ABS Material Properties

Download Report

Transcript ABS Material Properties

BURIED FLEXIBLE PIPELINES





The Design Process- Boundary Conditions
Design Fundamentals-AS2566.1
Materials
Installation AS 2566.2
Tips, Tricks & Traps
Presented by Geoffrey D Stone
C.Eng FIMechE; CP Eng FIEAust RPEQ
Principal Blenray Pty Ltd ( Design Detail & Development)
[email protected] 0402 35 2313
THE DESIGN PROCESS
Boundary Conditions







Soils & Soil Data
Trench Width &
Depth
Structural Response
to Loading
Trench Details
Stiffness
Thrust Blocks
Structural Interfaces




Water Table
Design Loads Trench
& Embankment Fill
Superimposed Live
Loads
Other Superimposed
Loads
Soils & Soils Data

Native Soil

– Classify
– Modulus

Bedding
– Type

Embedment
–
–
–
–
Material
Compaction
Geo-textile
Water Table
Backfill
– Type
– Compaction

Piles

Testing
– Field
– Laboratory
Trench Width & Depth
AS 2566.1 Minimum
 Embedment or Embankment
 Shape of trench

Trench Dimensions
Structural Response to Loading
Stiffness AS 2566.1
2 year values of pipe stiffness suitable for
good soils
 50 year values of pipe stiffness should be
used for poor soils, uncontrolled
installations or other higher risk
applications

Stiffness AS 2566.1
Thrust Blocks
Not required for fully welded systems as in
ABS, PP, PVC-U, PB or PE
 Required for rubber ring systems as used
for DICL, MSCL, GRP & PVC-U/O/M
 Design basis

– Steady state pressure
– Unsteady state pressure spikes
– Hydrostatic test pressure
Structures Interfaces







Differential
Settlement
Soil swelling
Water Retaining
Shear Loading
Thermal Loading
Chaffing
Water seal in
concrete
Water Table
Water hydrostatic level applies load onto
pipe-refer AS2566
 Rising water applies uneven load onto pipe
and the pipe may buckle or exceed its
strain limit
 Water may cause flotation of empty pipe
and special embedment may be necessary
 High water table increases construction
difficulty
– Safety
– Dewatering
– Quality

Loading
Design loads due to trench & embankment
fill
 External hydrostatic loads
 Internal pressure
 Superimposed dead loads
 Superimposed live loads
 Other unsustained loads

Design Loads due to Trench &
Embankment Fill
Superimposed Live Loads
Superimposed Live Loads
Other Unsustained Loads
1.
2.
3.
4.
Specialist
Engineering
National Codes
Local Conditions
Risk






Likelihood
Consequences
Responsibility
Safeguarding





Earthquake
Vibration/Shock
Differential
Settlement
Thermal Strain
Subsidence
Airport runways
Railways
DESIGN FUNDAMENTALS
AS2566.1 Buried Flexible Pipelines-Design





Deflection
Strength
Internal Pressure
Combined Loading
Buckling





Hoop Stress
Ring Bending Strain
Creep
Temperature
Other Considerations
Deflection
Short term
 Long term
 Vertical & Horizontal

– Considered equal
– Effect of excess side compaction
Modulus to use
 Acceptance criteria
 Measurement during installation

Strength
Loads cause strain in pipe wall
 Ring compression strains << ring bending
strains
 AS 2566.1 predicts maximum tensile ring
bending strains
 A Shape Factor adjusts strain values

– True Ellipse Shape Factor Df=3.0
– Δhorizontal < Δvertical Shape Factor Df > 3.0
Internal Pressure
Steady State
 Unsteady State

– AS 2566.1 Requirements 1.25
– AS 2885 Requirement 1.10
– Other codes requirements
Combined Loading
Combined external load and internal
pressure
 Re rounding effect

Buckling
Ovalization
 Buckling
 External Pressure
 No substantial soil support-Timoshenko
 Substantial soil support –I.D. Moore

Hoop Stress
Stress in the wall due to pressure
 Only criteria used for pipe class selection
 Does not take into account other stresses
 Basis of the Pipe Class System
 Relaxes with time for thermoplastic pipes
 Never Constant

Ring Bending Strain
Importance of Strain
 Comparison of allowable strain in
materials
1. ABS 1%
2. GRP 0.18 to 0.6 %
3. PE 4.0%
4. PVC-U 1%
5. PVC-M 1%
6. PVC-O 1.3%

Creep
Variation of Properties in Time
 Long term loading/Stress relaxation
 Reverse loading/Stress magnitude
 Repetitive loading/Fatigue

Temperature
The design temperature may vary due to:•Ambient diurnal temperature variations
•Flow rate
•Fluid temperature range
•Process conditions
•Installation ambient temperature
•Wall thickness
Other Considerations
Anchor forces
 Differential
Settlement
 Earthquake
 Subsidence
 Testing conditions
 Corrosion

Mass of pipe
contents
 Thermal Strain
 Local buckling
 Fatigue
 Pavement
settlement

Materials Selection
Types
 Costs
 Class
 Characteristics
 Fittings & Valves



Modulus GRP
Modulus
Thermoplastic Pipes
Materials - Types
GRP
 ABS
 PE
 PVC-U, PVC-M, PVC-O
 DICL
 MSCL

Materials Selection

Costs – Supply

1. Safety
2. Availability
3. Maintenance
4. Energy
5. Risks
1. Pipe
2. Fittings
3. Supports

Costs – Installation
1.
2.
3.
4.
5.
Standard of trades
Equipment
Jointing
Access
Testing
Costs - Whole of Life

