rock at 700mm, the moisture cannot move through it then that is deep
enough.
4. Seal
Sodium Bentonite is used to seal the bottom of the trench and bind the bottom of the root
barrier to the undisturbed soil.
In summary take the barrier down to soil that nothing will move through and bind the root
barrier to it.
5. Length
Sufficient to protect the structure from the effects of moisture
change in the soil. BSA guidelines consider the following
distances as reasonable. Structures closer than these distances
to trees must be protected from, or be specially engineered to
withstand the effect of the tree/s.
Height of Tree(h) Distance from house (d)
d = 1 h for class H and M sites.
d = 1.5 h for class E sites.
d = 2 h for rows or groups of trees.
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines – Moisture Control
6. Top Finish
Root Barrier must be finished above the ground or sealed into concrete so that roots cannot grow
over the top of it. See options below.
HOME
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Moisture Control
ROOT BARRIER™ FOR MOISTURE
CONTROL
1. Dig a narrow trench to the required depth, insert
ROOT BARRIER™. Ensure Root Barrier is left
50mm above finished ground height. (This is to
allow for settlement and may be trimmed off
later.)
2. Trim exposed roots to leave a clean cut, treat
with fungicide if required.
3. Back fill the base of the trench placing the layer
of Sodium Bentonite, then backfill using spoil
from the trench.
4. ROOT BARRIER™ should be trimmed to just
below lawn mower height but above ground.
(Top of ROOT BARRIER ™ must be exposed on
completion.)
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Part of a Foundation
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
2. Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines – Part of a Foundation
3. Depth
Depth is determined by a civil engineer’s assessment of “the zone of influence” in the soil. In
“normal” reactive clay depths between 1500mm and 4 metres may be expected. on the other
hand if you strike rock at 700mm, the moisture cannot move through it then that is deep
enough.
4. Seal
Sodium Bentonite is used to seal the bottom of the trench and bind the bottom of the root
barrier to the undisturbed soil.
In summary take the barrier down to soil that nothing will move through and bind the root
barrier to it.
5. Length
Sufficient to protect the structure from the effects of moisture
change in the soil. BSA guidelines consider the following
distances as reasonable. Structures closer than these distances
to trees must be protected from, or be specially engineered to
withstand the effect of the tree/s.
Height of Tree(h) Distance from house (d)
d = 1 h for class H and M sites.
d = 1.5 h for class E sites.
d = 2 h for rows or groups of trees.
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines – Part of a Foundation
6. Top Finish
Root Barrier must be finished above the ground or sealed into concrete so that roots cannot grow
over the top of it. See options below.
HOME
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Part of a Foundation
ROOT BARRIER ™ INSTALLATION AS
PART OF A FOUNDATION
1. Dig a trench to the required depth, insert ROOT
BARRIER ™. Ensure 50mm of root barrier is left
above finished ground height (this is to allow for
settlement and may be trimmed off later).
2. Trim exposed roots to leave a clean cut. Treat
with fungicide if required.
3. Back fill the base of the trench with Sodium
Bentonite, then back fill with flow able fill to get
compaction.
4. Bring ROOT BARRIER™ up inside the
foundation formwork prior to pouring slab.
5. ROOT BARRIER™ should be trimmed to just
below damp course height but above ground.
(Top of ROOT BARRIER™ must be exposed on
completion.
Guidelines Index
Page 4 of 4 (Foundation)
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Moisture Control for Contaminated sites
Root Barrier™ can be used as a waterproof cut off wall to separate underground contamination from the
surrounding environment. We produce water proof cut off walls up to a seven metre depth and seal the
wall using bentonite.
Root Barrier™ flexible cut off walls are HDPE and have a 700% elongation which give the product a
unique ability to handle changing hydraulic conditions in the ground with out breaking, combined with a
bentonite seal we have an effective, practical and economic solution to prevent migration of moisture.
In house trenching equipment is capable of depths to 3 metres very economically, while excavators are
used if deeper depths are required.
We supply either material only or a complete installation service. Required depth is normally determined
by a geotechnical report. The Root Barrier™ wall is installed with a minimum of joins, preferably in one
piece.
