FCP-Modify - Openreach

Download Report

Transcript FCP-Modify - Openreach

FCP-Modify – High level Process &
Illustrative Examples
Gary Williamson
Openreach LLU Technical Development Manager
Version 1 – 15th April 2013
Introduction

FCP-Modify is about getting more from existing LLU infrastructure through
rejuvenation and in-life upgrade:
 May be considered for any existing ‘pre-FCP’ PoP type.
 Firm order acceptance is always subject to survey. For some PoPs,
physical expansion may not be possible due to the presence of
surrounding equipment belonging to other customers or BT. Openreach
will offer what is possible for customer consideration.
 Can help improve service continuity through greater power resilience.
 Offers more for the customer – eg ‘Customer Use Cabinet’ (CuC).
 Lowers DC energy costs due to >95% power efficiency (cf 89%-92%)
 Can help customers to prepare for consolidation of their LLU estates.
Key Points
1. It is important that:
1. Prior to APO placement there is a customer / Openreach dialogue to agree
and document the customer requirements to be met.
2. Following receipt of an APO in which multiple similar PoPs are to be
upgraded, the work is undertaken as a programme. This will help to ensure
consistency of delivery for the customer.
3. Customers have a person who is the primary point of contact for FCP-Modify
orders over the end-to-end delivery process.
2. A ‘rack face’ map will be created for added cabinets and added rack spaces.
This will help the required positions of ethernet fibre and equipment to be
thought through and defined by the customer.
3. In some cases the APO survey will find that there is insufficient suitable space
and/or ac mains power capacity to satisfy the customer’s requirement.
Openreach will seek to offer an alternative based on what appears feasible.
Definitions – Categorisation for APO

FCP-New Build is the provision of a new PoP in response to a customer order.

FCP-Modify is the means to upgrade an existing ‘pre-FCP’ LLU PoP such that is
subsequently treated as an FCP installation for billing and future upgrade path purposes.






Will always include provision of at least one new FCP DC Power System.
Will always replace any existing Openreach maintained DC system(s).
Is not offered in ‘AC Only’ form.
May include additional rack space units (RSUs), Customer Use Cabinets and HDF racks.
Is always subject to survey for space and ac power supply capacity reasons.
Is always the subject of customer requirements document produced by the Openreach LLU Technical
Development Team for customer approval and having an solution code.

FCP-Refresh applies to an existing FCP installation for the incremental increase or decrease
of power capacity and/or the provision of additional features within the original physical
footprint / expected future maximum power envelope (eg Add an HDF / HDF sub-racks,
supply and install a Customer Use Cabinet). Does not entail re-engineering of the PoP.

FCP-Augment will entail re-engineering of an in-life FCP PoP to increase its spatial and/or
maximum power capacity envelope beyond the original expected future maximum.

