Transcript Bridge over BNSF 7 km East of Windham
Bridge over BNSF Railroad 7 km East of Windham - East
Bridge Replacement Project Using Accelerated Bridge Construction
Project Location
Existing Bridge
o o o 3-Span Concrete Tee Beam 123 Feet Long 28 Feet Wide
Approach Looking Southeast
Profile Looking Southwest
Design Parameters
o o o o o o o National Highway Route 2500 vehicles per day (23% Trucks) Major truck route between Great Falls and Billings US Air Force Missile Route Grain Elevator in Moccasin BNSF Railroad Crossing Accident cluster at bridge
New Bridge Requirements
o o o o o o New width = 40 feet Increased railroad lateral clearance Increased railroad vertical clearance Avoid existing foundations (timber piles) Minimize grade raise to catch slopes on existing approaches – avoid sliver fills and new R\W Minimize traffic disruptions
What are our options?
o New Bridge on Offset Alignment o New Bridge on same alignment using On-site Detour o New Bridge on same alignment using Phase Construction o New Bridge on same alignment using Off-site detour and ABC
Could Accelerated Construction work here??
o o o o How long can we shut down bridge site?
How quickly can we build a new bridge?
How much building can be completed before with existing bridge in place?
Is there a reasonable detour route?
o o o o o
Possible detour route
Secondary Highways – wide shoulders / flat slopes Similar detour length for thru-traffic Detour through town of Hobson – school crossing At-grade RR crossing in Hobson Many local detours possible (County Roads)
ABC Planning Efforts
o o o o o Contacts with o o Town of Hobson - Mayor Hobson School o o o o County Commissioners Trucking Industry – grain elevator Air Force Base BNSF Railroad Road User Cost Calculations Preliminary ABC Ideas Contract Time Estimates Local Events
– Hay Days – Utica Montana
What can we accelerate?
What portion of construction takes the most time?
o o o o o o Foundation construction – 4 days/shaft or 4 piles/day Drilled Shaft testing – 14 days before testing / longer if problems are encountered Forming bent caps – 3 days each Curing bent caps – 15 days per project Deck forming – 20 days up to 300 feet Deck curing and sealing – 28 days Allowing for some overlap……80 days for major items
Potential Solutions
o Foundations o o What can we do while traffic is on existing bridge?
What foundation types will work?
o Forming and curing bent caps o o What cast-in-place can be done while traffic is on existing bridge?
Precast end and intermediate caps?
o Deck forming and curing o Full-depth precast deck panels o o Partial-depth Stay-in-place Forms
Divided Work Into Stages
o What could be completed before detouring traffic o What would be accelerated while traffic is on detour route o What work could be done after traffic is moved back on new bridge
Work Prior to Detouring Traffic
Drilled 4 shafts outside the bridge limits and behind the existing intermediate bents.
Cast struts/crash wall on top of and between shafts
Cast walls on top of struts
Traffic on Detour
Day 1 o o Removed span 2 deck and beams Removed span 3 deck
Day 2 o o o Removed span 3 beams Removed bent 3 and 4 Removed span 1 deck
Day 3 o o o o Bent 4 – drove piles, formed and placed cap Bent 3 – Set cap and placed closure Removed span 1 beams Removed bents 1 and 2
Precast Pier Cap
Day 4 o o Bent 2 – Set cap Bent 1 – drove piles
Day 5 o o Bent 2 – placed closure Bent 4 –formed and placed cap
Day 6 o Span 3 – Set girders and deck panels
Day 7 o Sunday – no work Day 8 o Span 2 – Set girders and deck panels
Day 9 o Span 1 – Set girders and half the deck panels Day 10 o o Span 1 – Set remaining deck panels Began forming closure pours
Day 11 o o Bents 1 & 4 – Formed and placed backwalls Formed deck panel closure pours Day 12 o Continued forming deck panel closure pours Day 13 and 14 o Saturday and Sunday – No work Day 15 o o Adjusted deck grades Prepare for deck closure pours
Day 16 and 17 o UHPC Closure Pours
Day 18 and 19 o o Removing form work and grinding joints Fill low spots
Day 20 and 21 o Weekend no bridge work – building approach fills Day 22 o More grinding and approach fills Day 23 o o Tying barrier steel Test run with slip form Day 24 o Approach work Day 25 o o Slip formed barriers Final grading along RR tracks
Day 26 and 27 o o More grading work Approach rails Day 28 o Finished approach rails Day 29 o Opened to Traffic One day ahead of schedule (incentive/disincentive deadline)
Now lets see that in fast motion
Lessons Learned
o o o o o Project scheduling was intensive Design details are critical – things need to fit Allow adequate tolerance on precast elements UHPC is difficult to grind – reduce exposed area to minimize grinding Have an Engineer on site during construction of critical elements – be prepared to make decisions
Questions??
Project Contact: Jeff Olsen [email protected]
406-444-7610