Transcript Juraj Sabol - CIRED • International Conference on Electricity
Frankfurt (Germany), 6-9 June 2011
Grid Operational Efficiency Project HIFFI (WfM implementation)
Kosice, May 2011 VSE a.s., Košice, Slovakia
Marian Mester, head of Grid operation Juraj Sabol , head of IT and telco mamagement section
Company Profile
energy utility company member of the RWE Group since 2003 more than 605 000 points of delivery mission = provide reliable and complex services which correspond to the needs of customers sold more than 3,2 TWh in 2010 average number of employees = 1,575
Shareholders
Frankfurt (Germany), 6-9 June 2011
National Property Fund: RWE:
51 % 49 %
Distribution area: 16 221 km 2 HV Lines: 1 274 km HV & MV substations: 56 MV Lines & Cables: 8 207 km MV/LV Distribution stations: 4 974 LV Lines & Cables: 10 986 km
Frankfurt (Germany), 6-9 June 2011
Implementation of workforce management system with several aims
(Part 1)
: Efficiency / Productivity
Operational excellence
/ Reduction of operational costs / Cost transparency Implementation of
workflow-system
for systematic, fully
standardized and asset condition oriented maintenance
Optimal
allocation of human and production capacities
Optimal distribution of
working orders related to priorities
,
geographical location
, optimal
time reaction
in case of outage / failure 3
Frankfurt (Germany), 6-9 June 2011
Implementation of workforce management system with several aims
(Part 2)
: Regulation / Grid Quality / Renewal of Grid Assets
Grid quality
: improve SAIFI and SAIDI
Reduction of critical assets
(asset in bad technical conditions) by condition and risk based maintenance Asset
operational safety
High quality and actual
data of asset conditions
support short and mid-term CAPEX / OPEX planning Reasonable
allocation of financial means
for asset renewal (CAPEX / OPEX)
Reduction of
numbers of
used IT systems
(registers of asset conditions, planning of maintenance activities, ...)
Standardization of IT landscape
(unified integration platform)
Frankfurt (Germany), 6-9 June 2011
Long term preparation for WfM project Grid Organization
One grid unit (aprox 250 people) fully responsible for HV/LV : HV/LV grid maintenance Power failure HV/LV repairs Off take management 24 x 7 emergency service
Solid IT background
Implemented GIS containing detailed technical records of electricity distribution devices (VHV, HV and LV devices) SAP as a source of grid economic data GIS fully integrated with SAP (GIS is master)
Frankfurt (Germany), 6-9 June 2011
Workforce management as tool for efficient grid services being implemented Status 2008
Grid services operation without IT support, workforce coordination done by daily orders Necessity to optimize and increase efficiency has led to implementation of work force management as of 2009
1 st phase 2009 - 2010 2 nd phase 2011 3 rd phase 2012
Content Pilot project finalization (in one region)
Target asset: distribution transformer stations
(MV/LV) Project roll-out to all regions
Target assets: MV-grid
Interconnection WfM system with SCADA Lessons learned / Expectation Basic processes setting Mobile devices experiences Standardization of MV maintenance activities Higher data quality and actual data of MV-asset condition
Project finalization
Target assets: LV grid + Metering Full operation of WfM system (all voltage levels)
Systematic and fully standardized
asset condition maintenance Reasonable allocation of financial means 6
Frankfurt (Germany), 6-9 June 2011
Implementation of workforce management system as single system for grid operation and maintenance : IT platform - Primary systems SAP- ISU SCADA IBM MAXIMO
Off – takes management Outage management
Grid operation and maintenance WfM based on IBM Maximo Real time operated Real time integrated with other systems
Grid Maintenance Despite complex IT implementation, go-live expected in 3Q 2011
VSE as innovative first mover in CEE
7
Frankfurt (Germany), 6-9 June 2011
Workforce management system as a top decision support system for MV/LV based on other systems in VSE IT pool
8
Frankfurt (Germany), 6-9 June 2011
WfM is integrated with important IT systems in real time SCADA
(OMS)
GIS GPS Archive server HIFFI SYSTEM IBM Maximo Forms server GSM networ k SAP PM
(ERP)
SAP HR Attend.
system
Mobile clients (tablets) implemented planned 9
Frankfurt (Germany), 6-9 June 2011
HIFFI project - status quo (31.05.2011) Time schedule of HIFFI project
Project preparation: detail process analysis, definition of project goals, technical specification, tendering documentation etc.
Procurement process Business Blueprint Business Blueprint approval 1st phase: Pilot project implementation (Region Humenné) 2nd phase: Testing of system funcionality (MV-grid+DTs) 2nd phase: Roll-out (MV-grid+DTs) 2nd phase: full operation (MV grid+DTs) 3rd phase: Business Blueprint (LV-grid+Metering) 3rd phase: Implementation (LV-grid+Metering) 3rd phase: Testing (LV-grid+Metering) 3rd phase: Go Live (LV-grid+Metering)
2008 2009 2010 2011 2012
1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 1Q 2Q 3Q 4Q 10
Frankfurt (Germany), 6-9 June 2011
Project HIFFI – example of benefits The grid operation organization before HIFFI The organization having HIFFI Region „B“ Region „A“ Region „D“ Region „C“
Regions / 4 x
Sub-Regions / 12x
Operational Service Points / 26 x
Regions / 1 x
Sub-Regions / 8 x
Operational Service Points / 24 x