LLU-Regrade applies to any Non-FCP LLU PoP and encompasses changes of a minor
engineering nature within the existing design limits of the relevant product type.
Customer Requirements Definition
The embedded document is the blank template to be completed for each new
customer requirement that arises. One document may apply to many or few LLU
PoPs of a given type.
Dialogue with the customer may entail a degree of iteration as actual requirements
are confirmed and the associated indicative pricing is understood.
Once agreed, a PDF version of the Customer Requirements Definition paper will be
stored and made available for use by the Openreach Plan & Build and EIPB teams.
Each approved requirement will result in a “Solution Code”.
The customer will then be able to place APOs quoting the solution code on one or
many occasions.
FCP-Modify Pre-build process
Start
Customer & Openreach
SRM / LLU tech team
discuss and agree the
customer’s requirements.
Dimensioning detail
provided for LLUMS ‘wizard’
LLU Technical Development Team produces
LTDP document (PDF) defining the customer
requirement and indicative pricing.
Document is given an solution code and
published internally once agreed with the
customer, EIPB and the APO Team.
Solution Code at ‘Agreed
for APO’ status is notified
to customer to enable APO
placement
Customer places APO
quoting the relevant
Solution Code
Equipment
layout issued
Openreach / EIPB APO survey(s)
scheduled.
Yes
Proceed to order
delivery planning.
Customer
confirms
firm order?
No
Bill applicable
charges & Finish
Solution
recorded and
published
internally.
Use relevant
solution
document
APO survey work is
undertaken and the
results with floorplans
are returned to the
Openreach P&B team.
Openreach P&B team
prepares an ‘Art of the
possible’ survey
response for technical
sign-off. An Openreach
response is then
returned to the customer
for consideration
FCP-Modify – Delivery Planning
Start
Delivery planning
for firm build
order(s)
Job completion QA
and handover
documentation into
Openreach P&B.
PIRM updated.
MUA RFI date(s)
confirmed
Recovery of
redundant
equipment is
undertaken in
accordance with
agreed scope of
works.
New equipment
installation date(s)
confirmed
Changeover activity
is undertaken to
transfer customer
power loads onto the
new FCP power
system(s). Customer
confirms service is
OK
Delivery Manager liaises
with customer to agree
installation and
changeover date(s).
Confirms work activities
involved and roles.
On-site installation work is
undertaken up to the point
of changeover from old to
new.
On-site delivery – a virtual single visit engineering undertaking
Handover Pack
issued to customer.
Customer Handover
– virtual or attended.
Billing activity
undertaken inventory
and verified
Order is
complete.
Finish.
Annex 1 provides examples of
possible FCP-Modify
requirements – this is not
exhaustive
Versatility – FCP-Modify Parameters
FCP-Modify may be used to achieve the following - subject to survey
1.
2.
3.
4.
5.
6.
7.
8.
9.
Power capacity up to 10kW (single Power Base cabinet).
Power capacity 10.1kW to 20kW (two Power Base cabinets)
Dual power system working for resilience – two Power Base up to 10kW.
Dual power system working for resilience – four Power Base 10.1kW to 20kW
Additional rack space units – up to ten additional RSUs
Choice of added RSU sizes – choose from 600x600, 600x800 or 800x800mm.
Customer Use Cabinets (CuCs) on unused existing RSUs or new RSUs.
Additional HDF capacity to augment existing B-Buss HDF capacity.
Expanded Battery Capacity Cabinet (EBC-C option) where Non-ESS mains
supply due to insufficient standby generator capacity – or where greater battery
reserve is required.
10. Range of bespoke services covering changeover of customer equipment power
connections from old to new power system, recovery and disposal of replaced,
