Transcript A New High School - Uintah School District
Enrollment Growth Meetings
February 2012 Superintendent Mark Dockins
Presentation Purposes
Why the need for a change?
What are some proposed solutions?
How much will the proposed solutions cost?
When can the proposed plans be operational?
What is prompting this need for a change?
Explosive Enrollment Growth
Uintah was the fastest growing school district in the state last year at 4.6%.
Uintah continues to show enrollment growth even while other counties and states are in economic decline.
Our senior class this year has 391 students which started with 451 Kindergarten students.
This year our Kindergarten class has 726 students.
Our Kindergarten class for next year is projected to be 785.
2006-2012 Enrollment History
9000 8500 8000 7500 7000 6500 6000 5500 5000
Enrollment Projections School East Side Elementary Vernal Middle Vernal Jr. High Uintah High School *Calculated with a three year average *Calculated with a five year average Oct 2011 Capacity Enrollment 3500 2860 1000 928 1000 1500 870 1133 Oct 2012 Enrollment *3071 *971 Oct 2015 Enrollment *3682 *1239 *1010 *1131 *1110 *1302
What are some proposed solutions?
Four Possible Solutions
Adopt a Year-Round School Schedule Build additions onto Vernal Middle and Vernal Junior High Schools to increase capacities Bond to build a new high school, move 9 th up to the high school level and change the configuration at VJH/VMS graders Complete Current 10 year plan with an addition at UHS to accommodate 9 th graders and change the configuration at VJH/VMS
Year-Round Schooling
More efficient use of building Research suggests it benefits At-Risk students On-going costs:1M Logistics of Scheduling
Additions at VJH/VMS
Cost is not within scope of 10 year plan Both schools have already been remodeled recently How large do we want a middle school or junior high?
Auditoriums, cafeterias, hallways, safety, space for addition at VJH?
New Configuration with High School
K-5 Elementary schools Two 6,7,8 middle/junior high school Grades 9-12 high school
What Supports the Configuration of moving 9 th Grade to High School?
Enrollment growth Curriculum and activity needs match better with a 6/7/8 school vs 8/9 school 9 th grade credit/counseling Academic interventions More efficient use of personnel and resources with 9 th grade at high school: Performing Arts CTE/ATC/Concurrent Ed
UHS: Last School in Ten Year Plan The scope of the ten year plan for the bond was to remodel UHS. Within the scope of the remodel there are issues with stadium, cafeteria, auditorium and all mechanicals. This is planned to be a two year project and is anticipated to be in the 20M range.
An addition to handle capacity could be accomplished without raising taxes.
Fiscal Responsibility
A New High School Smaller high school atmosphere More opportunities for students to participate in certain activities How large do we want Uintah High School to be?
Cost: Expense of building and purchase of property Expense of operating a new high school: duplication of everything a high school needs Double the travel and expenses for extra-curricular/routes Lose identity of a single high school community
Cost of Proposals
Year-round School: 1M increase in operational costs Additions to VJH/VMS: 4.5 M Reconfiguration with New High School Bond (50 to 60 M) Property Building Leeway (6M) Maintenance and Operations Reconfiguration with UHS Expansion (3.5 M to add classroom capacity) UHS is last school on the ten year facilities plan and we can handle the cost of the remodel without bonding and raising taxes Can be accomplished within the scope of the current ten year plan and funding
When will the proposed changes be implemented?
1.
Year-round School: 2013-14 2.
VMS/VJH Additions: 2014-15 3.
UHS Addition: 2014-15 4.
New High School: 2015-16
Thank you for your attendance. We appreciate your interest in what we are trying to accomplish.