Costs - Standards
1. Authority
2. Industry
3. Acts
Selection of Pipe Class
Design Pressure
Steady State
 Design Pressure
Unsteady State
 Vacuum
Conditions
 Industry
Application &
Environment

Soil/Pipe Structure
Design
 Standardization
 Risk
– Likelihood
– Consequences
– Responsibility

Typical Material Characteristics
Fittings & Valves



Valve classes do not
meet all pipe classes
Injection moulded
fittings- Size
Limitation
Manufactured
fittings-Larger Sizes
– Tees
– Bends





Jointing
Gaskets
Expansion Bellows
Saddles
Valves
–
–
–
–
Isolation
Check
Air release
Control
Modulus-GRP Pipes
Manufacturers establish values by test
& calculation
 Axial & longitudinal modulus differs
 Values at various temperatures
required for design
 Strain rate changes values
 Standards such as ISO 14692

Modulus-Thermoplastic Pipes
Published figures normally are strain
rate at 20ºC
 Value determined by ASTM test
– Standard dog bone test specimen
– Fixed strain rate
 Values at various temperatures
required for design
 Strain rate changes values

INSTALLATION
Trench Excavation
 Trench Shields
 Laying & Jointing
 Embedment &
Compaction

Thrust Blocks
 Hydrostatic
Testing

Trench Excavation
Excavator bucket width
 Excavated depth
 Soil removal, testing and stockpile
 Shape of trench
 Pockets for pipeline projections
 Thrust block preparation
 Dewatering
 Welding machine access
 Adjacent pipes

Trench Shields






When to use
Remove in stages
Affect on compaction
Geotextile fabric
Over excavation
Wide trench
Trench Shields
Laying and Jointing






Join on the bank and lay
Lay in trench and join
Rubber ring joints PVCU, PVC-M, PVC-O,
GRP, DICL & MSCL
Solvent welded jointsABS, PVC-U & PVC-M
Fusion butt weld-PE, PB
& PP
Electro-fusion
couplings-PE







Wrapped joints-GRP
Welded joints-steel
Flanges & Mechanical
Joints-All
Alignment & Bending
Adjacent parallel pipes
Crossing Pipelines
Removal of temporary
pegs and supports
Embedment & Compaction






Materials
Dewatering
Bedding
Side Support
Overlay
Migration of fines






Pipeline Protection
Prevention of
floatation
Compaction trials
Compaction controls
Deflection controls
Gauging
Thrust Blocks
Hydro-testing





Establish test
pressure
Test standard
Prepare test
equipment
Prepare ITP’s
Prepare test points





Source of test water
Disposal of test water
Selection of test
lengths
Owner’s witness
Records
Hydrotest Methods
Constant pressure test (No water loss) –
DICL, MSCL, GRP & PVC
 Constant pressure test (water loss) – PE,
ABS, PP & PB
 Pressure decay – PE & PB
 Pressure rebound- DN ≤ DN315 ABS, PB
& PE

Tips, Tricks & Traps
 Design
 Installation
 Testing
 Product
quality
 Completion
 In Service leaks
Tips, Tricks & Traps - Design
Design pressure may not include surge
 Temperature profile not defined
 Pipeline route/soils not adequately
surveyed
 Consultant expects sub contractor or
material supplier to do the detail design
 Lower pipe class than necessary specified
 Temporary facilities not designed

Tips, Tricks & Traps - Installation
Variations from
design not engineered
 Surfaces not cleaned
 Aged solvent cement
 Pipe ends bevelled
 Damaged pipe
 UV degradation

Physical damage
 Solvent damage to
internal surface
 Use of incorrect
solvent
 Incorrect slings
 Foreign matter not
removed from trench

Tips, Tricks & Traps - Installation





No detail drawings
Insufficient joints for
erection
Incomplete insertion
in joints
Inadequate time for
welds or lay ups
Differential
settlement







Resources
Poor trench
conditions
Poor native soil
Soil properties not
measured routinely
Inadequate access
Water ingress
Cleanliness
Tips, Tricks & Traps -Testing






Lack of planning &
procedure
Standard provisions
not understood
Inexperienced testers
Test pressure
unknown
Equipment not
isolated
Procedure not agreed
beforehand



Records of test not
prepared
Person to witness test not
available
Resources not available
–
–
–
–
–
–
Water supply
Pump
Gauges
Data logger
Temperature instrument
Trained personnel
Tips, Tricks & Traps -
Product Quality – Inspection or QA






Non conformance with drawings
Pipe ovality
Lining thickness
Socket dimensions
Surface defects
Fabricated fittings
– Cracks at weld
– Dimensions
– Orientation
Tips, Tricks & Traps -Completion
Resources & budget
 Site clean up
 Reinstatement
 Handover to owner
 Records
 Work as Executed Drawings
 Quality Assurance Sign-Off
 Certificate of Practical Completion

Tips, Tricks & Traps -
In Service Leaks & Failures






Pipe burst
Flanged joints leak
Solvent welds leak
Rubber ring joints
leak
Fusion welds leak
Fittings






Buckling of thin wall
pipe
Thrust blocks
Waterhammer
Over pressure
Pipe shear
Fatigue & vibration
Questions
1.
2.
3.
4.
Is AS 2566 mandatory?
Can AWWA M45 be used?
Is FEA a viable alternative?
Who designs pipelines Civil, structural or
mechanical engineers?