customer owned, power systems to free up space within customer cabinets /
RSUs.
11. Retrofit upgrade of PoP lighting to FCP LED system (if required).
Example 1 - B-Buss7: “I want 11kW total power
now, up to 15kW in the future, three more 600x600 RSUs,
one with a CuC, another HDF rack and sub-racks for up to
54 more tie cables”
The existing B-Buss7 PoP (8kW DC)
Rear
Rear
DC MIDI
600x600
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
RSU4
600x600
RSU5
600x600
RSU6
600x600
RSU7
600x600
HDF2
Front
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
FCP-Modify – Indicative Solution Design
Old MIDI
removed
following
changeover
Rear
Rear
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
Front
RSU4
600x600
Front
Front
CuC 1 of 1
Rear
HDF3
RSU10
600x600
RSU9
600x600
RSU8
600x600
RSU6
600x600
RSU7
600x600
HDF2
Front
Front
Front
Rear
Power Base
2 of 2
RSU5
600x600
Rear
Power Base
1 of 2
Example 2 - B-Buss7: “I want to fit 800mm deep
cabinets in my B-Buss7 footprint. I don’t currently need
more power capacity overall but do need versatility in
terms of being able to house ethernet, routers and
possibly more tie cables.
The existing B-Buss7 PoP (8kW DC)
Rear
DC MIDI
600x600
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
RSU4
600x600
RSU5
600x600
RSU6
600x600
RSU7
600x600
Front
Rear
HDF2
space
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
Rear
800mm
HDF1
RSU1
600x800
RSU2
600x800
RSU3
600x800
RSU4
600x800
RSU5
600x800
Front
CuC
1 of 1
(800 x 800)
Power Base
1 of 1
(800 x 800)
Example 3 B-Buss3: “I have an AC only B-Buss3
and want 3.6kW DC now, up to 6kW in the future”.
The existing B-Buss3 PoP ((AC only). All
customer RSUs have customer cabinets in place.
One houses the customer’s old DC system.
Rear
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
FCP-Modify – Indicative Solution Design
Rear
Rear
HDF1
Front
Power Base
1 of 1
RSU1
600x600
RSU2
600x600
RSU3
600x600
Front
Shows RSU1 cleared – old
DC cabinet removed
FCP Power Base Cabinet 1 of 1 is installed and commissioned.
Transfer of live existing dc wiring from the customer’s old DC system will be a
service option (price for out of hours cut-over option to be advised.
Recovery and disposal of the old DC system will be a service option (price tba)
Example 4 B-Buss3:
“I want to grow my B-Buss3 to
have two more RSUs and a dual power system with 6kW
capacity now and up to 10kW in the future”.
The existing B-Buss3 PoP (4kW )
Rear
DC MIDI
600x600
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
FCP-Modify – Indicative Solution Design
Old MIDI
removed
following
changeover
Rear
HDF1
RSU1
600x600
RSU2
600x600
RSU4
600x600
RSU3
600x600
Rear
RSU5
600x600
Front
Front
Power Base
1 of 2
New RSUs
Power Base
2 of 2
FCP Power Base Cabinets 1 & 2 replace the existing DC midi system.
FCP Power Base Cabinet 2 of 2 provides redundant mirrored capacity needed for resilience.
Where possible, pre-provision of new Power Base cabinets will be made to simplify changeover from the old MIDI.
Example 5 B-Buss3:
“I want to grow my B-Buss3 to
have two more RSUs (600Wx800D) with 6kW capacity now
and up to 10.1kW in the future. I’ll need more HDF capacity
for up to 20 tie cables”.
The APO survey is undertaken and results in an FCP-Modify solution design as below
Power Base
1 of 2
(800 x 800)
New RSU Power Base
2 of 2
(600 x 800)
Rear
RSU4
600x800
Other equipment
Front
Rear
Rear
RSU5
600x600
HDF1
RSU1
600x600
Front
New RSU
Front
RSU2
600x600
RSU3
600x600
Other
equipment
Example 6 B-Buss3: “My Non-ESS fed B-Buss3 has
become critical in my network. It needs another RSU and a
dual power system with 7kW capacity and the EBC option for
maximised battery autonomy”.
The existing B-Buss3 PoP (4kW )
Rear
DC MIDI
600x600
HDF1
RSU1
600x600
RSU2
600x600
RSU3
600x600
