Transcript Document

Overview of Demand - Supply Situation
and Projects Implementation in the SAPP
by
Eng. Musara Beta
SAPP Chief Market Analyst
ZIMASSET Parliamentary Workshop
13 March 2014, HICC, Harare, Zimbabwe
1
SOUTHERN AFRICAN POWER POOL
Contents
1. Introduction to SAPP
2. SAPP Demand and Supply Situation
3. Update on Projects Implementation in SAPP
4. Conclusions
2
SOUTHERN AFRICAN POWER POOL
1. Introduction to SAPP
Key Facts





12 Countries
280 Million people
Installed Generation
Capacity – 56 GW
Available Generation
Capacity – 52 GW
Peak Demand – 54 GW
DR Congo
Angola
Namibia
Tanzania
Malawi
Zambia
Zimbabwe
Botswana
Mozambique
Swaziland
South Africa
Lesotho
3
SOUTHERN AFRICAN POWER POOL
SAPP Vision
The SAPP Vision is to:
 Facilitate the development of a competitive
electricity market in the Southern African region.
 Give the end user a choice of electricity supply.
 Ensure that the Southern African Region is the
region of choice for investment by energy
intensive users.
 Ensure sustainable energy developments through
sound economic, environmental & social
practices.
4
SOUTHERN AFRICAN POWER POOL
SAPP Membership -2013
No
Full Name of Utility
Abbreviation
Country
1
Botswana Power Corporation
OP
BPC
Botswana
2
Electricidade de Mocambique
OP
EDM
Mozambique
3
Electricity Supply Corporation of Malawi
NP
ESCOM
Malawi
4
Empresa Nacional de Electricidade
NP
ENE
Angola
5
ESKOM
OP
Eskom
South Africa
6
Lesotho Electricity Corporation
OP
LEC
Lesotho
7
NAMPOWER
OP
Nam Power
Namibia
8
Societe Nationale d’Electricite
OP
SNEL
DRC
9
Swaziland Electricity Board
OP
SEC
Swaziland
10
Tanzania Electricity Supply Company Ltd
NP
TANESCO
Tanzania
11
ZESCO Limited
OP
ZESCO
Zambia
12
13
14
15
16
Zimbabwe Electricity Supply Authority
OP
ZESA
Zimbabwe
Copperbelt Energy Corporation
Lunsemfwa Hydro Power Station
Hidro Cahora Bassa
Mozambique Transmission Compamy
ITC
IPP
OB
OB
CEC
LHPS
HCB
MOTRACO
Zambia
Zambia
Mozambique
Mozambique
OP: Operating
OB: Observer
5
Status
NP: Non-Operating ITC: Independent Transmission Company
IPP: Independent Power Producer
SOUTHERN AFRICAN POWER POOL
SADC Potential Energy Sources
KENYA
GEO-THERMAL
GABON
DR CONGO
TANZANIA
ANGOLA
ZAMBIA
NAMIBIA
BOTSWANA
SUPER GRID
SOLAR
SWAZILAND
6
SOUTHERN AFRICAN POWER POOL
Generation Mix & Contributions – Year 2013
74.3% Coal
20.1% Hydro
4.0% Nuclear
1.6% Gas/Diesel
7
80.4% South Africa
5.0% Mozambique
4.1% Zimbabwe
3.6% Zambia
2.6% DRC
4.4% Rest
SOUTHERN AFRICAN POWER POOL
2. SAPP Demand and Supply Situation
No.
Country
Utility
1
Angola
ENE
2,028
2
Botswana
BPC
352
3
DRC
SNEL
2,442
4
Lesotho
LEC
5
Malawi
6
Forecast
Demand
Capacity
Shortfall Calculated
including Reserve
reserves, Margin, %
MW
1,805
1333
322
580
1,268
1342
72
72
138
ESCOM
351
351
323
Mozambique
EDM /HCB
2308
2,279
763
7
Namibia
NamPower
501
392
635
8
South Africa
Eskom
44,170
41,074
38775
9
Swaziland
SEC
70
70
222
10
Tanzania
TANESCO
1380
1,143
898
11
Zambia
ZESCO / CEC/LHPC
2,128
2,029
2287
12
Zimbabwe
ZESA
2,045
1,600
2267
57,847
52,405
49,563
(4,592)
5.4%
54,088
49,106
47,009
(2,787)
4.3%
TOTAL SAPP
Total Interconnected SAPP
8
Installed Available
Capacity Capacity
[MW] As at
[MW]
Feb 2014 Feb 2014
SOUTHERN AFRICAN POWER POOL
SAPP Planned & Required Capacity
MW
Planned Capacity vs Forecast , MW
All SAPP Members (As at Sept 2013)
90000
80000
70000
60000
50000
40000
30000
20000
10000
0
 Projects are facing
delays
2012
2013
2014
GWh
Forecast
500000
450000
400000
350000
300000
250000
200000
150000
100000
50000
0
2016
2017
2018
 This is due to low
load factor plants
being
commissioned.
Capacity Planned
Energy Planned vs Forecast , GWh
All SAPP Members
2013
2014
2015
Energy Forecast
9
2015
2016
2017
2018
2019
 Capacity balance by
2017
but
energy
balance by 2019
2020
Energy Planned (GWh)
SOUTHERN AFRICAN POWER POOL
SAPP Planned & Required Capacity
All SAPP - Reserve Margin, %
27.0
23.8
24.0
21.0
Best practice
reserve
margin
18.0
17.2
15.0
12.6
12.0
6.6
9.0
6.0
3.0
3.2
1.8
2013
2014
2015
2016
2017
2018
Reserve Margin very tight in earlier years
10
SOUTHERN AFRICAN POWER POOL
Power Supply Challenges in SAPP

