Payment claim
Download
Report
Transcript Payment claim
Administration
of payment claim
Magda Kariņa
Central Finance and Contracting Agency,
Senior Expert, Programme Management
and Supervision Department
01.- 02.02.2012
Payment claim
Payment claim template is approved by the Cabinet of Ministers as Annex to the national
Regulation on EU funds project budget planning, payment and expenditure declaration
management
Beneficiaries fill in the payment claim information using an empty template
Payment claim and supporting documents to CFCA can be submitted:
paper form (physical submission, mail)
submission via fax,
electronic submission (signed and scanned documentation in digital storage or signed
and scanned documentation via e-mail- only signed with safe electonic signature )
Payment claim’s confirmation
Performed after verification of expenditure supporting documents
Important:
Expenditure supporting documentation – selection or 100% check
Checklist
Process
From submission till confirmation - 20 wd
Payment claim’s confirmation in CFCA
Verification of the payment claim and supporting documents
If necessary, perform supporting document selection
Fill out the checklist
It has been developed in each institution based on MA defined principles of division of
verification checks between the desk checks and on the spot checks (main principles are in
MA guidelines)
What expenditure supporting documents must be
presented with payment claim?
Current progress report of the project – has been received and reviewed
Copies of
Bank account printouts, Accounts
Consignment bills
Product and service contracts, changes of it, if made
Approved construction project and construction permission
Certificate of acceptance
Decree, working-time balance, certifications etc.
Others, if necessary
Beneficiary present copies of documents. Originals are checked during checks on the spot
Documents about the procurement for the Project are checked during progress report check
Expenditure supporting document selection (1)
To confirm payment claim, not always we check expenditure supporting documentation
100% :
First and final payment claim – 100% check; for intermediate payment claim may be
applied a sample check
The goal of sampling is to use an objective and independent method to determine the
amount and number of transactions for detailed verification
The sample of supporting documents is selected basing on the acceptable error rate
Expenditure supporting document selection (2)
To define the acceptable error rate, first expenditure must be divided in following groups:
Reimbursement
Travel and business travel costs
Administrative costs (rent, electricity, maintenance and telecommunications services
and other expenses)
Expenses related to procurements and contract documents, including expenditure on
procurement below the thresholds
Expenditure supporting document selection (3)
The error rate is determined for each expenditure group = irregularities + expenses about
which beneficiary didn’t submit acceptable supporting documentation against approved
claimed and eligible funding for each expenditure group
The identified errors in each expenditure groups are classified as:
Low error rate (A) - the level of errors in the group ≤ 3%
Average error rate (B) - 3%< error rate in the group ≤ 5%
High error rate (C) - the error rate in the group > 5%
According to the error rate in each group we determine amount of transactions which we
must verify in the next payment claim:
Low error rate (A) – at least 10% of the particular group in the reporting period
Average error rate (B) - at least 50% of the particular group in the reporting period
High error rate (C) - 100% of the particular group in the reporting period
Expenditure supporting document selection (4)
To ensure equal opportunities for every random object to get in the overall sample for low
and medium error level, the selection is made in MS Excel :
Prepare a list of payments / employees
Determine the total amount of the costs in each group included in the payment claim
Apply random testing according to our previously set error rate and calculate starting
point using the formula
= ROUND(RAND()*(N-1) +1;0), where "N" is the number of payment / employees
Calculate the step - the inverse percent of the minimum amount of test: 10% - one in
ten; 50% - every second
You have to check every tenth or every second until it reaches the required amount
Payment claim’s confirmation checklist in CFCA
(1)
Formal check
Are the files/forms complete?
There is no missing documents?
Are documents signed by the person entitled to do so?
Is beneficiary/ project/ payment claim/bank account identification correct?
Payment claim’s confirmation checklist in CFCA
(2)
Application is correct
Tables are arithmetically correct?
The total eligible expenditure and its breakdown by financial sources specified within
table is equal to the information provided within the summary of the eligible expenses?
Expenses presented within the tables corresponds to the approved eligible costs of
respective activity?
All expenditure has been settled during the project, except in those cases, which are set
by the activity's Regulations issued by the Cabinet of Ministers?
PC does not include charges, which are:
related to the incompliance with conditions of agreement of project implementation or,
related to the incompliance with activity's Regulations issued by the Cabinet of Ministers
previously detected as not eligible
Payment claim’s confirmation checklist in CFCA
(3)
Expenditure is real
Eligible expenditure claimed within current payment claim complies with submitted
supporting documentation?
Payments within payment claim are actually paid out and they have appropriate
supporting documentation, which complies with the agreement?
Products and services are delivered – information about fixed assets is correct, if
replaced, they fully meets the project's initial targets and provides the fulfillment of
planned results of the project?
Payment claim’s confirmation checklist in CFCA
(4)
Grant contract specifications are respected
Is claim without roundings, miscalculations?
Is budget not overrun?
Are budget lines respected?
Are Indicators and goals achieved (final payment)?
EU fund beneficiary has carried out procurement for the Project purposes according to
the requirements of laws and normative acts of Latvian Republic
Payment claim’s confirmation checklist in CFCA
(5)
There is an indication whether the revenue has been generated during the Project
implementation
Information about VAT report is correct?
Check of the progress report – if there are deficiency, it doesn’t affect the payment
claim
Information from IS about major errors detected during checks on the spot visits does
not impact refunding of the PC (if applicable)
Payment claim’s confirmation checklist in CFCA
(6)
The check of supporting documents (copies) of expenses included within PC have been
submitted and verified for the following cost items:
Reward, including the employer's social insurance contributions (SIC)
Business trip expenses, including travel expenses
Transport costs (the cost for fuel, public transport, vehicle rent or transport services)
Telecommunications and Internet costs
Stationery costs
Room rental and maintenance costs (heating, electricity, management services, water supply)
Expenditure for the purchase of office equipment, in order to support administrative activities
of the project
Publicity and representation expenses
Insurance costs
Expenses for equipment, supplies and technology
Costs for construction of buildings, structures, infrastructure and real estate purchase costs
Other expenses, if applicable
Amendment
Project manager can manually correct insignificant mistakes in beneficiaries payment claim
Also beneficiary can send in amendments – only few pages or all the payment claim (if the
last one occur – the first payment claim is asked to be revoked)
Challenges for improvement of payment claim process
To introduce the possibility for beneficiary to enter the payment claim directly in MIS
(using the electronic signature)
To enhance usage of sampling in payment claim verification process
Thank you!