Guidelines
Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
SIX CRITICAL POINTS TO SOLVE PROBLEMS WITH
TREE ROOTS, MOISTURE AND REACTIVE SOILS
1. PLACEMENT: Normally placed at back of kerb between the tree and road.
Try not to surround the tree. Our preferred method is placing the root barrier along beside
the building, path, road etc so that the tree roots cannot gain access to the structure.
Root barrier works as a waterproof seal protecting the soil under the structure from moisture
loss laterally. The structure prevents loss of moisture vertically and so the moisture content
of the soil can be stabilised and will stay reasonably constant. After installation the soil under
the building can be rehydrated to return it to the moisture content that it was when the
building was built
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
2. Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
3. Depth
Depth is determined by a civil engineer’s assessment of “the zone of influence” in the soil.
In “normal” reactive clay depths between 1500mm and 4 metres may be expected. on the
other hand if you strike rock at 700mm, the moisture cannot move through it then that is
deep enough. In “normal” soil 1000mm is regarded as sufficient (refer to guideline A). If back
of kerb protection is sufficient a 600mm barrier as per installation guideline B.
4. Seal
Sodium Bentonite is used to seal the bottom of the trench and bind the bottom of the root
barrier to the undisturbed soil.
In summary take the barrier down to soil that nothing will move through and bind the root
barrier to it.
5. Length
The length past the point at which the structure is showing signs of movement, as a
minimum at least sufficient to stop the roots going around the end of the barrier, normally
1 or 2 metres outside the drip line of the mature tree.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
6. Top Finish
Root Barrier must be finished above the ground or sealed into concrete so that roots cannot grow
over the top of it. See options below.
HOME
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
OPTION A – TYPICAL ROOT BARRIER ™
INSTALLED AT BACK OF KERB IN
NORMAL GROUND
1. Dig a trench to the required depth, insert
ROOT BARRIER ™. Ensure 50mm of root
barrier is left above finished ground height
(this is to allow for settlement and may be
trimmed off later).
2. In the base of the trench place a layer of pure
Sodium Bentonite 50mm to 100mm deep
then back fill.
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Roads
OPTION B – TYPICAL ROOT BARRIER ™
INSTALLED AT BACK OF KERB, FOR USE
ONLY IF ROAD BASE IS SOUND WITHOUT
CRACKS AND A GOOD SEAL CAN BE
ACHIEVED BETWEEN ROOT BARRIER ™ AND
ROAD BASE.
1. Dig a trench to the required depth, insert
ROOT BARRIER ™ into road base. Ensure
50mm of root barrier is left above finished
ground height (this is to allow for settlement
and may be trimmed off later).
2. If the barrier is to be placed back of kerb into
road base excavate a 100mm slot into
compacted road base, (not right through
base).
3. In the base of the trench place a layer of pure
Sodium Bentonite 100mm deep then back fill.
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
SIX CRITICAL POINTS TO SOLVE PROBLEMS WITH
TREE ROOTS, MOISTURE AND REACTIVE SOILS
1. PLACEMENT: Normal placement of the barrier is to locate it around the structure, out
from and parallel to the footings of the structure.
Try not to surround the tree. Our preferred method is placing the root barrier along beside
the building, path, road etc so that the tree roots cannot gain access to the structure.
Root barrier works as a waterproof seal protecting the soil under the structure from moisture
loss laterally. The structure prevents loss of moisture vertically and so the moisture content
of the soil can be stabilised and will stay reasonably constant. After installation the soil under
the building can be rehydrated to return it to the moisture content that it was when the
building was built
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
2. Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
3. Depth
Depth in reactive clay is determined by a civil engineer’s assessment of “the zone of
influence” in the soil. In reactive clay depths between 1500mm and 4 metres may be
expected. on the other hand if you strike rock at 700mm, the moisture cannot move through
then that is deep enough.
Depth in “normal” non-reactive soil is determined by aeration of the soil. In “normal”
undisturbed soil very little growth occurs below 1 metre.
4. Seal
Sodium Bentonite is used to seal the bottom of the trench and bind the bottom of the root
barrier to the undisturbed soil.
In summary take the barrier down to soil that nothing will move through and bind the root
barrier to it.
