NorthWestern Energy – Rick Edwards
Download
Report
Transcript NorthWestern Energy – Rick Edwards
Montana Ambassadors
Helena, Montana
February 25, 2011
Our Operations
Service territory includes Montana, South
Dakota, Nebraska, and Wyoming
661,000 customers
Electric
» 31,700 miles of transmission & distribution
» 297 communities
Natural Gas
» 8,400 miles of transmission and distribution
» 168 communities
Employees – 1,354
2
Montana Operations
Service territory includes western 2/3 of
Montana (107,600 square miles)
Electric
» 21,400 miles of distribution
» 7,000 miles of transmission
» Peak load -1,766 MW Average load – 1,216 MW
Natural Gas
» 4,100 miles of distribution
» 2,000 miles of transmission
» Total delivered – 40 BCF Peak Daily – 335,000 dkt
Employees – 1,037
3
Our transmission developments…
Why
Transmission Growth?
4
Western States RPS Requirements
5
5
Opportunities - Potential Wind Distribution
6
6
Montana is between resources & loads
7
Our transmission developments…
Purpose, Benefit, and Need
Meets NWE’s Federal Energy Regulatory Commission
(FERC) requirement to respond to new transmission
service requests
Provides transmission for new generation development
Enables the development of high quality MT wind power to
reach market
Provides and enables positive economic impact to
Montana, Idaho and the region
Improves electric system performance and flexibility
Meets the needs of regional electrical demand
8
NWE proposed transmission projects
Collector System
Colstrip Upgrade
MSTI
9
Mountain States Transmission Intertie (MSTI) Project
500 kV AC line from Townsend
MT to Midpoint Substation
near Twin Falls ID
Approximately 430 miles
depending on final route
1130 miles of alternatives
» 80+% on State and Federal
Public Lands
Advanced Stages of Public
Siting and Review – began in
2007
1500 MW Path Rating Capacity
Expected
Current Project cost is $1
billion
10
10
Montana Renewable Collector System
Currently
4,000 MW in
generation
interconnectio
n queue
Radial lines to
Townsend
Access to
MSTI, 500 kV
and NWE
network
MT-RCS
defined by this
Open Season
Potential
Collector Lines
New Townsend
Substation
High Wind
Area
Target in
service date is
2016
Confidential
11
Colstrip Upgrade
The project is currently being developed
primarily by BPA and NWE with the other
owners having various levels of interest.
Initially identified in transmission study as being
a piece of “low hanging fruit”
No new linear facilities required
12
Gas Operations
13
Gas Facts
Four major pipelines cross from Canada into
Montana
Carway, Aden, Canadian Montana Pipeline and
TransCanada (CMPL is owned by NWE)
Havre – Havre Pipeline and Chinook pipelines
tie to Many Islands Pipeline
Morgan/Monchy – Northern Border cross
Montana heading to the Mid-West
» 485 BCF per year of imports
14
Gas Facts
Carway and Aden come into NorthWestern’s
transmission line, and the 15 BCF of imports
equals about 38% of our 40 BCF annual market.
15 BCF at the average price of $3.90/mcf in 2010
would be $58.5 million
Montana produces about 95 BCF and consumes
76 BCF with most of the difference going into
Canada or Northern Border.
15
Questions ????