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
FCP-Modify – Indicative Solution Design
EBC-C
1 of 2
Rear
HDF1
Rear
RSU1
600x600
RSU2
600x600
RSU3
600x600
RSU4
600x600
Front
Front
New RSU
EBC-C
2 of 2
Power Base
2 of 2
FCP Power Base Cabinet 1 of 2 + EBC-C 1 of 2 replaces the existing DC midi system.
FCP Power Base Cabinet 2 of 2 + EBC-C 2 of 2 provides the mirrored capacity needed
for resilience.
Power Base
1 of 2
Note that Power Base 1 could be commissioned before removal of the old MIDI. EBC-C1
could be added post-removal of the MIDI for ease of changeover.
The EBC cabinets each provide ~24VU 19” space for customer use.
Example 7 – Migrate an MCU2 into FCP
“I want 4kW power capacity now, up to 6kW in the future
and another RSU with a CuC of 600mm width x 800mm
depth. I also need HDF for 21 more LLUT tie cables”.
Existing MCU2 PoP
Rear
RSU1
600x600
RSU2
600x600
Front
The APO survey is undertaken and results in an FCP-Modify solution design as below
FCP Power Base Cabinet 1 of 1 replaces
the existing APS3 DC system.
FCP Power Base Cabinet is 800x800mm
to house the added HDF capacity needed.
There will be an out of hours service
option for changeover of live DC wiring
from the old APS3 system and its
removal.
As FCP-Modify
Rear
900mm
x
600mm
Front
RSU1
600x600
Rear
RSU3
RSU2
600x600
Front
CuC
Power Base
1 of 1
1 of 1
600x800
800x800
Example 8 – MCU2 to ‘MCU2-Max Aux’
“I want something like the ‘MCU2-Max-Aux’ upgrade with
a 3rd RSU, 3.9kW of power now and up to 6kW in the
future. I want an 800mm wide Power Base”.
The existing MCU2
Rear
Other existing
equipment
RSU1
600x600
RSU2
600x600
Front
Other
existing
equipment
Other existing equipment
Power Base
1 of 1
800x600
RSU3
600x600
Space availability drives a
cross-suite FCP-Modify
solution
Example 9 – MCU2 to FCP
“I have a land-locked MCU2 and now need 4.1kW of
power to make full use of it”.
Other existing equipment
The existing MCU2
Rear
Other existing
equipment
FCP
Transplant
RSU1
600x600
RSU2
600x600
Front
‘Open Heart Surgery’ Power System Transplant using FCP
Power Core – undertaken as out of hours changeout*
Other existing equipment
Other
existing
equipment
Example 10 (1 of 2) – MCU2-Max Aux
“I’ve outgrown my MCU2-Max-Aux and now need to add
one RSU of 600x800mm and I need 8kW power capacity”.
The original MCU2 from 2006
Rear
Other existing
equipment
RSU1
600x600
Other
existing
equipment
RSU2
600x600
Front
Ceased LLU PoP still in-situ
MCU-Max
Aux
RSU3
600x600
The MCU-Aux -Max upgrade
from 2009
Example 10 (2 of 2) – MCU2-Max Aux
The original MCU2 from 2006
Rear
Other existing
equipment
MCU HDF
RSU1
600x600
Other
existing
equipment
RSU2
600x600
Front
RSU4
Power Base
1 of 1
Front
Space vacated by recovery of
ceased LLU PoP
Rear
The FCP-Modify
upgrade in 2013/14
MCU-Max
Aux
RSU3
600x600
The MCU-Aux-Max
upgrade from 2009
Note: The power is now all supplied from the new FCP Power Base. The redundant Eaton RM6 DC
system is recovered from the Aux cabinet, the space freed within being used by the customer.
Example 11 – LCU (also for BSR & CSR)
“I’ve outgrown my LCU and now need to double my
equipment mounting capacity and add 7 tie cables but
can’t afford to set up and kit out a new PoP. I need 2kW
now and I want DC and the inverter option”.
Other
existing
equipment
Other existing equipment
Rear
Other existing equipment
Front
Power Base
1 of 1
800 x 600 c/w 3
HDF sub-racks
LCU
Note: The power is now all supplied from the new FCP Power Base. The redundant AC / DC system is
recovered from the LCU. If ties re-provided, the old LCU enclosure may be removed to enable the
customer to expand their existing RSU upwards on the LCU space.
Example 12 – ASS600-C3
“I just want the FCP Power Base with 3kW so I can
rejuvenate and maximise usage of this PoP”. I need more
HDF too.
The existing ASS600-C3
Other existing
equipment