5. Length
The length past the point at which the structure is showing signs of movement, as a
minimum at least sufficient to stop the roots going around the end of the barrier, normally
1 or 2 metres outside the drip line of the mature tree.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
6. Top Finish
Root Barrier must be finished above the ground or sealed into concrete so that roots cannot grow
over the top of it. See options below.
HOME
Guidelines Index
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
ROOT BARRIER ™ PLACEMENT FOR
TREES
1.Dig a 100mm trench to required depth,
insert ROOT BARRIER. Ensure 50mm of
root barrier is left above finished ground
height (this is to allow for settlement and
may be trimmed off later).
2. Trim exposed roots to leave a clean cut.
Treat with fungicide if required.
Pipe Crossings. Ideally cut all services, lay
Root Barrier and cut small holes for
penetrations to reinstate services, sealing
crossings with sodium bentonite.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
INSTALLATION SYSTEM contd
3. Back fill the base of the trench
placing a layer of Bentonite, then back
fill using the spoil from the trench.
Guidelines Index
4. ROOT BARRIER ™ should be
trimmed to below lawn mower height
but above ground. Top of ROOT
BARRIER ™ must be exposed on
completion.
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines - Trees
ROOT BARRIER FOR TREES
1.Dig a 100mm trench to required depth,
insert ROOT BARRIER. Ensure 50mm of root
barrier is left above finished ground height
(this is to allow for settlement and may be
trimmed off later).
2. Trim exposed roots to leave a clean cut.
Treat with fungicide if required.
3. Back fill the base of the trench placing a
layer of Bentonite, then back fill using the
spoil from the trench.
4. ROOT BARRIER ™ should be trimmed to
below lawn mower height but above ground.
Top of ROOT BARRIER ™ must be exposed
on completion.
HOME
Guidelines Index
PRINT
www.rootbarrier.com.au
c
Design & Installation Guidelines – Surface finish
options for Root Barrier
Guidelines Index
HOME
PRINT
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Underground Tanks
ROOT BARRIER ™ USED TO PROTECT
UNDERGROUND TANKS
Root Barrier™ water proof cut off walls can be used to encapsulate underground tanks and
storm water control devices. The Root Barrier™ either to finish above the ground in the case
of a top entry tank or to cover the top in the case of a sealed and covered unit.
Following is a typical design for vertical root barriers when placed around the sides of the
tank, if you need to cover the top as well please call us to discuss the technical
requirements.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Underground Tanks
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Underground Tanks
STEP 1
• Remove any sharp objects that may damage
the barrier.
• Check density of embankment is hard enough
to stop roots growing around the bentonite seal.
• Surround tank by inserting ROOT BARRIER™
against side of excavation, ensure top is proud
above ground.
• Overlap start/finish, install ROOT BARRIER™
in one piece.
STEP 2
• Place 300mm of sand between the barrier and
the tank.
• Move top of barrier across gap to tank, create
void at base of barrier.
• Place bentonite between embankment and
barrier.
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
Underground Tanks
STEP 3
STEP 4
• Move barrier back to side of embankment,
ensure top is proud of ground.
• Place a spacer (20mmØ) vertically between
lapped ends.
• Fill sides with sand.
• Fill void around spacer with bentonite &
remove spacer.
• Complete top cover, ensure ROOT BARRIER™
is proud of ground.
• Trim ROOT BARRIER™ so that top is above
finished height.
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
UPGI Under Path Growth Inhibitor
1. Clear the damaged section, remove
existing roots in the vicinity and
prepare the subgrade as normal,
2a. For under concrete paths, pour the dry
Under Path Growth Inhibitor on to the
exposed natural ground and spread with a
rake at a ratio of 10 Kg per m2 of natural
ground.
2b. For under paving, pour the dry Under
Path Growth Inhibitor on to the exposed
natural ground and spread with a rake at a
ratio of 2.5 Kg per m2 of natural ground.
3. Continue to lay the new path as normal.
RESULT 50 mm deep zone immediately
below the treated area will have
a pH level outside the range required by the
tree.
