Karim Karzazi, AXA Matrix Risk Consultants, France

Download Report

Transcript Karim Karzazi, AXA Matrix Risk Consultants, France

Risk Consulting REVISION TO EN 12 845 and CEA 4001

EFSN – MAY 2014

REVISION TO EN 12 845 and CEA 4001 Do you think our sprinkler standards are so complicated?

REVISION TO EN 12 845 and CEA 4001 1: Current status of EN 12 845 – revision 1 2: revision 2 of EN 12845 3: CEA 4001- new edition 2013 4: CEA 4001 expected modifications

Current status of EN 12 845 – revision 1

Current version :

June 2009 Includes amendments A1 and A2

Revision 1 of EN 12 845

Includes ESFR, CMSA, excessive clearance, test line, electrical cables, K factor >115, third party inspection, new annex F … )

prEN 12845 rev 1 had a UAP draft dispatched to CCMC on 2013/12/18 (stage 30.99),

the next stage will be the submission to UAP ( formal vote yes/no ) by 2014/05/22

Future revision 2 of EN 12 845

New structure of document : 27 chapters distributed in 6 sections

SECTION 1: SCOPE, REFERENCES and DEFINITIONS

SECTION 2 : HAZARD EVALUATION

SECTION 3 : DESIGN CRITERIA

SECTION 4 : INSTALLATION

SECTION 5 : WATER SUPPLY

SECTION 6 : COMMISSIONING AND CONTROL PROGRAMME

Annexes

Draft expected S2-2014

Future revision 2 of EN 12 845 : KEY POINTS SECTION 1: SCOPE, REFERENCES and DEFINITIONS

Introduction enabling new technologies not included

Scope more precise to avoid conflict especially with residential sprinkler standard

More comprehensive set of definitions

Will include contract, planning and documentation

Future revision 2 of EN 12 845 : KEY POINTS SECTION 2 : HAZARD EVALUATION

New HHS 5 to take into account plastic goods

Classification will differentiate: manufacturing / non manufacturing.

Classification for manufacturing will include additional parameters to define hazard : Fire Hazard : FH1, FH2, FH3 or FH4

Will be detailed in the next presentation (Stuart Lloyd)

Future revision 2 of EN 12 845 : KEY POINTS SECTION 3 : DESIGN CRITERIA

Design density and area of operation linked to hazard class + ceiling height

Design section for storage will include existing and new protection tables + new HHS 5 classification.

Will cover the former special risk annex G (flammable liq, hanging garments, aerosols...)

Storage configuration STC1 to STC6 will remain similar as today

ESFR and CMSA will be as separate chapters

Future revision 2 of EN 12 845 : KEY POINTS SECTION 4 : INSTALLATION

No big modification but many improvements and precisions of existing text :

dry system,

more details about specific areas like stairways, concealed spaces..

location from beams,

Sprinkler above suspended ceiling. 9 m² for hollow spaces > 0.3 m and < 0.5 m…,

Clarification about location of in-rack sprinkler

Special rack configuration included

Corrosion issues

Electrical issues: more details provided especially regarding alarms

Future revision 2 of EN 12 845 : KEY POINTS SECTION 5 : WATER SUPPLY

Connection for other service : hydrants 90m 3 /h in OH and 120 m 3 /h in HH.

Detailed requirements for pump room and alarm valve room

Velocity in the suction pipe increased to 2,5 m/s for suction lift condition and 4m/s for positive head : cost effective modification

Specific requirements for diesel equipped with Electronic Fuel Management Control (ECM)

Future revision 2 of EN 12 845 : KEY POINTS Section 5 : water supply

Volume of tank no longer based on Q max : reduction of tank volume; based on unfavourable area.

Future revision 2 of EN 12 845 : KEY POINTS SECTION 6 : COMMISSIONING AND CONTROL PROGRAMME

Contract , planning and documentation: simplification with suppression of preliminary design stage

Flushing of pipework

Detail procedure for commissioning and first inspection to be be witnessed by the authorities or a third party inspection body accepted by the authorities

Model of maintenance report provided : complete list of all maintenance operation for each component

Model of commissioning and inspection report provided

Future revision 2 of EN 12 845 : KEY POINTS SECTION 6 : COMMISSIONING AND CONTROL PROGRAMME

Detailed user’s control programme

Future revision 2 of EN 12 845 Annexes

All references to pre-calculated system suppressed from main body of the text

Specific annex (stand alone) covers all the requirements for pre-calculated system (FH1 and FH2)

Number of annexes reduced

Comprehensive annex for new technologies detailing process to accept them

Future revision 2 of EN 12 845 : conclusion

Even if many modifications are expected:

 Standard should be simple to understand and to apply: more flow charts and graphics  Installation should not be more expensive than today (even less: e.g. tank volume … )  A large range of technology (K factor, type of sprinklers … ) should be possible

CEA 4001- new edition 2013

First published in 1996

Latest edition August 2013

Includes all the proposals drafted since 2009:

New concept for rack protection (multiple row, >3,2m wide…)

Protection of rubber tyres

Update classification of goods involving plastic

Sprinkler in freezers

Suction chambers

CEA 4001: expected modifications

Future Update planed for end of 2014-beginning 2015

Main modifications will concern:

Full revision of chapter 15 : pipework

Total revision of Annex L : ESFR

New annex for CMSA

CEA 4001: expected modifications revised chapter 15 : pipework

Include requirements for plastic pipe, press fitting pipe system, flexible pipe, stainless steel…

Detailed requirements for pipe thickness and pipe assembly

Table T 15.2.2.2 minimum wall thickness for steel pipes

(draft)

Roll grooved or welded Threaded pipes and cut grooved Nominal diameter External Ø DN 25 DN 32 DN 40 DN 50 DN 65 DN 80 DN 100 DN 125 1" 1"1/4 1"1/2 2" 2"1/2 3" 4" 5" DN 150 DN 200 DN 250 DN 300 6" 8" 10" 12" DN 350 DN 400 DN 450 DN 500 * 165,1 for EN 10255 14" 16" 18" 20" 33,7 42,4 48,3 60,3 76,1 88,9 114,3 139,7 168,3* 219,1 273 323,9 355,6 406,4 457 508 2,6 2,6 2,6 2,6 2,6 2,9 3,2 3,6 4 4,5 5 5,6 5,6 6,3 6,3 6,3 2,6 2,6 2,6 2,6 2,6 2,9 3,2 3,6 4 2,6 2,6 2,6 2,6 2,6 3,2 3,6 4 4,5 4,5 5 5,6 5,6 6,3 6,3 6,3 3,2 3,2 3,2 3,6 3,6 4 4,5 5 5 3,2 3,2 3,2 3,6 3,6 4 4,5 5 5 6,3 6,3 7,1 8 8,8 10 11 3,2 3,2 3,2 3,6 3,6 4 4,5 5 5 6,3 6,3 7,1 8 8,8 10 11

CEA 4001: expected modifications

Total revision of Annex L : ESFR

Similar to EN 12845 revision 1

Will include latest update especially regarding limitation for K14 (K200) ESFR heads

New annex for CMSA

Similar to EN 12845 revision 1 Ambition of CEA 4001: to be pro-active and up to date standard thanks to faster procedure than CEN

Contact

Thank you