SDC Bangkok Thailand SKH 23März2012

Download Report

Transcript SDC Bangkok Thailand SKH 23März2012

Swiss Humanitarian Aid
Thailand Floods 2011
Nov. 2th, 2011 – Nov. 11 th, 2011
SKH– Swiss Humanitarian Aid Schweizerisches Korps für Humanitäre Hilfe
Swiss Humanitarian Aid
•
•
•
•
•
Gerard Luyet, Hydrologist (WES) Responsable de l'activité Eau Potable SIG Genève
Claudio Valsangiacomo, PhD, Microbiologist (WES) Schweiz. Fachhochschule Gesundheit Tessin
Urs Nigg, Civil Engineer (DRR, Flood Management), Abt. GeP / BAFU
Philipp Teysseire, PhD, Civil Engineer (DRR, Flood Management), Ing. Büro T&C, Visp
Thomas Fisler (HA Coordinator), Bangkok
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Chao Phraya River
160‘000 km2
MQ: 883 m³/s
Q=3‘500 - 4000 m³/s
Flooded area November
2011
Swiss Humanitarian Aid
Facts
• Inundation triggered by monsun
• Affected population 23 Mio.
• Casualities 400 (Flooded area 60‘000 km2 ,
approx. 12 % of Thailand)
• Biggest flood in Thailand for 50 years
• Damages 11.8 Mrd. Euro
• Effects on world economy (Computer /
Harddisks- and Automobile Industries)
Swiss Humanitarian Aid
ACTIVITIES Nov. 3 - 9:
• Assessment to Bhumibol Dam, flight over flooded area
• Ground inspection of flood affected areas in North East and
Western Bangkok and coastal pumping stations,
• Site visit on construction works of big bag dam
• Water quality testing in and around greater Bangkok and
treatment plant
• Inspection of general conditions and water quality at Evacuation
Centres
• On site inspection Interaction with focal points and experts at
FROC (Flood Relief Operation Center)
• Meetings with staff of Ministry of Public Health
• Discussion/Evaluation on flood modelling computer simulation
Swiss Humanitarian Aid
Irrigation system around
Bangkok
Don Muang Airport
Inner Bangkok
Suwarnabhumi Airport
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Big bags along Defense line
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
Swiss Humanitarian Aid
FINDINGS ON FLOODWATER MANAGEMENT:
• The resilience and humanitarian disaster response in dealing
with the flood by everyone is outstanding
• The current event is considered as a natural disaster with a rare
probability
• The scale and magnitude of the floods exceeds a controlled
water management: damage control, humanitarian response
and asset preservation is the only option
• The concept of diverting the floodwater to the Eastern and
Western side of inner Bangkok is correct
• The influence of the built up area on the flood is only locally
relevant (Anthropogenic effects)
Swiss Humanitarian Aid
FINDINGS ON FLOODWATER MANAGEMENT:
• Drainage and retention infrastructures are not designed for
such large scale floods
• At present no accurate predictions of floodwater inundations
can be done
• Inflow of water towards inner Bangkok areas are still high
• King’s dyke and immediate dam reinforcement measures taken
are crucial to manage actual and further floods
• The impact of the flood will be long term and risk reduction
measures must be addressed long term
Swiss Humanitarian Aid
CONCLUSIONS:
• The flood level in downtown inner Bangkok is assumed to be at
very low intensity (if at all less than 30 cm)
• Existing and additional spot measures (sandbags, mobile
pumps) reduce the impact of further damages significantly
• The outer areas will be flooded for several days and weeks
• Emphasise on maximum pumping capacity to reduce further
flooding and drain off the existing inundations
• No additional technical options are identified to optimise the
chosen strategy
• The existing infrastructures need to be adjusted to minimise the
risk on future floods (long term floodwater management)
Swiss Humanitarian Aid
RECOMENDATIONS:
Short term:
• Continue to verify and monitor the protective measures of the
Suvarnabhumi airport as a priority
• Unaffected industrial areas require specialist expertise to advise
on immediate localised protection measures to avoid flooding
(inflatable flood barriers, sandbags, pumps)
• High priority towards all required measures to maintain
unhindered access of the Highway to the South
• Communicate preventive steps and alert areas within the
possible path of the flood as early as possible
• Maintain and monitor the inner city Klongs, install additional
pumping capacity if not already enforced
Swiss Humanitarian Aid
RECOMENDATIONS:
Medium term:
• Further develop emergency preparedness plans :
• Weather forecast and early warning/information to all
relevant Departments
• Organise network on floodwater management, intervention,
rescue and assistance services during extraordinary
situations
• Incident documentation of the current floods in order to draw
lessons learnt
• Expand currently developed floodwater modelling and
simulation to identify required measures
Swiss Humanitarian Aid
RECOMENDATIONS:
Medium term:
• In depth study required to identify various options for adaptive
design on sustainable flood protection, if not already enforced
• Create a solid financial base to ensure the needed sustainable
measures
Longer term:
• Further develop of an integrated risk management of all natural
dangers in Thailand
• Establish a sound risk management dialogue of all stakeholders
Swiss Humanitarian Aid
Meeting with Prime Minister Yingluck Shinawatra, Nov. 10, 2011
Activities
Swiss Humanitarian Aid
Thank you !