AC board
HDF
RSU1
600x600
RSU2
600x600
Other
existing
equipment
RSU3
600x600
Below: After the upgrade.
Power Base
1 of 1
800x600
Other existing
equipment
HDF
RSU1
600x600
RSU2
600x600
RSU3
600x600
The PoP following upgrade via FCP-Modify
All power now via Power Base. Old ac removed.
Capacity for up to 30 additional ties in PowerBase.
Customer is able to clear and re-use RSU3 due to
recovery of their old DC system.
Other
existing
equipment
Example 13 Bespoke Co-location Rooms
Start point would be a review of room usage and electrical supply design check.
FCP-Modify would provide Power-Base hardware and, as required, RSU / HDF
and CuC facilities. Note – different commercial terms apply for bespoke rooms.
BT AC mains supply to room.
Typically via ESS.
Originally designed for
customer specified max power
load.
FCP-Modify design would
review ac capacity to room to
ensure correctly rated supply.
May need to include some
ventilation / cooling based on
heat density.
Customer LLU equipment – incl DC
power and UPS
Example 14 Hostel Bays (Type A and B)
“I want to exploit my Hostel Bay and add capacity. I need 8kW
now and up to 10kW in the future. I want two more 600W x 800D
RSUs each with a CuC to hold my new equipment. I also need
an HDF for up to 54 new ties”.
As a result, the Openreach survey and design offers a solution that looks like this.
CP ‘X’ – FCP-Modify upgrade
Bay 1 Type A 8kW /
3.6metres
FCP
HDF
AC Supply to Hostel room
continues to be used
Bay 2 Type B
4kW / 1.8 metres
CP ‘Z’ – no change
Annex 2
‘FCP-Refresh’ high level APO process
‘FCP-Augment’
‘LLU Regrade’
Further work is to be undertaken on these.
FCP-Refresh – Power capacity increase
Start
FCP PoP
Customer pro-actively
requests increase in ac
power supply capacity
from initial maximum
power to a higher value
not exceeding the
‘expected future maximum
power’ stated at original
build order.
Where FCP DC system is
present alarm settings
are changed to reflect the
applicable new maximum
load current
(from dimensioning tool).
EIPB / FE D/L assumed
until PIMMS remote
config eliminates need
for site visit.
Customer places APO
quoting LLUC(s) and the
required new ‘usable
maximum power’ value
required (xx.xkW).
Customer is advised of
order completion via an
itemised statement of
new charges arising from
the APO.
LLUMS &
Billing System
Inventory records
updated & billing
triggered.
Yes
Openreach / EIPB APO
Power capacity survey(s)
undertaken
Enough ac
power capacity
for an
increase?
No
Customer informed of
power capacity situation
and indicative timescale
before an increase may
become possible.
Finish
FCP-Augment (applies to in-life FCP PoP
that originated as a new build or via FCP-Modify).
• Process would be similar to FCP-Modify and begin with a customer
requirements definition exercise to ensure that the need / indicative
pricing is documented and agreed.
• APO placed as the customer’s authority to proceed.
• APO survey would be undertaken for each PoP in scope.
• Response to customer based on ‘art of the possible’.
• Customer firm order decision.
•
Delivery planning, date setting, installation, QA.
•
Handover to customer.
•
Billing & inventory.
LLU-Regrades (‘Minor-works’)
In scope:
-
MCU-Max & Aux: 4.95kW to 6.6kW (rectifier infill)
B-Buss3: 4.4kW to 6.6kW (rectifier / battery infill)
Additional DC sub-distribution connected to existing DC system
Additional AC sub-distribution connected into existing AC system.
MCU1 to MCU2 (+1 rectifier & +5 HDF sub-racks + RSU#2 if space).
B-Buss7 Supplementary HDF rack
B-Buss7 to B-Buss3 downgrade
Inverter tower
Non-ESS to ESS transfer
Retrofit sub-meter.
HDF sub-rack provision into available space in or adjacent to the PoP.
Note: The above is not and exhaustive listing – further low-capex re-grade
solutions of a minor engineering nature may be added.