The ecar Ireland Project

Download Report

Transcript The ecar Ireland Project

The ecar Ireland Project

Smart Grid Technology Watch Event September 18 th 2014 John Whelan, ESB ecars

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

2

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

3

Ecar Ireland Program

• • • •

Government targets 2020

- 10% of all vehicles electric - 10% of all road energy transport will be renewable

Early supply of electric cars

MOU signed with Mitsubishi , Renault-Nissan and Toyota

Government incentives

€5000 grant Zero VRT Lowest road tax band Accelerated Capital Allowance (Businesses) Government taskforce to deliver other incentives

ESB is rolling out the infrastructure www.esb.ie/ecars

4

Ireland as a Test Bed for Electric Vehicles

• Large wind penetration • Limited range between cities • Type of homes • Good climate for batteries • Single network company

www.esb.ie/ecars

5

CO 2 Emissions Internal Combustion Engine Electricity Generation COAL GAS WIND End of chain emissions 2010 150 g/km 2015 130 g/km 130 g/km 50 g/km 0 g/km www.esb.ie/ecars

6

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

7

Electric Vehicles in ESB’s Fleet Old Electric Vehicles from 1950 - 1970 Current Electric Vehicles – Allied Peugeot / Micro-vett Fiat Fiorino / Smiths Edison www.esb.ie/ecars

8

Electric Vehicles Available in Ireland Mitsubishi iMiEV Nissan Leaf Mitsubishi Outlander Renault Kangoo Renault Zoe BMW i3 www.esb.ie/ecars

9

Other Electric Vehicles in Ireland Smiths Newton (Celtic Linen) Smiths Newton (Grange Builders Providers) Smiths Newton (OPW) www.esb.ie/ecars

10

All Major Car Manufacturers Have EV Programs www.esb.ie/ecars

11

EV Components Battery Pack Inverter Charger + DC-DC Converter AC Motor www.esb.ie/ecars

12

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

13

Charging Infrastructure HOME / WORK PUBLIC FAST 6 – 8 hours 1 – 2 hours 80% in 20 minutes www.esb.ie/ecars

14

Home Charge Points First 2000 installed for free 16/32 amps, single-phase Fed from customer distribution board www.esb.ie/ecars

15

Public AC Charge Points

22kW double socket (three-phase 32 amps) RFID card reader GPRS communications with back office Internal MID metering

www.esb.ie/ecars

16

Fast Charge Points

DC –

CHAdeMO

50kW DC/AC –

CCS

50kW

Fast AC

– 44kW

www.esb.ie/ecars

17

Ireland’s Current Charge Point Network 851

– Domestic and Commercial Charge Points

805

– AC Public Charge Points

61

– Fast Charge Points

1717 - Total www.esb.ie/ecars

18

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

19

Back Office www.esb.ie/ecars

20

Agenda

• • • • •

The ecar Ireland Project – Conception Electric Vehicles in Ireland Charge Point Infrastructure Charge Point Management System Grid Impacts www.esb.ie/ecars

21

Power Quality Measurements www.esb.ie/ecars

22

Charging Profiles (Slow AC) – Nissan Leaf Current Profile

20 16 12 8 4 0 10:30 11:56 13:22

Time

14:49 16:15 17:42

Power Factor Profile

1 0.98

0.96

0.94

0.92

0.9

10:30 11:56 13:22

Time

14:49 16:15 17:42 2 1.8

1.6

1.4

1.2

1 10:30 11:56

Voltage Harmonics Profile

13:22

Time

14:49 16:15 17:42

Current Harmonics Profile

16 12 8 4 0 -4 10:30 11:56 13:22

Time

14:49 16:15 17:42

www.esb.ie/ecars

23

Charging Profiles (Fast DC) – Nissan Leaf – DBT FCP Current Profile Power Factor Profile

70 60 50 40 30 20 10 0 15:12 15:23 I1 15:35

Time

I2 15:46 I3 15:58 1 0.8

0.6

0.4

0.2

0 15:12 15:23 15:35

Time

15:46 15:58

Current Harmonics Profile Reactive Power Profile

30 25 20 15 10 5 0 15:12 15:58 0 -5000 15:23 I1 15:35

Time

I2 15:46 I3 -10000 15:12 15:23 15:35

Time

15:46 15:58

www.esb.ie/ecars

24

Macro Level Grid Impacts www.esb.ie/ecars

25

Thank You