Note: Not suitable for extremely wet areas.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
ROOT BARRIER™ AS A PIPE WRAP
Root Barrier™ pipe wrap is an evolution from our vertical Root Barrier™ cut off walls. The
problem of how to protect services from plants planted very near or directly above the
services location. A second consideration is the regular occurrence of roots tracking beside
services in the sand bed the pipe is laid on. Root Barrier™ has developed a simple,
economic and practical solution which provides a permanent root proof insulation layer
around the service.
Root growth will continue within the services trench, Root Barrier™ pipe wrap process will
insulate the service to keep the roots away by providing 100mm thick root proof zone around
the service.
Placement of Root Barrier™ pipe wrap is at the time the service is installed in the trench,
see installation guidelines on the next page.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
TREE CARE
• Working in from the ‘Drip Line’ (the edge of the leaves) the
closer you get to the trunk the more risk you have of
damaging or destabilising the tree.
• 50% of the distance from the drip line to the trunk of the tree
is regarded as the closest you can go without major risk to the
plant’s health. Consult an arborist if it is necessary to cut
closer.
Area of good soil that the plant will require to live a healthy life may be calculated by
multiplying the radius of the mature plant canopy by  r2 x .3m. The answer will give you the
cubic volume of good soil required. If works require the ground surface area is not available
for the plant, special pits filled with quality soils, drainage etc may provide the answer.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
Placement of Root Barrier Pipe
Wrap™ is at the time the service is
installed in the trench, the simple
process is;
1. Excavate the trench 200mm wider
than the service.
2. place Root Barrier in the trench in
a U shape, starting 2 metres before
the mature tree leaves begin and
finish 2metres past the edge of the
canopy. (an average tree requires 15
metres)
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
3. place 100mm bedding sand inside
the Root Barrier in the trench.
4. Install the service as normal.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
5. Pour some root growth inhibitor
onto the conduits.
6. Place bentonite seal at ends if
required.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
7. Cover the service with 100mm of
sand.
8. add balance of 55kg root growth
inhibitor per cubic metre of sand, on
top of the sand. Top up bentonite
seals if required.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
9. fold the Root Barrier flaps over to
overlap and cover the top of the sand.
10. Ensure ends of root barrier pipe
wrap are sealed with either duct tape or
bentonite to prevent root growth
inhibitor leaching into surrounding soil.
The service, root growth inhibitor and
sand are now completely encapsulated
within the Root Barrier envelope and
can not leach away or effect the local
environment.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER as a pipe wrap
11. Back fill to cover installation as normal.
Guidelines Index
HOME
www.rootbarrier.com.au
c
Design & Installation Guidelines –
ROOT BARRIER PIPE WRAP
BARRIER PLACEMENT
1. Dig trench for service to the required
depth.
2. Insert ROOT BARRIER™
3. Place 100mm layer of sand in the
channel.
4. Then the service.
5. Then cover to 100mm above the service.
6. Place ROOT GROWTH INHIBITOR at a
rate of 55kg per M³ of sand.
7. FOLD the sides of the ROOT
BARRIER™ down so that they overlap
and encapsulate the service and
insulating layer.
8. BACKFILL the trench as normal.
Guidelines Index
Print
HOME
www.rootbarrier.com.au
c
ROOT BARRIER ™
PRESENTATION
Here are links to supplementary documents on the internet.
Technical Specs – includes technical information & product specification.
Material Safety Data Sheet for Sodium Bentonite.
BSA Advisory Guidelines and Fact Sheet for Contractors and Home
Owners.
BSA Fact Sheet on Subsidence – Page 1, Page 2, Page 3, Page 4.
BCC Natural Assets Law
BCC Natural Assets Law Summary
Contact us
ROOT BARRIER (a division of Coulton Pty Ltd)
61 Somerset St
Windsor QLD 4030
ABN 38 085 138 674
Phone: 1300 13 66 44 or 07 3861 0141
Fax: 07 3861 0701
Email: [email protected]
Web: www.rootbarrier.com.au
The information contained in this presentation
reflects our best knowledge at the time of issue
and is subject to change without notice. No
warranty is expressed or implied other than by
law. We do not undertake any liability for the use
of our products and information.
HOME
www.rootbarrier.com.au