Demand for power in Southern African has been
increasing at an average rate of 3% per annum.
 In 2007, demand growth for South Africa
was 4.9% and for the whole region 4.6%.
11

In the last 10 years demand in the SAPP
increased by more than 32% which is equivalent
to 13,000 MW (from 41,000 MW in 2004 to
54,000MW in 2013).

Unfortunately, there has been no corresponding
investments in generation and transmission
infrastructure, (11,202MW generation added
from 2004 to 2013) resulting in the current
supply deficit that the region is experiencing.
SOUTHERN AFRICAN POWER POOL
Why has the SAPP run into supply deficit ?
12
1.
Economic Growth of more than 5% in most of the
SADC member countries resulting in unprecedented
growth in electricity consumption and demand.
2.
Increase in demand for base metals resulting in high
metal prices on the World Market with new mining
companies being established in the SADC region in the
last few years.
3.
Inadequate Investments in generation and
transmission infrastructure over the last 20-years.
4.
Electrification Programmes have partly contributed to
the increased consumption and demand.
5.
The challenge was identified and communicated but
not adequately mitigated.
SOUTHERN AFRICAN POWER POOL
Short Term Measures to Meet Demand
The SAPP has proposed the following measures:
a)
Demand Management based on others experiences:
 Power Conservation Programme (PCP)
 Study and understand the concept of PCP
 Formulate and adopt PCP for SADC
 Demand Side Management (DSM)
 Mechanism to provide financial support for


13
development and implementation of DSM in the SADC
Develop local manufacturing capability to support DSM
initiatives.
SADC Policy for efficient use of electrical energy
• Incandescent versus CFLs
• Minimum energy efficiency standards for new
connections
SOUTHERN AFRICAN POWER POOL
IMPACT OF LOAD MANAGEMENT [2009 – 2015]
ALL SAPP MEMBERS
All SAPP Members
Capacity Required
Peak Demand
If no load
management options
implemented, the
deficit could have
been worse
2009 Plan
2015
2014
2013
2012
2011
2010
2009
MW
90000
85000
80000
75000
70000
65000
60000
55000
50000
45000
40000
Year
Capacity Planned
Peak Demand after load reduction
Situation improves
and is better after
load management.
2015
2014
2013
2012
2011
2010
85000
80000
75000
70000
65000
60000
55000
50000
45000
40000
35000
30000
2009
MW
Capacity Required
Year
14
SOUTHERN AFRICAN POWER POOL
Short Term Measures to Meet Demand
b)
c)
15
Create an enabling environment for power sector
investment:


Policy and Legal framework
Regulatory framework

SAPP Governance documents revised from 2006 to
accommodate other players such as IPPs in the
structures of SAPP
Implement cost reflective and time of use tariffs in
SADC member countries.
SOUTHERN AFRICAN POWER POOL
Short Term Measures to Meet Demand
d)




e)
Supply Side Measures
Maximize utilization of all installed supply option
 Re-capitalization of power utilities
Short and Medium-term generation projects
 Ensure projects are properly prepared for financing
 Governments to prioritize funding of power projects
Create an enabling environment for renewable energy
Develop a structure for the implementation of a least-cost
SAPP generating facility
Provide Investment incentives to all Investors in the
power sector, both local and foreign.


