New Plant Configuration
Management Development
and Implementation Process
John Maciejewski
INPO
New Plant Configuration Management Development
and Implementation Process
Issued AP-932 “New Plant Configuration
Management Development and Implementation
Process” in November 2009 as Preliminary
Process document that provides flexibility in how
to implement
New Plant Configuration Management Development
and Implementation Process
Plan to issue AP-932 as final in 2010
Plan to expand AP-932 to cover CM during
operation considering :
The 3-D model
Computer technology
AP-929
New Plant Configuration Management Development
and Implementation Process
Reasons for development:
INPO AP-929 developed based on
modifications/changes to an existing plant
Extensive use of computer technology for new
plant deployment
Benchmarking international projects revealed
significant use of computer technology in providing
CM
Recommendations from several CNO’s
Use by other industries of relational databases to
control information
New Plant Configuration Management Development
and Implementation Process
Document sections:
Configuration management program attributes
Process description is for new plant deployment
(not operation)
Includes incorporating information needed for
operation and a description of linking information
using relational databases
New Plant Configuration Management Development
and Implementation Process
Concepts
CM development starts early in the design phase
Design is essentially complete prior to
construction
Computer technology is used extensively in
design ( 3-D model, data bases)
Computer technology supports development of a
detailed design that can be built.
The plant is built as designed. Changes are only
made because of errors in design.
New Plant Configuration Management Development
and Implementation Process
CM attributes for pre-commercial operation
A listing of CM attributes for design and
construction that will enable establishment of
effective CM
New Plant Configuration Management Development
and Implementation Process
Process elements:
Determine CM scope and information
Establish an electronic platform and standard
format
Electronically link related information
Enter information into the computer
Produce information for construction
Build the plant per the design (correct errors only)
Turnover the computer databases and physical plant
to COL holder
New Plant Configuration Management Development and
Implementation Process
Using the component designator as the common
relationship
Using a common electronic platform/framework, design
information can be linked electronically to the related
components and other related information using the component
designator.
For example the component designator (e. g., MOV-XX) is the
common relationship for relating information.
Design information and information based on design information
should be linked.
New Plant Configuration Management Development and
Implementation Process
SUMMARY
INPO issued AP-932 “New Plant Configuration
Management Development and Implementation Process”
in November 2009
Concepts are based on CM lessons learned and recent
benchmarking
Incorporates computer technology as a tool for CM
Plan to issue AP-932 final in 2010