16
Address policy issues relating to legal & regulatory
frameworks, i.e. enabling environment.
Allow for VAT and tax exemptions for import of power
equipment and machinery for a defined period.
SOUTHERN AFRICAN POWER POOL
3. UPDATE ON PROJECTS IMPLEMENTATION
17
SOUTHERN AFRICAN POWER POOL
Projects Commissioned in 2013
GENERATION PROJECTS COMMISSIONED 2013
Capacity
No
Utility
Country
Name
Type
[MW]
1
BPC
Botswana
Morupule B
Coal
450
2
IPP
Zambia
Ndola Energy
HFO
50
3
SNEL
DRC
Inga 1
Hydro
55
4
IPP
Tanzania
Mwanza HFO
Gas
60
5
Eskom
South Africa
Komati
Coal
202
6
Eskom
South Africa
Grotvlei
Coal
40
7
Eskom
South Africa
Koeberg
Nuclear
30
8
IPP
South Africa
Solar
Solar
130
9
IPP
Malawi
Kapichira
Hydro
64
10
ZESCO
Zambia
Kariba North
Hydro
180
11
IPP
Mozambique
Ressano Gassia
Gas
100
TOTAL
18
1361
SOUTHERN AFRICAN POWER POOL
Projects Planned to be Commissioned in 2014
GENERATION PROJECTS -2014 TARGET
No
Utility
Country
Name
Type
Capacity
[MW]
1
2
3
4
5
ENE
ENE
ENE
ENE
IPP
Angola
Angola
Angola
Angola
Tanzania
Lomaum
CFL New
Kinyeredzi
Hydro
Coal
Coal
Coal
Gas
65
70
50
50
150
6
7
IPP
IPP
Tanzania
Tanzania
Sao Hill
Somanga
Gas
Gas
10
290
8
Eskom
RSA
OCGT
Gas
800
9
Eskom
RSA
Medupi
Coal
722
10
Eskom
RSA
Ingula
Hydro
1332
11
IPP
RSA
Cogen
Gas
100
12
IPP
RSA
Sere
Wind
100
13
IPP
RSA
RE - Round 1
PV, CSP, Solar
1328
14
IPP
RSA
RE - Round 2
PV, CSP, Solar
554
15
IPP
Gas
175
16
BPC
Botswana
Morupule
Coal
150
17
ZESCO
Zambia
Kariba North
Hydro
180
18
ZESCO
Zambia
Lunzua
Hydro
15
BIOCOM
BOM- JESUS
Mozambique Ressano Garcia
TOTAL
19
685 MW
Not Interconnected
1982 MW
Renewable Energy
6141
SOUTHERN AFRICAN POWER POOL
SAPP Committed Generation Projects
No
Country
COMMITTED GENERATION CAPACITY, MW
2014
2016
2017
TOTAL
1
Angola
235
0
1280
2271
3,721
2
Botswana
150
-
-
-
150
3
DRC
-
580
-
240
820
4
Lesotho
-
-
35
-
35
5
Malawi
-
-
-
34
34
6
Mozambique
175
-
40
300
515
7
Namibia
-
-
15
-
15
8
RSA
4,936
2,527
3,717
1,918
13,098
9
Swaziland
-
-
-
-
10
Tanzania
450
240
660
250
1,600
11
Zambia
195
735
40
126
1,096
12
Zimbabwe
-
15
-
1,140
1,155
6,141
4,097
5,787
6,279
TOTAL
20
2015
-
22,304
SOUTHERN AFRICAN POWER POOL
SAPP Priority Transmission Projects
Priority transmission projects are defined as follows:
1.
21
Outstanding transmission interconnectors whose
aim is to interconnect non-operating members of
the SAPP:

Mozambique-Malawi

Zambia-Tanzania-Kenya and

Interconnection of Angola
2.
Transmission interconnectors aimed at relieving
congestion on the SAPP grid, and
3.
New transmission interconnectors aimed at
evacuate power from generating stations to the
load centres.
SOUTHERN AFRICAN POWER POOL
Transmission Projects
USD 5.6 billion
DRC
2016 -2017: ZIZABONA -220/330 kV
Tanzania
2016: Mozambique Malawi
2017: Zambia - Tanzania - 400 kV
Malawi
Angola
Zambia
2018:DRC - Angola – 400 kV
Zimbabwe
2017: MOZAMBIQUE BACKBONE -RSA
2015-2025: 765 kV Strengthening
Namibia
Mozambique
Botswana
Swaziland
2016: RSA Strengthening
South Africa
Lesotho
2017: Botswana Strengthening
22
SOUTHERN AFRICAN POWER POOL
ZIMBABWE POWER SYSTEM TRANSFER LIMITS
Limited by Line
Loading between KRN
& KRS Under
Contingencies
23
Limited by Voltage
at Bindura
740M
W
500MW
Kariba
ZAMBIA
Mutorashanga
Bindura
Alaska
Norton
330MW
MOZAMBIQUE
Harare
Warren
Dema
Hwange
Sherwood
Haven
Orange Grove
Chertsey
Insukamini
Marvel
Tokwe
BOTSWANA
Plumtree
Triangle
Maximum Transfer From
ZESA to the South
320MW
Beitbridge
SOUTH AFRICA
23
Limited by WarrenNorton Line Loading
Under Contingencies
SOUTHERN AFRICAN POWER POOL
Project Implementation Challenges
24
i.
Projects Preparation and Packaging – Projects good on
paper but lacks development to bankability levels
i.
Tariffs levels – most utility tariffs are not favorable for
new projects development
ii.
Weak Utility Balance Sheets – not favorable to anchor
projects

SAPP
plans
to
strengthen
Project
Management
capabilities in order to prepare projects to bankability
levels
SOUTHERN AFRICAN POWER POOL
4. CONCLUSIONS

Electricity is critical for economic development

Projects Packaging is critical for projects to attract
funding and be implemented


SAPP CC plays a critical role in mobilising grant
funding and project coordination
A Master Plan for the regional power market is vital
as it:

Helps to reduce capital costs by implementing leastcost projects for the benefit of the region.

Reduces excess capacity from the pool.
In the SAPP, a saving of over US$48 billion could be realized if
projects are implemented in a coordinated fashion.
25
SOUTHERN AFRICAN POWER POOL
Thank you for your attention
26
SOUTHERN AFRICAN POWER POOL
Thank you very much for your attention
27